RESOLVED – That the Board: (i) Approve the progression of the Doncaster UTC project to full approval and award up to $£0.15m grant to Doncaster UTC subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix A to the report. (ii) Delegate authority to the Head of Paid Service, in conjunction with the S73 and the Monitoring Officer, to enter into the contractual arrangements required as a result of the above approval.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
This paper requests approval for Doncaster UTC’s scheme with an LGF grant value of £0.150m
Thematic Priority
• Facilitate and proactively support growth amongst existing firms • Develop the SCRs skills base, labour mobility and education performance • Secure investment in infrastructure where it will do most to support growth
Freedom of Information and Schedule 12A of the Local Government Act 1972
Under the Freedom of Information Act this paper and any appendices will be made available under the SCR Publication Scheme
Recommendations The Skills and Employment Thematic Board consider and approve: 1. Progression of ‘Doncaster UTC’ project to full approval and award of up to £0.150m grant to Doncaster UTC subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix A. 2. Delegated Authority to the Head of Paid of Service, in conjunction with the Section 73 and the Monitoring Officer, to enter into the contractual arrangements required as a result of the above approval.
1. Introduction
1.1The LEP Board (18th Aug 2018) approved that a £16.9m LGF Skills Capital Commissioning Call be launched inviting strategic business case submissions from interested applicants. The call specifically asked for projects that supported delivery of education and skills across science, technology, engineering and maths (STEM) with a focus on higher level skills in recognition of the strategic role such skills play in supporting growth in the region. On the 5th Nov 2018 the Strategic Business Case (SBC) submitted by Doncaster UTC for the scheme ‘Doncaster UTC’ was accepted by the LEP Board into the LGF programme. This paper requests approval for the Doncaster UTC scheme which has a total LGF value over all years of £0.150m.
2. Proposal and justification
2.1Doncaster UTC Doncaster UTC have requested £0.150m LGF grant to support a £0.750m scheme to purchase and install specialist equipment focused on robotics, physics, computing, and virtual reality at new site which specialises in Engineering and Creative and Digital Technologies opening in September 2020.
The full investment will allow the UTC to enhance their core curriculum based around STEM (science, technology, engineering and mathematics) and allow the college to place further emphasis on digital technologies. Over a period of 10 years the project is estimated to support 589 learners gross additional with an estimated 191 of the net additional learners moving into employment subsequently. This indicates a potential cost equivalent of £787 per job to SCR and is estimated to generate benefits of £6,737,779 of GVA. This project therefore offers good value for money for SCR, with a BCR of 48. Appendix A provides a summary of the scheme appraisal and the suggested conditions of award
3. Consideration of alternative approaches
3.1The project considered two other options in developing their business case. They made the case that with reduced or no LGF investment the UTC would not be able to deliver the digital technologies aspect of the curriculum. They made the case that the UTC would suffer reduced learner numbers in this scenario. The SCR investment is supported on the basis that it will allow the UTC to strengthen its digital technologies offering which will in turn enhance the student and employer engagement.
4. Implications
4.1Financial The total project costs are £0.750m, Doncaster UTC are proposing a contribution of £0.600m and seeking the remaining £0.150m funding from the Local Growth Fund. The project has been in the LGF pipeline since November 2018 and at the current level the project only has a very marginal effect on remaining LGF available.
4.2Legal The legal implications of each project have been fully considered by a representative of the Monitoring Officer and included in the recommendations agreed by the Appraisal Panel as presented in the supporting information.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow SCR - Skills & Employment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
SCR Renewal Action Plan ImplementationRESOLVED – That the Board: a) Note the update on the SCR Renewal Action Plan, including the update on work to better ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.