Resolved
RESOLVED that the Committee note the Dashboard and the progress in embedding processes.
Audit, Standards and Risk Committee noted this item on Wednesday 22 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Committee note the Dashboard and the progress in embedding processes.
Audit, Standards and Risk Committee
Wednesday, 22 March 2023
Risk Management Monitoring Report Is the paper exempt from the press and public? No
Reason why exempt: Not applicable
Purpose of this report: Monitoring/Assurance
Is this a Key Decision? No
Has it been included on the Forward Plan of Not a Key Decision Key Decisions?
Director Approving Submission of the Report: Gareth Sutton, Director of Resources & Investment/s73 Officer
Report Author(s): Claire James, Head of Corporate Governance [email protected]
Executive Summary This report provides an update on the progress of embedding the Risk Management Framework and the Risk Management Dashboard, which includes: • The corporate risks of the Mayoral Combined Authority (MCA). • ‘High’ and ‘Medium/High’ risks at Directorate level (operational risk). • Risks with a health and safety ‘theme’ with a score of 5 or over.
What does this mean for businesses, people and places in South Yorkshire? Effective risk management is a key principle of good governance and decision making, which enables the MCA to pursue its ambitions and objectives in the most effective and efficient way, bringing about better outcomes for residents and businesses in South Yorkshire.
Recommendations ASRC members are asked to consider the Risk Management Dashboard and note the progress in embedding risk management processes.
Consideration by any other Board, Committee, Assurance or Advisory Panel None 1. Background
1.1Following the recommendation of the Audit, Standards and Risk Committee, the MCA approved the Risk Management Framework at their meeting in July. In October, a post-implementation self-assessment commenced. This review took into account the recommendations of the internal audit report on risk management previously considered by the Committee in July.
The findings of the assessment culminated in a report to the Executive Leadership Board in December and an amended Framework progressing to the Committee in January for consideration.
2. Embedding the Risk Management Framework – Progress since January
2.1Since January two key changes have been implemented to further embed risk management practice. The landing page in the IT system has been reconfigured to give users a better oversight of all recorded risks. This is shown through a stacked bar chart for all the Corporate risks by owner, and also a stacked bar chart of operational risks for each Directorate. Each user can see all risks but can only edit those that they either own or have been assigned. The dashboard also includes direct links, bespoke to the user, to their specific risks and their actions.
Users of the system will now be sent, on the 1st of the month, rather than weekly, a reminder to review their risks. The reminder includes a link directly to the user’s risks and a link directly to the user’s actions. The reminder also sets out the hard deadlines for quarterly reviews and system shutdown dates where the system will be frozen in order to generate reports for the Executive Leadership Board and the Audit, Standards and Risk Committee. These changes have been communicated to users via an e-bulletin.
Next steps Governance Team will continue to enhance the dashboard with the inclusion of comparative data from period to period including the development of the heat map to show risk score movement over time (rather than just from inherent to residual score) and in response to any feedback from the Committee.
A Risk Management Support Plan will be developed for the next 12 months to ensure that these and other activities can be delivered within the allocated resource. The Plan will include the following activity: • Quarterly reporting cycle (production of dashboard). • Dashboard development. • Development of training resources to support users of the IT system. • System maintenance.
3. Risk Dashboard
3.1The Risk Dashboard provided at appendix A provides the following information:
Corporate Risks
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13i: App A: Risk Management Dashboard: 13 March 23Appendix | 732 KB | Download |
PDF |
Risk ManagementReport | 223 KB | DownloadRead as text |
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... | Decided | Open |
| 9 Jul 2026 | Questions from Members of the PublicThat the questions and responses be noted. | Noted | Open |
| 9 Jul 2026 | Terms of ReferenceThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Health and Safety UpdateThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Bus Franchising UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.