The Cabinet considered a report of the Deputy Chief Executive (Place) providing an update on the progress of the Southend (ABPS) development, specifically in relation to the phase 2 Local Growth Fund (LGF) allocation. To note the positive progress made in delivering the ABPS project and the significant opportunity it presents to increase economic growth, employment and skills. Other Options: None. Note: This is an Executive Function Eligible for call in to Place Scrutiny Committee Executive Councillors: Lamb, Holland and Moring. To note the positive progress made in delivering the ABPS project and the significant opportunity it presents to increase economic growth, employment and skills. Other Options: None. Note: This is an Executive Function Eligible for call in to Place Scrutiny Committee Executive Councillors: Lamb, Holland and Moring.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
To update Members on the progress of the Airport Business Park Southend (ABPS) development, specifically in relation to the phase 2 Local Growth Fund (LGF) allocation.
Recommendations
2.1To note and the progress of the development of Airport Business Park Southend.
Background
3.1On 14th March 2017 Cabinet received an update report in regards to the ABPS project highlighting notional allocation of £19.89m Local Growth Fund (LGF) funding from the South East Local Enterprise Partnership (SELEP) and the commencement of phase 1 works.
3.2Since that report good progress has been made with the development which includes:
3.2.1 Highways – the roundabout on Cherry Orchard Way, which provides access to the site, is now complete and in use. The phase 1 spine road has also been delivered with a traffic island just before the roundabout and the wearing course to be laid once utilities works are complete.
3.2.2 Rugby Club - practical completion of the rugby club pitches has been certified so are now subject to a 12 month maintenance contract. The Rugby Club has submitted its application for its premises licence to Rochford District Council for approval – securing this is a pre-commencement condition put in place by the
Report Title: Airport Business Park Southend Update Page 1 of 4 Report Number: 17/077 Club. The Relocation Agreement and specifications are nearly finalised to then commence works on the clubhouse building.
3.2.3 Management Company - draft Management Company Articles have been approved and prospective Management Agents have been interviewed by HBDL ready for consideration by the Partnership Board.
3.2.4 Occupiers – advanced negotiations with some potential occupiers continue while the pipeline of interested parties continues to grow. An updated promotional brochure has been produced illustrating the progress made and the next phase of marketing is underway.
3.3The utilities works are currently subject to a short delay. This is being managed through the governance arrangements in place with the contractor being managed by Henry Boot Developments Ltd (HBDL) who, in turn, is accountable to the Council.
3.4At the 22nd September SELEP Accountability Board the Airport Business Park LGF business case was considered. Having already secured, and spent in accordance with the grant terms, £3.2m from an earlier round of LGF the business case sought to combine the phases for ease and transparency of reporting; this was agreed.
3.5As the overall LGF allocation exceeds £8m additional stages have to be progressed through to secure the total award but on the basis of the outline business case submitted, and the positive assessment by the SELEP Independent Technical Evaluator, £815,000 phase 2 funding was agreed to be made available to the Council prior to submission of the full business case to enable the Council to commence the next phase of works. So as to support SELEP in its delivery of LGF, where Council capital was to be spent on phase 1 works, this was swapped with LGF thereby bringing forward a further £4.5m of LGF and moving the Council’s capital spend to later years. This does not alter the Council’s match funding commitment or the outputs and outcomes of the project, it just moves the spend to later in the programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.