Brownfield Housing Fund New Schemes - Project Mandates

Approved Committee 3 papers

MCA - Housing and Infrastructure Board approved this item on Wednesday 31 August 2022. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

RESOLVED that the Board advise the approval of the two schemes listed in Sections 2.2 and 2.3 being accepted onto the BHF Phase 3 Pipeline.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to MCA - Housing and Infrastructure Board

Housing and Infrastructure Board

31 August 2022

Brownfield Housing Fund New Pipeline Schemes

Is the paper exempt from the press No and public?

Purpose of this report: Policy Decision

Is this a Key Decision? No

Has it been included on the No Forward Plan?

Director Approving Submission of the Report: John Dowie, Executive Director of Infrastructure and Place (Interim)

Report Author(s): Becky Guthrie [email protected]

Colin Blackburn [email protected]

Executive Summary To seek approval to add two new schemes onto the Brownfield Housing Fund (BHF) Phase 3 Pipeline for funding and delivery by end March 2025.

What does this mean for businesses, people and places in South Yorkshire? The purpose of the BHF is to unlock development on brownfield land, delivering additional housing units that otherwise would not come forward. The creation of additional, quality housing alleviates pressure on the existing housing stock and helps to maintain affordability in the region. The BHF leverages other public and private sector investment, creating growth, jobs and skills opportunities for the people of South Yorkshire.

Recommendations The Board is asked to approve the two schemes listed in Sections 2.2 and 2.3 being accepted onto the BHF Phase 3 Pipeline. Consideration by any other Board, Committee, Assurance or Advisory Panel SYMCA Management Board 16th August 2022 1. Background

1.1In June 2020, the Government launched ‘A New Deal for Britain’ which is a key part of the Government’s Strategy to rebuild Britain following Covid 19 and support the economic recovery across the UK. As part of this strategy, £40.3m of capital funding was allocated to the South Yorkshire Mayoral Combined Authority (SYMCA) for supporting the development of housing schemes on brownfield land. SYMCA has subsequently been awarded a further £13m as part of the Levelling Up agenda making a total of £53m which needs to be spent by end March 2025.

1.2This report proposes two new schemes to add onto the BHF Phase 3 Pipeline. These two schemes are recommended to the Board for acceptance onto the BHF Phase 3 Pipeline by the MCA Management Board in accordance with the MCA Assurance Framework.

2. Proposals and Justification

2.1Brownfield Housing Fund Phase 3 Pipeline Approvals The proposed new schemes to be added onto the BHF Phase 3 Pipeline are summarised below, with the details of each set out in the attached Project Mandate forms for each of the schemes. These have been brought forward from the ‘Pending Pipeline’ following further development work by the local authority.

2.2Gleadless Valley- Gaunt Road Scheme, Sheffield This scheme would deliver 30 affordable homes. The project is part of the Gleadless Valley masterplan delivering a potential rehousing option for later phases of remodelling / redevelopment across Gleadless Valley. BHF grant is being requested to fill a viability gap for this scheme.

Estimated BHF ‘ask’ of c£900k; Intervention Rate of c£30k per housing unit (see Section 6 below regarding the above average intervention rate). Start on Site is anticipated to be March 2023.

2.3Gleadless Valley- Hemsworth OPIL Scheme, Sheffield This scheme would deliver 81 specialist older persons living units. The project is part of the Gleadless Valley masterplan delivering a potential rehousing option for later phases of remodelling / redevelopment across Gleadless Valley. BHF grant is being requested to fill a viability gap for this scheme.

Estimated BHF ‘ask’ of c£894k; Intervention Rate of c£11k per housing unit; Start on Site is anticipated to be April 2023.

3. Options Considered and Recommended Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SIP Gaunt_PM FormAppendix A 1.1 MB Download
PDF
SIP Hemsworth _PM FormAppendix B 1.1 MB Download
PDF
Brownfield Housing Fund New Schemes: Project MandatesReport 501 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 12 attended
TF
Councillor Terry FoxCo-Chair, present
GS
Gemma SmithCo-Chair, apologies
AB
Councillor Amy BrookesCommittee Member, apologies
RF
Councillor Robert FrostCommittee Member, present
DJ
Councillor Douglas JohnsonCommittee Member, present
GJ
Councillor Glyn JonesCommittee Member, present
DA
Damian AllenCommittee Member, apologies
JD
John DowieCommittee Member, expected
DB
Councillor Dominic BeckReserve, apologies
BG
Becky GuthrieOfficer, in attendance
RS
Ryan ShepherdOfficer, in attendance
KL
Karen LytheObserver, in attendance

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Brownfield Housing Fund New Schemes - Project MandatesThis decision
  2. Brownfield Housing Fund ProgrammeNoted
  3. Brownfield Housing Fund UpdateNoted
  4. Brownfield Housing Fund Open CallDecided
  5. Brownfield Housing Fund Open Call - Project MandatesNoted
  6. Brownfield Housing Fund Open Call UpdateNoted

More from South Yorkshire Mayoral Combined Authority MCA - Housing and Infrastructure Board

All decisions
MeetingDecisionOutcome
16 Mar 2023 Minutes of Previous MeetingRESOLVED that the minutes of the previous meeting held on 8 February 2023 be approved. Approved Open
16 Mar 2023 Matters Arising / Action LogRESOLVED that the Action Log be noted. Noted Open
16 Mar 2023 Programme ApprovalsRESOLVED that the Board: Approve £3m grant award to Sheffield City Council for the “West Bar” project. Approve £1.3m ... Approved Open
8 Feb 2023 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on 8 December 2022 be approved. Approved Open
8 Feb 2023 Matters Arising / Action LogRESOLVED that the Action Log be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies