Internal Audit Service Quarterly Performance Report

Noted Finance 6 papers

Audit Committee noted this item on Wednesday 18 January 2017. Below is the council's own wording, with the papers it was decided on.

Item640

Resolved

- That the progress made in delivering the 2016/17 Internal Audit Strategy, be noted.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Audit Committee

Purpose of report

1.1To update the Audit Committee on the progress made in delivering the Internal Audit Strategy for 2016/17.

Recommendations

2.1The Audit Committee notes the progress made in delivering the 2016/17 Internal Audit Strategy.

3. Internal Audit Plan Status

3.1Appendix 1 sets out the current status of the audit work planned for the year as at 6th January 2017. There have been a few final amendments to the Audit Plan. 3.2 The Adult Social Care Independent File Review audit has been deleted as the service has informed Internal Audit that the:  Adult Social Care File Audit Framework will be developed after the implementation of the new client file recording database LiquidLogic that is to be implemented in the summer of 2017. This new system will be an asset and will be able to capture easily what will be needed to:  provide evidence of safe practice, or  be able to highlight issues that may need addressing or further improvement.  it was not economic to spend time and resources on amending Care First (the current case management IT system) with the imminent introduction of LiquidLogic  Safeguarding Board will be made aware of this change of plan, and will be scheduled to discuss this later in 2017.

Internal Audit Service, Quarterly Page 1 of 4 Performance Report 3.3 An interim manager was bought in, in May 2016, to review the current arrangements for managing Better Start Early Years project. This work is just coming to an end and a new governance framework is in the process of being implemented. Therefore, this audit will be postponed until these new arrangements have had time to become embedded into the day to day operational processes of this project. 3.4 A new job has been added into the Audit Plan which involves looking at the design and effectiveness of the arrangements within the Departments of Place and People to get assurance over the delivery of projects. 3.5 In the event, specialist resources were only available to do most of the ICT audit work in the January to March 2017 quarter. Therefore, the IT Systems and Network Access Controls review will be moved to early 2017/18, given the other work already being done in this area during this period. 3.6 Finally, the payroll audit will now be done in April 2017, when all the actions should have been implemented (there is one with a target date of March 2017). 3.7 Therefore, the budgeted number of days contained in the Audit Plan for this year is now 730. As reported previously, this reduction is days from the original estimate, is mainly due to the team keeping a cash sum to fund the planned recruitment exercise. 3.8 Expected timings for the remaining audits are highlighted in the Audit Plan. 3.9 A revised split of coverage over the different audit categories and departments is also contained at the end of the Audit Plan, for information.

4. Audit Opinions and Themes

4.1Appendix 2 summarises the level of assurance reported for each audit completed to date. The Corporate Management Team has given the position on audit opinions serious consideration and is urgently seeking ways to address and improve the situation, including staff training through the roll out of the new framework "How it works, a guide for managers to help the Council run effectively". 4.2 It should be noted that the assurance reported when audits are revisited, relates to the degree to which the service has dealt with the actions agreed. It does not relate how well the system, service or process is operating as a whole. 4.3 Appendix 3 summarises the results of and where appropriate, the audit opinions given on work completed to date. School audits, where draft reports were issued before they became academies, have been included for information.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Service Quarterly Performance ReportReport 97 KB DownloadRead as text
PDF
b App 1 Audit Plan 2016-17 to AC finalAppendix 126 KB Download
PDF
c App 2 Summary of audit results to AC finalAppendix 48 KB Download
PDF
d1 App 3a Opinion and Themes High to AC finalAppendix 50 KB Download
PDF
d2 App 3b Opinion and Themes Satisfactory to AC finalAppendix 73 KB Download
PDF
d3 App 3c Opinion and Themes Partial to AC finalAppendix 99 KB Download

At this meeting

Whole meeting

Who was there

9 of 20 attended
LE
Linda EverardCouncil Staff, in attendance
BA
Councillor Brian AylingCommittee Member, present
SB
Councillor Steve BuckleyVice-Chair, present
MD
Councillor Meg DavidsonChair, present
CN
Councillor Cheryl NevinCommittee Member, present
AB
Councillor Alex BrightCommittee Member, present
DG
Councillor David GarstonCommittee Member, apologies, sent representative
MS
Councillor Mike StaffordCommittee Member, absent
JM
Councillor James MoyiesCommittee Member, present
JW
Councillor Julian Ware-LaneCommittee Member, present
CG
Colin GambleOfficer, in attendance
KP
Kashyap PandyaCo-Optee, in attendance

All 20 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Internal Audit Service Quarterly Performance ReportThis decision
  2. Internal Audit Service Quarterly Performance ReportNoted
  3. Internal Audit Service Mandate & Charter, Strategy and 2026/27 PlanApproved
  4. Internal Audit Service Quarterly Performance ReportNoted
  5. Internal Audit Service Quarterly Performance ReportNoted
  6. Head of Internal Audit Annual Report 2024/25Decided

More from Southend-on-Sea Audit Committee

All decisions
MeetingDecisionOutcome
23 Apr 2025 Minutes of the Meeting held on Monday 27 January 2025That the Minutes of the Meeting held on Monday, 27 January 2025 be confirmed as a correct record and signed. Decided Open
23 Apr 2025 Minutes of the meeting held on Tuesday 25 February 2025That the Minutes of the Meeting held on Tuesday, 25 February 2025 be confirmed as a correct record and signed. Decided Open
23 Apr 2025 CIPFA Financial Management Code Action Plan Progress ReportThat the Council’s annual review against the expectations of CIPFA’s Financial Management Code and the assurance that... Noted Open
23 Apr 2025 Counter Fraud and Investigation Team Quarterly Performance ReportThat the performance of the Counter Fraud and Investigation Team over the last three months, be noted. Reasons for de... Noted Open
23 Apr 2025 Internal Audit Service Quarterly Performance ReportThat the progress made in delivering the 2024/25 Internal Audit Strategy and Plan, be noted. Reasons for decision: In... Noted Open