MCA - Housing and Infrastructure Board approved this item on Tuesday 26 October 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the Board approve: i ) Full approval and award of £0.25m grant for the ‘BHF Revenue Project’ to South Yorkshire Mayoral Combined Authority (SYMCA). ii) Progression of ‘Adwick Depot’ project to proceed to Full Business Case (FBC) for Brownfield Housing Funding (BHF) to Doncaster Metropolitan Council (DMBC) subject to the conditions set out in the Assurance Summary attached at Appendix A. iii) Progression of ‘Attercliffe Waterside’ project to proceed to FBC for BHF to Sheffield City Council (SCC) subject to the conditions set out in the Assurance Summary attached at Appendix B. iv) Progression of ‘Park Hill Phase 4’ project to SYMCA to proceed to FBC for BHF to SCC subject to the conditions set out in the Assurance Summary attached at Appendix C and discussions around the possibility of increasing the social housing content. v) Progression of ‘Nightingale School’ project to proceed to FBC for BHF to DMBC subject to the conditions set out in the Assurance Summary attached at Appendix D. vi) Progression of ‘Small Sites’ project to proceed to FBC for BHF to DMBC subject to the conditions set out in the Assurance Summary attached at Appendix E. vii) Approval of the changes to the Getting Building Fund project ‘Barnsley College Digital Sci-Tech Building’. viii) Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes 1-7 covered above.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Programme Approvals Is the paper exempt from the press No and public?
Purpose of this report: Funding Decision
Is this a Key Decision? Yes
Has it been included on the Yes Forward Plan?
Director Approving Submission of the Report: Gareth Sutton, Chief Finance Officer/s73 Officer
Report Author(s): Carl Howard – Senior Programme Manager [email removed]
Executive Summary This paper requests approval of one scheme subject to conditions set out in the Assurance Panel Summary. The paper also requests progression of five schemes to develop Full Business Cases (FBCs). One change request is presented for agreement.
What does this mean for businesses, people and places in South Yorkshire? This report is seeking approval to progress business cases and enter into contract for a number of investment proposals which will support the Mayoral Combined Authority’s (MCA’s) aspirations.
Recommendations The Board consider and approve:
1. Full approval and award of £0.25m grant for the “BHF Revenue Project” to SYMCA (South Yorkshire Mayoral Combined Authority); 2. Progression of “Adwick Depot” project to proceed to FBC (Full Business Case) for BHF (Brownfield Housing Funding) to DMBC (Doncaster Metropolitan Borough Council) subject to the conditions set out in the Assurance Summary attached at Appendix A 3. Progression of “Attercliffe Waterside” project to proceed to FBC (Full Business Case) for BHF (Brownfield Housing Funding) to SCC (Sheffield City Council) subject to the conditions set out in the Assurance Summary attached at Appendix B 4. Progression of “Park Hill Phase 4” project to MCA to proceed to FBC (Full Business Case) for BHF (Brownfield Housing Funding) to SCC (Sheffield City Council) subject to the conditions set out in the Assurance Summary attached at Appendix C 5. Progression of “Nightingale School” project to proceed to FBC (Full Business Case) for BHF (Brownfield Housing Funding) to DMBC (Doncaster Metropolitan Borough Council) subject to the conditions set out in the Assurance Summary attached at Appendix D 6. Progression of “Small Sites” project to proceed to FBC (Full Business Case) for BHF (Brownfield Housing Funding) to DMBC (Doncaster Metropolitan Borough Council) subject to the conditions set out in the Assurance Summary attached at Appendix E 7. Approval of the changes to the GBF (Getting Building Fund) project “Barnsley College Digital Sci-Tech Building”. 8. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes 1 – 7 covered above.
Consideration by any other Board, Committee, Assurance or Advisory Panel Assurance Panel 01 October 2021 Assurance Panel 11 October 2021
1. Proposals and Justification
1.1This report seeks approval and progression for schemes funded from BHF. The paper also requests one project change to an existing GBF contract to allow a small time extension. The paper requests delegated authority to enter into legal agreement.
The MCA received confirmation of £40.34m BHF award in December 2020 with the aim of creating more homes by bringing more brownfield land into development. The Fund aims to ease viability issues that brownfield projects face alongside wider interventions aimed at economic development. There is a target of £20m spend to be achieved by March 31st 2022.
1.2In June 2020 the MCA was awarded £33.6m GBF to invest in ‘shovel-ready’ projects that will provide stimulus to local economies. The funds need to be defrayed by 31st March 2022 which allows an 18-month delivery window.
1.3Progression of activity to full approval and award of funding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Housing and Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.