Programme Performance & Approvals Report

Approved Committee 7 papers

AI summarySouth Yorkshire MCA Board approved four transport and housing projects including £10.8m for Mexborough and £1.13m for Maltby, with delegated approval for c£2m Preformed Windings investment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPlus performance review noted and delegations granted
MoneyNot stated
What happens nextOfficers to enter legal agreementsHead of Paid Service to sign off contracts
Who it affectsNot stated

What was decided

The Board noted performance of MCA capital and revenue programmes to end of Q2 2025/26, including £50m capital spend against a £93m target. Report P1, P11

The Board gave full approval and awarded £1m to Sheffield City Council for A61 Chesterfield Road Bus Priority Phase 1, £10.8m to City of Doncaster Council for Mexborough Transport Network Sustainable Improvements, £1.07m to City of Doncaster Council for Bawtry Road Walking and Cycling Phase 1, and £1.13m to Rotherham Metropolitan Borough Council for Rotherham Direct Delivery Priority Sites Maltby. Report P1, P38, P47, P57

The Board delegated authority to the Head of Paid Service, in consultation with the Mayor, to consider full approval and award of a c£2m loan or grant to Preformed Windings Ltd, and to the Executive Director of Growth, Business and Skills to progress 2026/27 Local Growth Fund grants plus £1m of Sheffield City Council gainshare. Report P1, P109, P126

Why

The four schemes had satisfied business case assessment, were recommended by Investment Board, and met conditions set out in Assurance Summaries C to F. Report P1, P9, P46, P52, P62, P102

Approval would accelerate delivery against the Mayor's Plan for Good Growth, support sustainable transport, affordable housing and clean energy investment, and keep scheme delivery on track for the March 2027 CRSTS deadline. Report P30, P31, P110, P111

Delegations enable faster progress on time-critical investments, including a Business Growth proposal and Local Growth Fund use for 2026/27. Report P107, P126

What happens next

The Head of Paid Service, in consultation with the Section 73 and Monitoring Officer, will enter into legal agreements for the approved and delegated items. Report P1

Phase 1 of the A61 Chesterfield Road scheme will commence immediately, with Phase 2 planning continuing in parallel. Report P45

Officers will develop and submit an expression of interest to the Arts Council for the Place Partnerships South Yorkshire Childhood Music project, and accept any resulting grant. Report P1

The money

  • £1m Grant to Sheffield City Council for A61 Chesterfield Road Bus Priority Phase 1 Report P1, P38
  • £10.8m Grant to City of Doncaster Council for Mexborough Transport Network Sustainable Improvements Report P1, P47
  • £1.07m Grant to City of Doncaster Council for A638 Bawtry Road Walking and Cycling Phase 1 Report P1, P57
  • £1.13m Grant to Rotherham Metropolitan Borough Council for Rotherham Direct Delivery Priority Sites Maltby Report P1
  • c£2m Loan or grant to Preformed Windings Ltd, subject to delegated approval Report P1, P109
  • £1m Sheffield City Council gainshare allocation to support 2026/27 activity Report P1, P126
  • £2.05m Top up to Rotherham Project Feasibility Fund from 2024/25 and 2025/26 Gainshare Report P84

Options considered

  • Chosen: Full approval of A61 Chesterfield Road Bus Priority Phase 1 with £1m to Sheffield City Council. Meets assurance requirements and accelerates bus priority on a key corridor Report P38, P46
  • Chosen: Full approval of Mexborough Transport Network Sustainable Improvements with £10.8m. Supports sustainable transport in a deprived area and meets assurance requirements Report P47, P52
  • Chosen: Full approval of Bawtry Road Walking and Cycling Phase 1 with £1.07m. Aligns with Doncaster Local Plan and regional active travel goals Report P57, P62
  • Chosen: Full approval of Rotherham Direct Delivery Priority Sites Maltby with £1.13m. Increase above £0.77m OBC approval requires MCA approval, supports 45 social rent homes Report P98, P102
  • Chosen: Delegated approval of c£2m loan or grant to Preformed Windings Ltd. Supports clean energy jobs and first UK high-voltage testing facility Report P109, P111
  • Chosen: Note Q2 2025/26 programme performance and accept Adult Skills 2024/25 outturn position including clawback of £1.170m for under-delivery. Standard performance review and financial control for Adult Skills Fund Report P11, P140, P142

Implications

  • Financial: Capital programme 2025/26 forecast to deliver c.£160m of investment across South Yorkshire, with Q2 spend of c£50m against a £93m target. Report P10, P11
  • Financial: Local Growth Fund envelope for 2026/27 is c. £15m (c. £11m revenue, c. £4m capital), top-upable to c. £16m from SPF Investment Zone pot, plus £1m Sheffield gainshare drawdown. Report P125, P126
  • Risk: CRSTS schemes must be contractually committed by March 2027, with construction potentially extending into 2027/28, creating programme completion risk. Report P28, P31
  • Staffing: Recruitment underway for at least 4 Mayoral Delivery Fund posts, with further prioritisation required as more interventions move into delivery. Report P86
  • Equalities: Maltby scheme addresses housing need in Rotherham, which ranks 35th on the Index of Multiple Deprivation, and aims to mitigate Right to Buy losses of 1,053 homes since 2018. Report P101

Who and where

  • Sheffield City Council, as grant recipient for A61 bus priority scheme Report P38
  • City of Doncaster Council, as grant recipient for Mexborough and Bawtry Road schemes Report P47, P57
  • Rotherham Metropolitan Borough Council, as grant recipient for Maltby housing and as Feasibility Fund user Report P77
  • Preformed Windings Ltd, potential recipient of c£2m loan or grant Report P109
  • Barnsley, Doncaster, Rotherham and Sheffield residents, as users of new transport and housing Report P39, P49, P101
  • Local SMEs and adult learners, as beneficiaries of skills and business support programmes Report P119, P120, P136

Timeline

  • August 2025: Connect to Work local authority delivery commenced Report P168
  • Q2 2025/26: Q2 performance review reported to Board; £50m capital spend recorded Report P11
  • Q3 2025/26: Skills Bootcamps construction specific activity to commence Report P149
  • Q4 2025/26: First ATF3 scheme at Jossey Lane due to complete; North Bridge Connector starts on site Report P55
  • January 2026: Rotherham Gateway Station Outline Business Case awaiting Ministerial approval Report P32
  • 31 March 2026: Brownfield Housing Fund projects must be in contract Report P94
  • March 2027: CRSTS schemes to be contractually committed Report P28

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, the main transport funding programme
  • TCR: Transport for City Regions, the successor fund forming part of the Integrated Settlement
  • TCF: Transforming Cities Fund, an earlier transport programme now largely complete
  • UKSPF: UK Shared Prosperity Fund, the main revenue programme for business, skills and communities
  • PBIS: Place Based Investment Strategy used by local authority partners
  • FBC: Full Business Case, the final stage of project assurance
  • SBC: Strategic Business Case, an early stage of project assurance
  • ATE: Active Travel England, the national body overseeing active travel funding
  • CATF: Consolidated Active Travel Fund blending capital and revenue
  • MDF: Mayoral Delivery Fund, drawn from Gainshare to support Mayoral priorities
  • IZ: Investment Zone, a designated area receiving business support funding
  • LTN 1/20: Local Transport Note 1/20, the national standard for cycle infrastructure design
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item436

Resolved

RESOLVED that the Board considers: 1. Performance of the MCA’s externally funded capital and revenue programmes to the end of Q2 2025/26. 2. Progression of “A61 Chesterfield Road Bus Priority Phase 1” to full approval and award of £1m to Sheffield City Council, subject to the conditions set out in Assurance Summary C. 3. Progression of “Mexborough - Transport Network Sustainable Improvements” to full approval and award of £10.8m grant to City of Doncaster Council, subject to the conditions set out in Assurance Summary D. 4. Progression of “Bawtry Road Walking and Cycling Phase 1” to full approval and award of £1.07m grant to City of Doncaster Council, subject to the conditions set out in Assurance Summary E. 5. Progression of “Rotherham Direct Delivery Priority Sites – Maltby" to full approval and award of £1.13m grant to Rotherham Metropolitan Borough Council, subject to the conditions set out in Assurance Summary F. 6. Progression of change request detailed in section 2.6 7. Delegated authority to the Head of Paid Service, in consultation with Mayor Oliver Coppard in his position as Portfolio Lead for Economic Growth, Section 73 and Monitoring Officer for consideration of the following: a) Progression of “Preformed Windings Growth Plan” to full approval and award of c£2m loan/grant to Preformed Windings Ltd as detailed in section 2.10. 8. Delegated authority to the Executive Director of Growth, Business and Skills in consultation with Section 73 and Monitoring Officer to progress proposals for utilising the Local Growth Fund in 2026/27 plus £1m Sheffield City Council’s gainshare allocation to full approval and award of grants as detailed in 2.12 9. Delegate authority to the Executive Director, Strategy and Mayoral Office Policy and Strategic Development to develop and submit an expression of interest to the Arts Council to seek support for the Place Partnerships, South Yorkshire Childhood Music project. and subsequent acceptance of any grant as detailed in 2.27 10. Delegate authority to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the points above.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Mayoral Combined Authority Board

Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
14.i. Appendix A Programme Performance ReportAppendix 97 KB Download
PDF
14.ii. Appendix B Q2 202526 Programme PerformanceAppendix 5.5 MB Download
PDF
14iii. Appendix C: A61 Chesterfield Rd Phase 1 Assurance SummaryAppendix 289 KB Download
PDF
14iv. Appendix D: Mexbrough Assurance SummaryAppendix 309 KB Download
PDF
14v Appendix E: Bawtry Road Walking and Cycling Assurance SummaryAppendix 268 KB Download
PDF
14vi Appendix F: Maltby Assurance SummaryAppendix 277 KB Download
PDF
Programme Performance & Approvals ReportReport 2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 23 attended
MO
Mayor Oliver Coppard LAB South Yorkshire Mayoral Combined AuthorityChair, present
SS
Councillor Sir Steve Houghton CBE LAB Barnsley MBCCommittee Member, apologies
TH
Councillor Tom Hunt LAB Sheffield City CouncilCommittee Member, present
MR
Mayor Ros Jones CBE LAB City of Doncaster CouncilCommittee Member, present
CR
Councillor Chris Read LAB Rotherham MBCCommittee Member, present
FB
Councillor Fran Belbin LAB Sheffield City CouncilReserve
VC
Councillor Victoria Cusworth LAB Rotherham Metropolitan Borough CouncilReserve
GJ
Councillor Glyn Jones LAB City of Doncaster CouncilReserve
CM
Councillor Caroline Makinson LAB Barnsley MBCReserve, present
SH
Cllr Sharon Howard (Rotational Member) Barnsley MBCNotify
SJ
Sara JohnOfficer, in attendance
JQ
Joseph QuinnOfficer, expected

All 23 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Programme Performance & Approvals ReportThis decision
  2. Programme Performance & Approvals ReportApproved
  3. Programme Performance and Approvals ReportApproved
  4. Programme Performance and Approvals ReportApproved
  5. Programme Approvals and Performance ReportApproved
  6. Programme Performance UpdateNoted

More from South Yorkshire Mayoral Combined Authority Mayoral Combined Authority Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the meeting held on 14 July 2026RESOLVED that the minutes of the meeting held on 14 th July 2026 be approved. Approved Open
15 Sep 2026 South Yorkshire Strategy and Proposed Implementation ApproachRESOLVED that the Board endorses: 1. The South Yorkshire Strategy as the shared regional framework. 2. The proposed c... Agreed Open
15 Sep 2026 City Densification FundRESOLVED that the Board: 1. Notes the Government’s allocation of £85m of ing to South Yorkshire. 2. Endorses the prog... Agreed Open
15 Sep 2026 National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ... Noted Open
15 Sep 2026 Governance UpdateRESOLVED that the Board: 1. Notes the recommendation of the Overview & Scrutiny Committee at its meeting on 7th July ... Decided Open