Resolved
RESOLVED – That the Board note progress on the work required to take forward the CRSTS submission including the requirement to seek further information from all project sponsors and for completion of this within short timescales.
MCA - Transport and the Environment Board decided this item on Thursday 16 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Board note progress on the work required to take forward the CRSTS submission including the requirement to seek further information from all project sponsors and for completion of this within short timescales.
Transport and the Environment Board
16 December 2021
City Region Sustainable Transport Settlement Is the paper exempt from the press No and public?
Purpose of this report: Discussion
Is this a Key Decision? No
Has it been included on the Not a Key Decision Forward Plan?
Director Approving Submission of the Report: Martin Swales, Interim Director of Transport, Housing and Infrastructure
Report Author(s): Alex Linton – LTP Programme Manager [email removed]
Executive Summary This report presents an update on the status of the City Region Sustainable Transport Settlement (CRSTS) and the next steps needed to meet Department for Transport (DfT) requirements.
What does this mean for businesses, people and places in South Yorkshire? The CRSTS settlement will provide the vast majority of local transport funding for SYMCA for the next five years and therefore is essential in delivering an efficient and effective transport system and networks to enable reliable movement of people and goods around the region for all purposes.
Recommendations The Board are asked to note progress on the work required to take forward the CRSTS submission including the requirement to seek further information from all project sponsors and for completion of this within short timescales.
Consideration by any other Board, Committee, Assurance or Advisory Panel None 1. Background
1.1The Government Spending Review included announcements regarding a number of transport funding streams for SYMCA, including the CRSTS provisional award of £570m for the five-year settlement period April 2022 to March 2027.
1.2Following the award announcement the Mayoral Combined Authority (MCA) Executive Team has met with Treasury (HMT) and DfT on a number of occasions to discuss next stage requirements. SYMCA is now required to submit a programme level Business Case by mid-January 2022 before the award is formally confirmed in March.
2. Key Issues
2.1As previously advised to Board, the total CRSTS bid submitted by SYMCA to DfT was £660m. We were also required to submit a lower bound proposal for £400m. The award of £570m was therefore a very positive outcome. This provisional allocation was announced as part of the Government Spending Review and a programme level Business Case - based on the £570m allocation – is now required for assessment by HMT and DfT.
2.2This advice has now been confirmed in writing through a letter from the Secretary of State for Transport to Mayor Jarvis. The letter re-confirmed the level of allocation and outlined DfT expectations for the business case submission process and programme content.
2.3DfT have identified some conditions and specific projects that will be scrutinised in more detail within the business case process. Additionally, individual scheme sign off from DfT will be required for any schemes with a value greater than £50m, anything with a delivery period extending beyond March 2027 and any scheme that potentially carries a revenue risk to the department or other Government funded sources. They have also named schemes within the South Yorkshire programme for which they will require further justification. These are primarily the larger road-based and rail schemes with concerns being centred around the fit with Government’s programme objectives of sustainable transport and also future demand for some of the schemes. The scheme sponsors are supporting further development work.
2.4The CRSTS guidance also clearly indicates that Mayors of recipient MCA’s will be held far more accountable for performance against these funds and be required to publish delivery progress. It is also expected that a ‘Leaderboard of MCA performance’ will be produced to further demonstrate Authority standards. This further emphasises the importance of setting deliverable and achievable project targets when setting out the profile and forecast for the programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
City Region Sustainable Transport SettlementReport | 144 KB | DownloadRead as text |
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Mar 2023 | Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na... | Approved | Open |
| 17 Mar 2023 | Minutes of the Last MeetingRESOLVED that the minutes of the meeting held on 9 February be approved. | Approved | Open |
| 17 Mar 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
| 17 Mar 2023 | Transport UpdateRESOLVED that the Transport Update be noted. | Noted | Open |
| 17 Mar 2023 | Bus Recovery Grant ExtensionRESOLVED that Transport and Environment Board members: Note the recent funding extension by DfT of Bus Recovery Grant... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.