Future Phases of Affordable Housing Development Programme/Update
NotedScrutiny1 paper
Policy and Resources Scrutiny Committee noted this item on Wednesday 30 January 2019. Below is the council's own wording, with the papers it was decided on.
- That the following decisions of Cabinet be noted:- “1. That sites be brought forward within Phases 3 and 4 of the HRA Land Review. 2. That further feasibility work be undertaken on a number of sites that will form Phases 5 and 6 of the HRA Project. 3. That the proposed method of funding for the projects and the use of S106 funds for the feasibility works for Phases 5 and 6, to a maximum of £50,000, be endorsed. 4. That the options for the delivery of 2 garage sites for Modern Methods of Construction (MMC) pilots be investigated, including undertaking a procurement exercise of solutions put forward by the market and also a value for money exercise. Furthermore, to explore subsequent pilot sites to test Modern Methods of Construction on a broader scale, including Lundy Close. 5. That the use of S106 contributions received from developers, in order to facilitate the provision of affordable housing through the creation of an ongoing fund for the purchase of developable land in the borough, be endorsed.” Note: This is an Executive Function Cabinet Member: Cllr Cox
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To provide an overview of the future phases of the HRA Land Review project, request agreement to progress with Phases 3 & 4 of the project to fund and construct 56 units of affordable housing and undertake feasibility studies for Phases 5 & 6 of the project.
1.2To provide an update and seek agreement to undertake Modern Methods of Construction (MMC) pilot projects across 2 garage sites and develop a Land Purchase Fund using existing S106 contributions.
Recommendations
That Cabinet agrees to:
a. Bring forward sites within Phases 3 and 4 of the HRA Land Review,
b. Undertake further feasibility work of a number of sites that will form Phases 5 & 6 of the HRA Project,
c. Agree the proposed method of funding for the projects and also agree the use of S106 funds for the feasibility works for Phases 5 & 6 (to a maximum of £50,000),
d. Investigate the options for the delivery of 2 garage sites for Modern Methods of Construction (MMC) pilots to include undertaking a procurement exercise of solutions put forward by the market and also a value for money exercise. Furthermore, to explore subsequent pilot sites to test Modern Methods Construction on a broader scale.
Future Phases of Affordable Housing Development Page 1 of 14 Programme Update e. To agree the use of S106 contributions received from developers in order to facilitate the provision of affordable housing through the creation of an ongoing fund for the purchase of developable land in the borough.
Background
3.1The need for affordable housing within the borough is greater than ever and the Council’s commitment to addressing this housing need for affordable housing is well documented with the Council’s Southend 2050 Vision & the Housing, Homelessness and Rough Sleeping Strategy both reflecting this.
3.2The March 2017 Cabinet report titled Future Phases of the Housing Revenue Account (HRA) Development Project agreed to build on the success of the Phase 1 of the HRA Land Review and to bring forward sites in Phase 2 of the project. It also agreed to undertake feasibility work on a number of sites that would form future phases of the HRA Land Review Project.
3.3Phase 2 of the project is now underway; with Essex based Marfleet Construction appointed as main contractor for the works and completion estimated by summer 2019. Initial feasibility and ground investigation works have also been carried out for Phases 3 & 4 of the project.
HRA Land Phase 3 overview
3.4Phase 3 of the HRA Land Review Project consists of the redevelopment of 5 underutilised garage sites in the east of the borough, within the Shoeburyness Ward.
Future Phases of Affordable Housing Development Page 2 of 14 Programme Update 3.5 The site plan above highlights 7 garage sites around the Eagle Way estate as part of the project however it is proposed to only redevelop 5 for affordable housing with the other 2 earmarked to meet the need for garage hire/relocation (highlighted as R).
Site Potential Units Nos Eagle Way (former compound location) 12 Eagle Way 1 3 Eagle Way 3 2 Fraser Close site 3 6 Anson Chase 2 2 Total 25
3.6The majority of the sites earmarked for redevelopment are predominantly void, with the exception of Fraser Close site 3, which only has two voids. There will be 17 garage tenants displaced by the redeveloped sites. The alternative garages will have capacity for another 4 units, leaving 13 units to relocate. There are several nearby garage sites which have been refurbished in recent years, and have capacity (16 available garages) to accommodate the displaced tenants.
3.7Finances
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy and Resources Scrutiny Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.