MCA - Transport and the Environment Board approved this item on Thursday 16 December 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED - That the Board approve: (i) Progression of ‘T27 South Yorkshire Rail Station Improvements’ to MCA for full approval and award of £3.45m grant from Transforming Cities Fund to South Yorkshire Passenger Transport Executive subject to the conditions set out in the Assurance Summary attached at Appendix A1. (ii) Progression of ‘O43 Goldthorpe Station Access’ to full approval and award of £0.55m grant from Active Travel Fund 2/Gainshare to Barnsley Metropolitan Council subject to the conditions set out in the Assurance Summary attached at Appendix A2. (iii) Progression of ‘O44 Elsecar Station Access’ to full approval and award £0.58m grant from ATF2/Gainshare to BMBC subject to the conditions set out in the Assurance Summary attached at Appendix A3. (iv) Progression of ‘O46 Warmsworth to Conisbrough Active Travel Link’ to full approval and award of £1.0m grant from ATF2/Gainshare to DMBC subject to the conditions set out in the Assurance Summary attached at Appendix A4. (v) Progression of ‘D31 Community Transport Electric Minibus’ SBC for approval to proceed to FBC for Gainshare funding to SYPTE subject to the conditions set out in the Assurance Summary attached at Appendix B1. (vi) Progression of ‘T5 A631 Rotherham to Maltby Bus Corridor’ OBC to proceed to FBC for ATF/Gainshare funding to RMBC subject to the conditions set out in the Assurance Summary attached at Appendix B2. (vii) Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes covered in ii) to iv) above subject to funding being available.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Report to MCA - Transport and the Environment Board
Executive summary
This paper requests full approval of 4 schemes and progression of 2 schemes from Strategic Business Case (SBC) and Outline Business Case (OBC) to Full Business Case (FBC), subject to the conditions set out in the Assurance Summaries. The paper also requests delegated authority to enter into necessary legal agreements for the schemes
What does this mean for businesses, people and places in South Yorkshire? This report is seeking approval to progress business cases and enter into contract for a number of investment proposals which will support the MCA’s aspirations.
Recommendations The Board consider and approve: 1. Progression of “T27 South Yorkshire Rail Station Improvements” to MCA for full approval and award of £3.45m grant from Transforming Cities Fund (TCF2) to South Yorkshire Passenger Transport Executive (SYPTE) subject to the conditions set out in the Assurance Summary attached at Appendix A1; 2. Progression of ‘O43 Goldthorpe Station Access’ to full approval and award of £0.55m grant from Active Travel Fund 2/Gainshare (ATF2/Gainshare) to Barnsley Metropolitan Borough Council (BMBC) subject to the conditions set out in the Assurance Summary attached at Appendix A2; 3. Progression of ‘O44 Elsecar Station Access’ to full approval and award of £0.58m grant from ATF2/Gainshare to BMBC subject to the conditions set out in the Assurance Summary attached at Appendix A3; 4. Progression of ‘O46 Warmsworth to Conisbrough Active Travel Link” to full approval and award of £1.0m grant from ATF2/Gainshare to DMBC subject to the conditions set out in the Assurance Summary attached at Appendix A4; 5. Progression of “D31 Community Transport Electric Minibus” Strategic Business Case (SBC) for approval to proceed to Full Business Case (FBC) for Gainshare funding to SYPTE subject to the conditions set out in the Assurance Summary attached at Appendix B1; 6. Progression of “T5 A631 Rotherham to Maltby Bus Corridor” Outline Business Case (OBC) to proceed to FBC for ATF/Gainshare funding to RMBC subject to the conditions set out in the Assurance Summary attached at B2; and, 7. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes covered at 2-4 above subject to funding being available.
Consideration by any other Board, Committee, Assurance or Advisory Panel Assurance Panel 25 October 2021 Assurance Panel 08 November 2021 Assurance Panel 22 November 2021 Assurance Panel 06 December 2021
Background
1.1This report seeks approval for the progression of schemes funded from multiple funding streams. The paper also requests delegated authority to enter into legal agreements for the named schemes.
1.2Progression of schemes to full approval and award of funding
The paper is seeking progression to full approval and award of funding for 3 projects and progression to the MCA – due to the value exceeding the Board’s delegation limits - for one scheme with a recommendation to approve. The schemes are detailed in Appendix A. The total amount of funding requested is £5.38m grant; £3.45m from the TCF2 and £2.13m from the ATF2 fund and previously committed Gainshare. The projects are located across Barnsley and Doncaster. The assurance summaries include conditions of funding which must be met before contract execution.
Full details of the schemes and risks are included in Appendix A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies