Mayoral Combined Authority Board approved this item on Monday 23 September 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED, that the MCA: 1. Notes the change proposed to the existing contract ‘Upper Don Valley Flood Alleviation Scheme’ which re-profiles £2.3m LGF expenditure from 2019/20 to 2020/21 subject to the conditions referenced within the report. 2. Delegates authority to the Head of Paid of Service, in conjunction with the Section 73 Officer and the Monitoring Officer, to enter into the contractual arrangements required as a result of the above approval 3. Notes the pending submission of the ‘A630: Parkway Widening’ Business Case to the DfT.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
The paper requests approval of one LGF change request for Upper Don Valley and provides an update on the retained major project ‘A630: Parkway Widening’ whose Business Case is due to be submitted to Department of Transport (DfT) in October 2019.
Thematic Priority
To secure investment in infrastructure where it will do most to support growth.
Freedom of Information and Schedule 12A of the Local Government Act 1972
The paper will be available under the Combined Authority Publication Scheme
Recommendations
The SCR MCA consider and approve: 1. The change proposed to the existing contract ‘Upper Don Valley Flood Alleviation Scheme’ which re-profiles £2.3m LGF expenditure from 2019/20 to 2020/21 subject to the conditions set out in this paper. 2. Delegated Authority to the Head of Paid of Service, in conjunction with the Section 73 Officer and the Monitoring Officer, to enter into the contractual arrangements required as a result of the above approval. The SCR MCA to note:
1. The submission of the retained major ‘A630: Sheffield Parkway Widening’ full business case to DfT for formal appraisal. On satisfactory conclusion of the DfT appraisal the ringfenced £40.5m SCR MCA will be asked to enter into contractual arrangements as a result of the approval at a future meeting.
1. Introduction
1.1The SCR LGF Programme has a total value of £378m of which £304m is already contracted and partially delivered. This paper requests approval to a change proposed in an existing contracted project, ‘Upper Don Valley: Flood Alleviation’.
1.2£40.5m of the remaining £74m is ringfenced for the retained major transport project ‘A630: Parkway Widening’ and this paper updates on progress towards scheme approval and contract. 2. Proposal and justification
2.1Upper Don Valley Flood Alleviation Scheme
The Upper Don Valley Flood Alleviation grant was approved by the MCA on11th June 2018 to manage flood risk in the strategically important Upper Don Valley, which in itself is part of a wider programme to protect the city.
The project experienced delays in securing match funding to enable the scheme to proceed and as a result has proposed a slippage in expenditure. The existing and proposed funding profile is detailed in the table below:
The change request is recommended for approval subject to the following conditions:
1. Enhanced monthly monitoring including; 2. Sheffield City Council to provide procurement milestones; and 3. Sheffield City Council to provide a formal works programme upon appointment of the contractor.
The SCR MCA are asked to approve the change request so that a revised funding agreement can be entered into.
2.2Parkway Widening
£40.5m of the Local Growth Fund (LGF) allocated to SCR is ringfenced to deliver the A630 Parkway widening scheme, which aims to increase the capacity of the Parkway and J33 of the M1. This is a “retained major” transport project which means that DfT will undertake appraisal of the project business case rather than the SCR Assurance Team and the decision to approve the project and grant funding has been retained by DfT.
A Full Business Case (FBC) is to be submitted to DfT on 15th October 2019 and the scheme promoter is now preparing the final draft. The SCR Executive team is working alongside the scheme promoter as a critical friend to review the business case and finalise the submission in line with government requirements.
At the time of writing, the final tender price is still awaited and hence the final benefit to cost ratio (BCR) cannot yet be confirmed. The need to submit the FBC in October is based on a programme requirement to provide DfT with a suitable assessment window prior to potential approval before the Christmas break. This enables works to commence on site early 2020 and for the scheme to open to traffic in August 2021.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.