Capital Monitoring for 2017/18 and Revised Capital
NotedScrutiny7 papers
Policy and Resources Scrutiny Committee noted this item on Thursday 30 November 2017. Below is the council's own wording, with the papers it was decided on.
- That the following recommendations of Cabinet be noted:- “1. That the actual capital expenditure position as at 30 th September 2017 of £27.790 million as shown in Section 4 and Appendix 1 of the submitted report, be noted. 2. That the financial position of the Capital Programme as at 30 th September 2017, as set out in Section 5 of the report, be noted. 3. That the proposed changes to the Capital Programme as set out in Appendix 6 to the report, be approved. 4. That the revised Capital Programme for 2017/18 to 2020/21 resulting from these changes, as set out in Appendix 7 to the report, be approved.” Note:-This is a Council Function Executive Councillor :- Lamb
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
Summary Executive Summary of Capital of Capital Expenditure toExpenditure at 30th end of December September 2008 2017 - Expected Outturn Appendix 1 Original Budget Revised Budget Actual Forecast outturn Forecast Variance to 2017/18 Revisions 2017/18 2017/18 2017/18 Year End 2017/18 % Variance £000 £000 £000 £000 £000 £000 Chief Executive 6,400 17,694 24,094 13,097 17,464 (6,630) 54% People 13,582 3,127 16,709 2,617 9,278 (7,431) 16% Place 48,140 (5,480) 42,660 10,078 28,984 (13,676) 24% Housing Revenue Account 8,610 3,498 12,108 1,998 10,608 (1,500) 17% 76,732 18,839 95,571 27,790 66,334 (29,237) 29%
Council Approved Original Budget - February 2017 76,732
Chief Executive amendments 18,352 People amendments (1,041) Place amendments (310) HRA amendments 4,864
Carry Forward requests from 2016/17 7,040 Accelerated Delivery requests to 2016/17 (856) Budget re-profiles (June Cabinet) (11,927) Actual compared to Revised Budget spent is £27.790M or New external funding 2,717 29% Council Approved Revised Budget - June 2017 95,571 Appendix 2
Capital programme Delivery Cummulative Capital Expenditure 2013/14 to 2017/18
Follow Policy and Resources Scrutiny Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.