What was decided
The Board approved full approval and a £12.46m grant to Sheffield City Council for the Nether Edge Wedge Phase 1 active travel scheme, post OBC in-principle approval and a £3.97m grant/loan to Vac-Ex Ltd for the Doncaster 191 manufacturing facility, full approval and a £2.4m grant to Sheffield City Council for AT City Centre Connections Castle Street, and full approval and £7.064m for Highways Maintenance Incentive Funding 2026/27. Report P31, P32, P45, P72, P96, P97
The Board accepted new government grants: £1.42m from DESNZ for the Housing Retrofit Programme, £1.87m from DBT and WYCA for the Made Smarter Yorkshire and Humber Programme, £1.31m from DBT for Made Smarter Enhancement Funding, and £0.5m from DESNZ for Made Smarter Housing Retrofit, and endorsed bids to DEFRA for the Third National Forest Programme, to establish the What Works Centre for Local Employment Support, and to the Bloomberg Philanthropies Youth Climate Action Fund.
The Board delegated authority to the Head of Paid Service, Section 73 and Monitoring Officer for the Integrated Settlement Active Travel Revenue Funding of £3.23m, to the Executive Director for Growth, Business and Skills for the Construction Skills Package across 2026/27 to 2028/29 and extension of the Business Growth Advisor Service with c£0.75m to local authorities, and approved the use of any unspent AY 2024/25 Adult Skills funding for delivery in AY 2025/26. Report P1
Why
The capital programme delivered £168m of investment in South Yorkshire in 2025/26 against a forecast of c.£160m, the highest annual capital delivery value to date. Report P10
Programme decisions are made under the MCA Assurance Framework, with Investment Board recommendations supporting MCA Board decisions and officer delegations for lower value or time-critical items. Report P4, P9
What happens next
Delegated authority is given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the points approved. Report P1
Delivery of approved transport schemes will continue with monitoring of schemes at risk of not being contractually committed by the March 2027 CRSTS deadline, and skill and business support programmes will continue through to 2028/29 and beyond. Report 2.1, P29, P63, P131
The money
- £12.46m Grant to Sheffield City Council for Nether Edge Wedge Phase 1 active travel Report P31, P32
- £3m Grant to SYMCA for Bus Lane Review, per the decision wording; P37 cites £3.11m Report P37
- £2.4m Grant to Sheffield City Council for AT City Centre Connections Castle Street Report P45
- £3.97m Grant/loan to Vac-Ex Ltd for Doncaster 191 manufacturing facility Report P96, P97
- £7.064m Highways Maintenance Incentive Funding 2026/27 Report P72
- £3.23m Integrated Settlement Active Travel Revenue Funding across 2026/27 to 2028/29 Report P61, P63
- c£0.75m Grant to local authorities for Business Growth Advisor Service extension
- £1.42m Grant from DESNZ for the Housing Retrofit Programme
Options considered
- Chosen: Approve Nether Edge Wedge Phase 1 active travel scheme at £12.46m. Around 70% of trips in the area are by car, above the citywide average of 62%, and cycling levels are above average, indicating strong potential for further uptake Report P31, P32, P33, P34
- Chosen: Approve SYMCA Bus Lane Review at post OBC in-principle stage. Improve performance of existing bus services in Rotherham and Sheffield by reducing journey times and improving reliability Report P37, P38
- Chosen: Approve AT City Centre Connections Castle Street. Support regeneration of the Castlegate area with a new active travel route and improved cross-city connectivity Report P45, P46, P47, P50
- Chosen: Approve Doncaster 191 grant/loan to Vac-Ex Ltd at £3.97m. Support manufacturing expansion that is expected to create skilled jobs and strengthen the regional supply chain Report P96, P97, P98
Implications
- Financial: Capital programme delivered £168m in 2025/26, the highest annual value to date, with over 200 projects in delivery and over 90 in development gateways. Report P9, P10
- Financial: Brownfield Housing Fund is now fully allocated, with around £60m of the £66m Programme contracted and the remainder in contract negotiation. Report P86, P87
- Financial: A small overall underspend of approximately £1.2m was identified in the UKSPF return and the 2025/2026 LGF transition year is underspent, with mitigation through LGF allocations in 2026/27. Report P100, P101
- Risk: Schemes at risk of not being contractually committed by March 2027 are being monitored closely; inflationary pressures and supply chain disruption may increase the need to descope or reprioritise. Report P13, 2.1
- Staffing: Recruitment-related slippage and capacity constraints in delivery teams have slowed revenue and capital drawdown in the early stages of the Mayoral Delivery Fund. Report P83
- Equalities: Nether Edge Wedge scheme aims to create a safer and more inclusive transport environment for all ages and abilities, and Castle Street improvements are designed to support people with mobility impairments, wheelchair users and those with pushchairs. Report P36, P47
Who and where
- Sheffield City Council as delivery partner and grant recipient for active travel schemes Report P31, P32, P45
- Barnsley, Doncaster and Rotherham councils receiving Highways Maintenance allocations Report P75, P76
- Vac-Ex Ltd as grant/loan recipient for the Doncaster 191 manufacturing facility Report P96, P97
- South Yorkshire residents, including economically inactive participants in Pathways to Work programmes Report P152, P146, P147
- Local Further Education colleges, skills providers and employers delivering Adult Skills, Skills Bootcamps and Construction Skills Report P16, P114, P131
Timeline
- Q4 2025/26: Capital programme delivered £168m against a forecast of c.£160m Report P10
- 2026/27: Highways Maintenance Incentive Funding of £7.064m to be awarded; CRSTS defrayal deadline for contractual commitment is March 2027 Report P71, P72, 2.1
- 2026/27 to 2028/29: Integrated Settlement Active Travel Revenue Funding of £3.23m across the three years and Construction Skills Package delivery Report P63, P131
- September 2026: Working Win Individual Placement and Support programme ends, replaced by Connect to Work from April 2026 Report P157, P167
- March 2027: CRSTS schemes must be contractually committed to continue benefitting from CRSTS funding Report 2.1, P29
Plain English for the jargon
- OBC: Outline Business Case, a stage in the development of a project business case before full approval
- CRSTS: City Region Sustainable Travel Settlements, a transport funding programme
- TCF: Transforming Cities Fund, a transport infrastructure programme
- AY: Academic Year, used to time skills programme delivery
- Gainshare: Long-term devolved funding of £30m per annum for economic development and regeneration
- DESNZ: Department of Energy Security and Net Zero
- DBT: Department for Business and Trade
- WYCA: West Yorkshire Combined Authority