- That the progress of the Airport Business Park development, be noted. Reasons for Decision The Airport Business Park Southend is a 2050 roadmap project and its ongoing development contributes towards a number of Southend 2050 outcomes. It is also significant for South Essex as SELEP’s largest LGF allocation and a key location in the context of the South Essex 2050 work. Other Options While not continuing with the project could be an option in theory this could not be achieved without disproportionate cost, legal challenge and disruption as the development is underway with funding, consents and a development partner in place. It would also undermine the 2050 roadmap and ambition. Note: This is an Executive Function Referred direct to Place Scrutiny Committee Cabinet Members: Cllrs Robinson and Woodley
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
This report seeks to provide an update on the development of the Airport Business Park which is being progressed with the Council’s development partner Henry Boot Developments Ltd.
Recommendations
To note the progress of the Airport Business Park development
Background
3.1Airport Business Park Southend (ABPS) is a Southend 2050 roadmap project and is identified in Opportunity and Prosperity outcome 4 as it seeks to create prosperity and job opportunities for local people.
3.2The ABPS site is located in Rochford district and comes under the Joint Area Action Plan (JAAP) area. It is owned by Southend-on-Sea Borough Council and prior to development commencement was constituted of rugby pitches and agricultural land.
3.3Cabinet last received at update on the ABPS project on 7th November 2017 (minute 455 refers). At this time development had received £3.2m of Local Growth Fund (LGF) funding from the South East Local Enterprise Partnership (SELEP) and a notional allocation of a further £19.89m was going through the full business case process with a re-profiling of some of the funding in relation to the Council’s match funding. This was agreed by SELEP on 14 September 2018 and since then reporting and monitoring of the project’s progress has been on the basis of a total LGF investment of £23.09m.
Airport Business Park Update 18/055 3.4 The total cost of the project, including construction of the Launchpad, is £31.07m of which £23.09m is funded from LGF with the remainder (£7.98m) coming from the Council’s existing capital programme. LGF money has to be spent within the Growth Deal period which ends on 31 March 2021 and the current spend profile for the project reflects that requirement. In the period 2016/17 to 2018/19 £8.57m of LGF was spent mainly funding Phase 1 infrastructure works and building the new clubhouse and pitches for Westcliff Rugby Football Club. Over the same period the Council made a match funding contribution of £1.06m. The spend profile for the remainder of the project is:
Source 2019/20 £m 2020/21 £m 2021/22 £m Total £m LGF 11.842 2.678 14.520 SBC capital 0.267 5.140 1.513 6.920 Total 12.109 7.818 1.513 21.44
The increased spend 2019/20 reflects an increase in activity in readiness for the relocation of WRFC and the first occupier moving on to the site. Works are progressing well on site and at the end of Q2 the project was £0.679m ahead of the spend profile which reflects good progress rather than any overspend. SELEP are comfortable with this accelerated delivery.
3.5Progress on the site since the last report, and as indicated above through the spend profile, has been substantial and includes:
3.6Phase 1 – this was the first phase of highways and utilities from, and including, the entrance on Cherry Orchard Way through to the turning for the new rugby club clubhouse and pitches. The utilities had been subject to a delay following the company appointed to deliver them going into administration. The phase 1 utilities are now nearing completion so as to enable the relocation of Westcliff Rugby Club in early December 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.