Quarter 1 Revenue & Capital Programme Report

Approved Committee 5 papers

Mayoral Combined Authority Board approved this item on Monday 23 September 2019. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

RESOLVED, that the MCA: 1. Notes the forecast underspend of c. £204k on the MCA/LEP Revenue Budget. 2. Notes the forecast spend on the MCA/LEP Revenue Programmes is to budget. 3. Notes the forecast overspend of c. £615k on the South Yorkshire Transport Revenue Budget. 4. Notes the changes to the South Yorkshire Transport Capital Programme. 5. Approves the budget variations in relation to staffing costs as contained within the report.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Mayoral Combined Authority Board

Purpose of report

This report provides the Q1 position for the revenue and capital programme of the Sheffield City Region (SCR) Mayoral Combined Authority (MCA) for the financial year 2019/20.

Thematic Priority

All

Freedom of Information and Schedule 12A of the Local Government Act 1972

The paper will be available under the Mayoral Combined Authority Publication Scheme

Recommendations

SCRMCA are asked to consider and note the 2019/20 Q1 position for the Mayoral Combined Authority’s revenue budget and capital programme, and in particular to:

1. Consider and Note the forecast underspend of c. £204k on the MCA/LEP Revenue Budget; 2. Consider and Note the forecast spend on the MCA/LEP Revenue Programmes is to budget; 3. Consider and Note the forecast overspend of c. £615k on the South Yorkshire Transport Revenue Budget; 4. Consider and Note the changes to the South Yorkshire Transport Capital Programme. 5. Consider and Note the budget variations requested in 2.6.

1. Introduction

1.1The Mayoral Combined Authority operates a number of revenue budgets, as well as capital and revenue programmes. This paper summarises the Q1 position of those budgets and programmes for the financial year 2019/20. 1.2 The report is structured to provide Members with an early indication of the forecast outturn position in relation to: • South Yorkshire Transport Revenue budget • MCA / LEP Revenue budget • Revenue Programme activity, and the • South Yorkshire Transport Capital Programme 1.3 A separate report is being presented to Members on progress on delivering the 2019/20 LGF capital programme.

1.4The approved budget in respect of the above revenue and capital programmes incorporate the budget variations to revenue programme activity already approved by the MCA up to and including 3 June 2019. 2. Proposal and justification

2.1The key issues regarding the financial performance of the SCRMCA are set out below. 2.2 South Yorkshire Transport Revenue Budget

The South Yorkshire Transport revenue budget as originally approved was £62.828m made up of £59.736m of SYPTE operational expenditure and SCRMCA transport revenue expenditure of £3.092m.

The current forecast is for a £138k overspend on the SCRMCA transport revenue budget and a £477k overspend on the SYPTE operational budget producing an overall overspend of £615k against the South Yorkshire transport revenue budget.

SYPTE officers are reviewing whether it may be possible to mitigate the forecast overspend with the release of at least some of the provision made for known risks made at 2018/19 year end.

See Appendix 1 for further detail. 2.3 MCA/LEP Revenue Budget

The revenue budget is deployed to cover the day-to-day activity of running the MCA and LEP in its delivery of the Strategic Economic Plan (SEP). Typical costs include staffing, accommodation, business support, international trade and investment marketing and the commissioning of specific pieces of work as part of implementing the SEP and developing the Local Industrial Strategy and work towards the Shared Prosperity Fund (SPF).

The 2019/20 Q1 outturn position on the core activities funded through the revenue budget is shown in the table below.

Variance Budget Outturn Variance % Expenditure £'000 £'000 £'000 £'000 Net Revenue Expenditure £6,506 £6,302 (£204) (3%) Non-specific Income (£6,506) (£6,506) £0 0% £0 (£204) (£204) (3%)

There is currently an anticipated underspend of £204k in net revenue expenditure. Further information on the revenue budget’s Q1 outturn position can be found in Appendix 2.

2.4Revenue Programme activity

Following the variations approved by the MCA on the 3 June 2019, as at Q1 all of the revenue programmes are forecast to spend to budget. The overall budget for revenue programmes in 2019/20 is now £9.724m.

See Appendix 3 for further detail.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
11 Appendix 1Appendix 505 KB Download
PDF
11 Appendix 2Appendix 483 KB Download
PDF
11 Appendix 3Appendix 405 KB Download
PDF
11 Appendix 4Appendix 533 KB Download
PDF
Quarter 1 Revenue & Capital Programme ReportReport 216 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 23 attended
MD
Mayor Dan JarvisChair, present
CR
Councillor Chris ReadVice-Chair, present
GP
Councillor Garry PurdyCommittee Member, present
JD
Councillor Julie DoreCommittee Member, present
MT
Councillor Martin Thacker MBECommittee Member, apologies, sent representative
MR
Mayor Ros JonesCommittee Member, present
SG
Councillor Simon GreavesCommittee Member, apologies
SS
Councillor Sir Steve Houghton CBECommittee Member, present
SF
Councillor Steve FritchleyCommittee Member, apologies
TG
Councillor Tricia GilbyCommittee Member, apologies
TT
Tim TaylorOfficer, in attendance
NB
Nigel BrewsterObserver, present

All 23 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Quarter 1 Revenue & Capital Programme ReportThis decision
  2. Quarter 2 Capital and Revenue Monitoring ReportDecided

More from South Yorkshire Mayoral Combined Authority Mayoral Combined Authority Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the meeting held on 14 July 2026RESOLVED that the minutes of the meeting held on 14 th July 2026 be approved. Approved Open
15 Sep 2026 South Yorkshire Strategy and Proposed Implementation ApproachRESOLVED that the Board endorses: 1. The South Yorkshire Strategy as the shared regional framework. 2. The proposed c... Agreed Open
15 Sep 2026 City Densification FundRESOLVED that the Board: 1. Notes the Government’s allocation of £85m of ing to South Yorkshire. 2. Endorses the prog... Agreed Open
15 Sep 2026 National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ... Noted Open
15 Sep 2026 Governance UpdateRESOLVED that the Board: 1. Notes the recommendation of the Overview & Scrutiny Committee at its meeting on 7th July ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies