Resolved
RESOLVED, that the Board: Notes the scale of the pipeline and actions in progress to address the overprogramming position. Notes the need to maximise claims at Q2 ahead of the annual performance review.
SCR - Infrastructure Board decided this item on Thursday 24 October 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, that the Board: Notes the scale of the pipeline and actions in progress to address the overprogramming position. Notes the need to maximise claims at Q2 ahead of the annual performance review.
This paper provides members with an update relating to the current LFG programme commitments and the scale of projects in the over-programmed pipeline
Thematic Priority
Cross cutting theme
Freedom of Information
The paper will be available under the SCR Publication Scheme
The Board is asked to:
1. Consider and note the scale of the pipeline and actions in progress to address the over- programming position.
2. Note the need to maximise claims at Q2 ahead of the annual performance review.
1. Introduction
1.1LGF is a 6 year, £360m funding programme secured through three rounds of Local Growth Fund bids. 2019/20 is the fifth and penultimate year of funding. Some investment made in the early years of the programme have now repaid loan funding back to the programme which has increased the total value of available programme funding to £378m
1.2In the first four years of delivery £239m has been spent (defrayed). A further £49m is committed to projects currently in contract and a further £19m has been approved for projects which are in the process of satisfying contract conditions. The total combined value of approved projects and spend to date is therefore £307m.
1.3The LGF grant allocation includes a ringfenced amount of £40.5m for a major transport project which is retained for separate approval by the DfT, this funding cannot be utilised for other projects 1.4 The level of funding remaining available for LGF projects across all thematic areas (the programme headroom) is now £30.2m. 1.5 All funding needs to be fully spent (defrayed) by 31st March 2021.
2. Proposal and justification
2.1When the 2019/20 budget was approved by the MCA in March 2019 the pipeline of projects indicated that there was potential over-programming of up to £24.4m.
As projects have developed some cost estimates have increased and a number of new projects have come forward seeking funding. As a result of these changes the current combined value of projects in the pipeline (including the retained major) has increased to £120.5m this equates to £80m excluding the retained major and therefore the potential over-programming has now increased to £49.8m.
This calculation includes a number of new inward investment projects.
2.2The current profile of project approvals and the remaining pipeline is set out below by theme;
Executive Approved Pipeline Total Comments Board Business £46m £42.5m £88.5m This is £36.5m above the Growth notional allocation and it is unlikely that all projects will land in the region or be able to complete works by 31st March 2021. This also includes the latest inward investment schemes which have yet to be accepted to the programme. Housing £10.0m £1.35m £11.35m £4.05m of the £10m housing funding is currently committed to schemes, the remaining £6m is held in the housing fund for pipeline schemes. Infrastructure £199.3m £20.1m £219.4m This includes several highways schemes designed to unlock development space for employment and housing Skills and £18.3m £7.5m £25.8m This is £2.2m below the notional Employment allocation and it is unlike that all projects will be able to complete works by 31st March 2021. Transport £28.5m £49m £77.5m This includes the £40.5m retained major transport project. Total £302.1m £120.5m £422.6m
This shows that the total request for project funding is £423 m. There is a £5.1m corporate commitment which covers the costs associated with carrying out the accountable body functions for the LGF programme. The total spend requirement is therefore £428m.
2.3It will not be possible to approve all the projects currently seeking funding based on the current programme, and continuing to approve schemes as they become ready, the programme could be fully committed by the January cycle, although this full commitment point has slipped throughout the year so far. 2.4 The LEP Board in September considered a range of options to address the over programming position and agreed to 3 actions;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Project listsAppendix A | 378 KB | Download |
PDF |
Local Growth Fund UpdateReport | 114 KB | DownloadRead as text |
Follow SCR - Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2020 | Minutes of the Previous MeetingThat the minutes of the previous meeting held on 2 July 2020 be agreed as a true record. | Agreed | Open |
| 3 Sep 2020 | Getting SCR BuildingRESOLVED – That the report be noted. | Noted | Open |
| 3 Sep 2020 | SCR Renewal Action Plan ImplementationRESOLVED – That the report be noted. | Noted | Open |
| 3 Sep 2020 | GatewayEast Economic BlueprintRESOLVED – That the Board endorse the GatewayEast Economic Blueprint and the progression of the workstreams identified. | Decided | Open |
| 3 Sep 2020 | Infrastructure Delivery Plan DashboardRESOLVED – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.