Resolved
RESOLVED – That the Board noted the emerging draft South Yorkshire Flood Catchment Plan.
MCA - Housing and Infrastructure Board noted this item on Tuesday 26 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Board noted the emerging draft South Yorkshire Flood Catchment Plan.
Appendix A
Connected by Water Catchment Plan (Name TBC) FRONT PAGE – Connected by Water Logo, plus strapline, plus all organisations logos (EA, SYMCA, 4 Councils, YW). Insert a range of photos from around South Yorkshire ADD CONTENTS PAGE
1 Why is a plan needed? The flooding in November 2019 provided the catalyst for the creation of the Connected by Water Catchment Plan. One of the wettest Autumns on record led to unprecedented river levels, and widespread flooding across South Yorkshire. Communities were evacuated from their homes, precious belongings destroyed or ruined, businesses devastated, infrastructure severely disrupted and people unable to return to their homes for many months. As the flood water subsided, communities, businesses and senior leaders resolutely agreed that we need to work together to reduce the risk and impact of flooding in our region. However, the stark reality is that climate change is leading to wetter winters with more intense rainfall. It will also lead to sea level rise. Both factors will increase the risk of flooding from the rivers, surface water and the public sewer network across South Yorkshire. If we are to meet this challenge, and reduce both the risk and impact of flooding in the future, we cannot stand still. Unless we do more, our communities will struggle to cope with the increasingly catastrophic impacts of more frequent and severe floods. The region was devastated by flooding back in 2007, and much work has been done since then to better protect communities across South Yorkshire. However, the shock of the events of 2019, together with the stark reality of climate change, have galvanised a South Yorkshire wide alliance of partners, Connected by Water, who are determined to explore all measures to both adapt to and mitigate climate change in our region. Since November 2019, we have been working together, not only to deliver flood risk management schemes on the ground, but also to plan catchment wide measures for the future to help us meet the challenges that climate change will present us. This plan is one of the products of this collaboration. The Connected by Water Catchment Plan outlines the actions we will take in South Yorkshire to reduce the risk of flooding and develop more resilient communities who can adapt to the future impacts of climate change. The landscapes and rivers which make South Yorkshire vulnerable to flooding, are also one of its most precious assets. South Yorkshire covers largely the same geography as the catchment for the River Don. The uplands of the River Porter, Rivelin, Loxley in Sheffield, and in the River Dearne in Barnsley, give us beautiful moorland landscapes. These uplands lead into wetland nature reserves along the Dearne and Rother in Barnsley and Rotherham and on to nationally significant lowland peat around the Lower Don in Doncaster. Add map / image / artwork of area plan covers – could also be on inside of front cover potentially? There is exciting potential to restore and develop these natural landscapes to slow and store water, help nature recover, and provide wildlife-rich environments for people to thrive in. Nature-based solutions form a key element of this catchment plan. These measures will not only reduce flood risk, but will mitigate climate change and restore nature by storing carbon and protecting the environment that we all love and depend on. This plan is a ‘living plan’. We do not know all the answers. This plan is just the start. We will continue to incorporate emerging data, knowledge and opportunities so that we build and shape the plan in the coming months and years. It will evolve and change as we find out more and develop actions as a partnership.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft South Yorkshire Catchment PlanReport | 700 KB | DownloadRead as text |
PDF |
South Yorkshire Flood Catchment Plan UpdateReport | 161 KB | Download |
Follow MCA - Housing and Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2023 | Minutes of Previous MeetingRESOLVED that the minutes of the previous meeting held on 8 February 2023 be approved. | Approved | Open |
| 16 Mar 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
| 16 Mar 2023 | Programme ApprovalsRESOLVED that the Board: Approve £3m grant award to Sheffield City Council for the “West Bar” project. Approve £1.3m ... | Approved | Open |
| 8 Feb 2023 | Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on 8 December 2022 be approved. | Approved | Open |
| 8 Feb 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.