Resolved
RESOLVED – That the Housing and Infrastructure Board noted and commented on the workstreams being undertaken to prepare the South Yorkshire Flood Catchment Plan.
MCA - Housing and Infrastructure Board noted this item on Tuesday 22 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Housing and Infrastructure Board noted and commented on the workstreams being undertaken to prepare the South Yorkshire Flood Catchment Plan.
Housing and Infrastructure Board
22 June 2021
South Yorkshire Flood Catchment Plan Update
Is the paper exempt from the press No and public?
Reason why exempt: Not applicable
Purpose of this report: Discussion
Funding Stream: Not applicable
Is this a Key Decision No
Has it been included on the Forward Not a Key Decision Plan?
Director Approving Submission of the Report: Martin Swales, Interim Director of Transport, Housing and Infrastructure
Report Author(s): Colin Blackburn [email removed]
Executive Summary: An update on ongoing work and themes informing the preparation of the South Yorkshire Flood Catchment Plan
What does this mean for businesses, people and places in South Yorkshire? The Catchment Plan could help identify and secure additional funding and investment that will reduce flood risk to homes and businesses, as well as improving the resilience of places to future flooding.
Recommendations: • To note and comment on the workstreams being undertaken to prepare the South Yorkshire Flood Catchment Plan
Consideration by any other Board, Committee, Assurance or Advisory Panel N/A 1. Background
1.1Following the 2019 flood event in South Yorkshire, Mayor Dan Jarvis and Local Authority Leaders submitted a South Yorkshire Business and Infrastructure Resilience Priority Flood Programme to Government, which included the proposal to prepare a catchment wide flood plan covering the whole of South Yorkshire.
1.2The aim of this proposal was to develop a new more effective and integrated collaborative approach to future flood policy and investment, by taking a holistic ‘South Yorkshire’ approach embracing all rivers and watercourses rather than continuing to consider flood policy and investments in a largely piecemeal way.
1.3This approach was considered to offer the opportunity to both maximise funding opportunities and lead to more effective outcomes in terms of protecting homes and businesses from flooding in the future. It would also enable the potential future impacts of climate change to be taken into account and understand better the contribution that Natural Flood Management could play in building resilience to, and reducing, future flooding.
1.4Initial work has begun to prepare the Draft Catchment Plan and the emerging workstreams and themes are presented for the Board’s consideration.
2. Key Issues
2.1The attached presentation at Appendix A provides an update on progress in preparing the South Yorkshire Catchment Plan. A steering group has been established to oversee the preparation pf the Plan comprising of senior officers from the MCA Executive, Environment Agency, four South Yorkshire Authorities, and Yorkshire Water. The outputs of the work of the Group are reported to both this Board and the South Yorkshire Flood Risk Partnership which are jointly overseeing the preparation of the Plan.
2.2There are several purposes of the Plan as set out in the presentation, and the aim is for it to be a ‘living document’ to facilitate the development of a long term strategy for flood risk management and climate resilience. This will enable partners and communities to incorporate emerging data, knowledge and opportunities to continue to build and shape the Plan over time. Importantly, the programme arising from the Plan will provide a clear programme of well developed projects to secure the remaining investment that is required to alleviate and mitigate future flooding.
2.3The preparation work is set around four key workstream themes, with one local authority leading on each of one of themes:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
South Yorkshire Catchment Plan Update PresentationAppendix A | 1.6 MB | Download |
PDF |
South Yorkshire Flood Catchment Plan UpdateReport | 133 KB | DownloadRead as text |
Follow MCA - Housing and Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2023 | Minutes of Previous MeetingRESOLVED that the minutes of the previous meeting held on 8 February 2023 be approved. | Approved | Open |
| 16 Mar 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
| 16 Mar 2023 | Programme ApprovalsRESOLVED that the Board: Approve £3m grant award to Sheffield City Council for the “West Bar” project. Approve £1.3m ... | Approved | Open |
| 8 Feb 2023 | Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on 8 December 2022 be approved. | Approved | Open |
| 8 Feb 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.