SCR - Infrastructure Board noted this item on Thursday 24 October 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, that the contents of the report are noted.
This paper and accompanying performance dashboard provide board members with up to date performance information on the Infrastructure programme delivered on behalf of the LEP and MCA
Thematic Priority Secure investment in infrastructure where it will do most to support growth.
Freedom of Information
This paper is not exempt from FOI requests and will be published in line with the Combined Authority Publication Scheme.
The Board are asked to:
1. Scrutinise the performance information provided in order to identify future performance deep- dives or significant areas of risk.
1. Introduction
1.1Performance dashboards for the Infrastructure programme of the LEP and MCA are attached for members to review
2. Proposal and justification
2.1The following is a summary of performance by programme.
2.2Infrastructure
Further programme detail is provided in Appendix 1a A full performance dashboard is provided at Appendix 1b
The Infrastructure programme is now in the fourth year of a 5-year initiative to grow the economy in the Sheffield City Region and the schemes within the programme are continuing to deliver and contribute to the outputs/outcomes required to support the overarching goals of the Strategic Economic Plan 2015-2025.
The Strategic Economic Plan 2015-2025 valued the package offered by the SCR Infrastructure programme at £596m, and SCR asked for a 36% match funding contribution from government, a minimum £217m for the period 2015-2021 with £29.2m in 2015/2016.
The SCR is continuing to work, secure and accelerate the delivery of the Infrastructure package of investment that currently comprises of 53 schemes, Table 1 shows the status of each in terms of their position within the SCR assurance framework together with the total value of SCR Local Growth Fund attributed to each.
Table 1: Scheme Status Status No. of Schemes £ LGF Fund Value (Baseline) Complete 24 £99,144,818 In Delivery 21 £96,368,888 Pending Contract 2 £8,495,372 Pipeline 6 £23,145,228 Total 53 £227,154,306
Performance Summary
The Strategic Economic Plan 2015-2025 stated that the SCRIF Programme was forecast to return benefits with 24,000 associated jobs contributing to the overall growth deal target of 70,000 and unlocking the delivery of over 14,000 houses.
Outputs/ Outcome
Table 2 illustrates how the Infrastructure Programme outputs/ outcomes are currently performing based on the Q1 2019/20 performance reports returned by the Scheme Promotors. The baseline figure is taken from figures defined in a either a business case or part of the contracted funding agreement.
Table 2 Output/Outcome Performance Outputs/Outcome Baseline Actual to Date Jobs Created: 45,570 4,014 Housing Units 9301 403 Newly Built Road (km) 13 9 Commercial Floorspace (m2) 1,628,508 71870 Reduced Flooding (m2) 23,588 2,581
Management Action
There is one project which is identified as high risk because wider works set out in the contract will not be completed. Discussions are ongoing with the project sponsor with a view to receiving a proposed contract change for consideration. Seven projects have amber risks including potential cost overruns and delayed or non-delivery. Close monitoring of risks and issues takes place and discussions are ongoing with all project partners about whether activity can conclude within the LGF Programme window or whether projects should be deferred until additional funding becomes available. A wide evaluation to appraise the viability of schemes is underway, with outcomes expected to be reported and agreed at the November LEP Board.
3. Consideration of alternative approaches
3.1The Performance Dashboard is the first iteration of data for the Thematic Boards and reflects the feedback taken from the meeting. Members can shape how the dashboard looks and the data and information included to fulfil their remit for performance management. 4. Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Infrastructure Programme SummaryAppendix 1a | 638 KB | Download |
PDF |
Infrastructure DashboardAppendix 1b | 103 KB | Download |
PDF |
LGF Infrastructure Performance DashboardReport | 99 KB | DownloadRead as text |
Follow SCR - Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2020 | Minutes of the Previous MeetingThat the minutes of the previous meeting held on 2 July 2020 be agreed as a true record. | Agreed | Open |
| 3 Sep 2020 | Getting SCR BuildingRESOLVED – That the report be noted. | Noted | Open |
| 3 Sep 2020 | SCR Renewal Action Plan ImplementationRESOLVED – That the report be noted. | Noted | Open |
| 3 Sep 2020 | GatewayEast Economic BlueprintRESOLVED – That the Board endorse the GatewayEast Economic Blueprint and the progression of the workstreams identified. | Decided | Open |
| 3 Sep 2020 | Infrastructure Delivery Plan DashboardRESOLVED – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.