Future Phases of the Housing Revenue Account (HRA) Development Project
NotedScrutiny1 paper
Policy and Resources Scrutiny Committee noted this item on Wednesday 12 April 2017. Below is the council's own wording, with the papers it was decided on.
- That the following recommendations of Cabinet be noted:- “1. That the following sites within Phase 2 of the HRA Land Review Project be brought forward for development:- § Rochford Road – 15 units § Audleys Close – 1 unit 2. That resident consultation be undertaken and that following completion of such exercise the Deputy Chief Executive (People), in consultation with the Portfolio Holder for Housing, Planning and Public Protection Services, be authorised to finalise the plans and submit a detailed planning application. 3. That the proposed method of funding for the project from the 2017/18 capital programme to be met from the HRA Capital Investment Reserve, be approved. 4. That further feasibility work be undertaken in respect of a number of sites that would form future phases of the HRA Land Review Project.” Note :- This is a Council Function. Executive Councillor :- Flewitt
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To provide an overview of the future phases of the HRA Land Review Project which seeks to meet the Council’s aim of developing affordable housing in the borough and request agreement to progress with the second phase of the project.
Recommendations
2.1That the Cabinet Agrees to:-
a. Bring forward the following sites within Phase 2 of the HRA Land Review Project for development:- Rochford Road – 15 units Audleys Close – 1 unit b. Undertake resident consultation, finalise plans and submit a detailed planning application c. Agree the proposed method of funding for the project from the 2017/18 capital programme to be met from the HRA Capital Investment Reserve d. Undertake further feasibility work of a number of sites that would form future phases of the HRA Land Review Project.
Background
3.1The need for affordable housing within the borough is as great as ever and the Council’s commitment to addressing this is well documented. The Council’s Corporate Priorities and the aims of the Strategic Housing Strategy 2011-21 both reflect this.
3.2Following an assessment of 124 parcels of Housing Revenue Account (HRA) land, a Cabinet paper in July 2014 entitled Investigation of potential development sites on HRA Land further detailed the sites identified within a
Future Phases of the Housing Revenue Account (HRA) Development Project Page 1 of 7 feasibility study. These sites were packaged in 3 distinct phases – Phase 1 (Shoeburyness), Phase 2 (St. Laurence), and Phase 3 (Blenheim/Belfairs). The pilot scheme for the first new Council house was completed in Byron Avenue and Phase 1 (18 properties), currently being built in Shoeburyness, will be finished in the next few months.
3.3The architects for Phase 1 of the project, AK Design, have also progressed with the feasibility assessment for the sites within Phase 2. This feasibility work has further developed the opportunities and constraints for each site which has necessitated some changes to sites included within this phase. The sites in Phase 2 are within the St Laurence ward and it is anticipated these sites will yield 16 properties as per below.
Phase 2
Ward Site Total Housing Units St Laurence Rochford Rd 15 St Laurence Audleys Close 1 Total 16
3.4The proposed sites are two underutilised garage sites in the St Laurence ward of the borough. The larger site is on Rochford Road, and the second site is in Audleys Close.
3.5Land within Bishop House had previously been included within Phase 2; however this proved to be an unviable site.
3.6The Rochford Road garage site has the potential for:
- 12 x 2 bedroom flats (4 of which will be ground floor and designed to be adapted/adaptable) Future Phases of the Housing Revenue Account (HRA) Development Project Page 2 of 7 - 3 x 3 bedroom houses
3.7The Audleys Close garage site is an extremely constrained site, and as a result it only has the potential for 1 x 2 bedroom bungalow, which has been designed for disabled use.
Finances
3.8Phase 1 of the HRA Land Review project achieved a contract value of just over £2.5m, with on-costs bringing the total project to the value £2.8m. This equated to just under £1600 per m2 + on costs.
3.9Using the HRA Phase 1 tendering process as a point of reference and understanding that the cost of construction is increasing it is anticipated a build cost of around £2100m² could be achieved. The following figures have been calculated on the assumption that the build cost will be £2100m² + 15% SBC on-costs (allowing for new transport works as well).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy and Resources Scrutiny Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.