Resolved
RESOLVED that the Board note the progress and positive impacts within South Yorkshire communities, as a result of the investment of the Getting Building Fund.
Mayoral Combined Authority Board noted this item on Monday 31 July 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Board note the progress and positive impacts within South Yorkshire communities, as a result of the investment of the Getting Building Fund.
Mayoral Combined Authority Board
31 July 2023
Getting Building Fund Delivery
Is the paper exempt from the press No and public?
Reason why exempt: Not applicable
Purpose of this report: Monitoring/Assurance
Is this a Key Decision? No
Has it been included on the Not a Key Decision Forward Plan?
Director Approving Submission of the Report: Gareth Sutton, Executive Director Resources & Investment/s73 Officer
Report Author(s): Sue Sykes- Assistant Director, Funding Monitoring & Reporting [email protected]
Executive Summary This report provides an update on the delivery and progress of the Getting Building Fund.
What does this mean for businesses, people and places in South Yorkshire? This report showcases the projects funded by the Getting Building Fund resource and how they support the MCA’s aspirations.
Recommendations That Board note the progress and impacts within South Yorkshire communities, as a result of the investment of the Getting Building Fund.
Consideration by any other Board, Committee, Assurance or Advisory Panel None 1. Background
1.1In June 2020, the Government launched ‘A New Deal for Britain’ which was a key part of the fiscal stimulus package designed to keep the country working during the pandemic.
As part of this strategy £33.6m of Getting Building Funding resource was awarded to the MCA for “shovel ready” infrastructure schemes which were able to have an immediate impact in priming investment in local areas.
GBF funding has been used dynamically to complement other funding resources received by the individual local authority partners and the MCA. Being used alongside Future High Street Fund, Towns Deal, Brownfield Housing, Transforming Cities Fund, and Gainshare monies, the MCA and partners have been able to deliver transformative schemes at pace that kept the construction industry working and will provide a lasting legacy for future generations.
1.2Financial Progress
On submission of the final expenditure report into Government at the end of May 2023 the MCA was able to declare that the full £33.6m has been defrayed.
Projects’ current delivery is split into three categories: a) Fully spent and physically complete; b) Fully spent GBF but concluding additional works funded through other sources; and, c) Concluding GBF spend.
1.3The report provides details on each project and outlines how schemes would be funded
Projects Fully Spent and Physically Complete
1.4Barnsley College Barnsley College Digital Innovation Hub – Phase 2 GBF Investment - £1.4m
The SciTech Digital Innovation Hub was officially opened in October 2021 by Nadhim Zahawi, Secretary of State for Education, and accommodates students studying a range of Digital Industries subjects including broadcast journalism, computing and IT, digital design, digital photography, film and TV and games design.
GBF funding contributed to new improved space and facilities. Facilities within the hub have a special focus on digital industries cyber security, network technologies, Artificial Intelligence and Virtual Reality alongside software and programming. 1.5 Rotherham Metropolitan Borough Council Century II Business Centre GBF Investment - £3.6m
GBF was used to support the build of new office/light industrial units in Rotherham which are due to open in September on conclusion of utility works. Some units incorporate laboratory specifications after working with Hallam University and Food Engineering specialists to identify potential gaps in provision.
Staff within Rotherham Investment & Development Office (RIDO) have received a high level of enquiries about available space and are optimistic about this addition to their Council owned managed workspace portfolio and how it will complement their public sector business support offer.
1.6DN Colleges Group Digital Infrastructure GBF Investment - £0.6m
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Getting Building Fund DeliveryReport | 789 KB | DownloadRead as text |
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Minutes of the meeting held on 14 July 2026RESOLVED that the minutes of the meeting held on 14 th July 2026 be approved. | Approved | Open |
| 15 Sep 2026 | South Yorkshire Strategy and Proposed Implementation ApproachRESOLVED that the Board endorses: 1. The South Yorkshire Strategy as the shared regional framework. 2. The proposed c... | Agreed | Open |
| 15 Sep 2026 | City Densification FundRESOLVED that the Board: 1. Notes the Government’s allocation of £85m of ing to South Yorkshire. 2. Endorses the prog... | Agreed | Open |
| 15 Sep 2026 | National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ... | Noted | Open |
| 15 Sep 2026 | Governance UpdateRESOLVED that the Board: 1. Notes the recommendation of the Overview & Scrutiny Committee at its meeting on 7th July ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.