Policy and Resources Scrutiny Committee, Thursday 30 November 2017 at 6.30pm

Transport Review (Delivery Models)

Noted Scrutiny 2 papers

Policy and Resources Scrutiny Committee noted this item on Thursday 30 November 2017. Below is the council's own wording, with the papers it was decided on.

Item532

Resolved

- That the following decisions of Cabinet be noted:- “1. That the following key elements to enable procurement activities to commence around this passenger transport review, in parallel with completing the policy consultation with users, be approved: (a) Procure a partner to develop a ‘For Profit’ JV partnership as the recommended operating model for providing all its passenger transport services; (b) Use a full procurement procedure (either competitive dialogue or open procedure) to procure a partner to develop a ‘For Profit’ JV partnership as opposed to contracting directly with a local authority owned company under Regulation 12 (the old teckal arrangements); (c) Implement the new service from 1 st August 2019 based on the time table set out in paragraph 6.2 of the submitted report; (d) Grant a tender exemption to extend existing contracts, based on the understanding that market conditions and potential legislative changes have hindered the Council’s ability to procure a partner to develop other types of JV partnership. 2. That a further report be presented to Cabinet in January 2018 that will provide details of the confirmed procurement procedure to procure a partner to develop the JV partnership.” Note: This is an Executive Function Executive Councillor: Moring
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Policy and Resources Scrutiny Committee

Purpose of report

1.1The pupose of this report is to seek approval to progress this review to procurement stage to identify a preferred partner

1.2In order to commence procurement it is critical that the Council has an agreed position on the type of operating model it wants passenger transport to operate under in the future. The report sets out the options that were considered and seeks Members’ agreement to the preferred operating model

1.3The report also details an indicative procurement timescale associated with procuring a partner for the preferred operating model and implementation date of the new service. To achieve these dates a number of approvals are sought, specifically around the extension of existing contracts and the report seeks Members’ agreement to these

1.4As part of this review, a consultation on the recommended policy changes was also undertaken with stakeholders, parents/carers and service users which will be presented for approval in a separate Cabinet report. In regards the transport operating model there will be two parts:

a) Part 1 – The purpose of this report is: (i) to update members on the transport review and seek members’ approval on the preferred operating model.

b) Part 2 – Subject to approval with the recommendations above, a further report is to be presented to Cabinet in January 2018 that will provide details of: (i) how the agreed Joint Venture (JV) will operate on a day to day basis (ii) confirmed procurement procedure to procure the JV partnership – competitive dialogue or open procedure

Page 1 of 14 Report No 2. Recommendations

2.1That the following key elements are agreed to enable procurement activities to commence around this passenger transport review, in parallel with completing the policy consultation with users. Approval is requested for the Council to:

2.1.1 Procure a partner to develop a ‘For Profit’ JV partnership as the recommended operating model for providing all its passenger transport services

2.1.2 Use a full procurement procedure (either competitive dialogue or open procedure) to procure a partner to develop a ‘For Profit’ JV partnership as opposed to contracting directly with a local authority owned company under Regulation 12 (the old teckal arrangements)

2.1.3 Implement the new service from 1st August 2019based on the time table set out in 6.2 below

2.1.4 Grant a tender exemption to extend existing contracts, based on the understanding that market conditions and potential legislative changes have hindered the Council’s ability to procure a partner to develop other types of JV partnership

Next Steps

2.1.5 Subject to approval with the recommendations above, a further report to be presented to Cabinet in January 2018 that will provide details of the confirmed procurement procedure to procure a partner to develop the JV partnership

Background

3.1The Council currently provides transport to adults and childrens across various service areas. The cost for this provision is estimated to be circa £2.1m per annum which is split between nine external contractors and the services provided in-house (this cost also includes the internal transport team). Contracts across the service areas are close to their expiry dates, having been extended as far as possible to enable the transport review to be undertaken. New procurement arrangements are therefore required in the near future to replace the existing contracts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Passenger Transport Report: Operating Model Options ExploredAppendix A 44 KB Download
PDF
Transport Review (Delivery Models)Report 212 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

21 of 35 attended
BA
Councillor Brian AylingChair, present
DK
Councillor Derek KenyonVice-Chair, apologies, sent representative
BA
Councillor Bernard ArscottCommittee Member, apologies, sent representative
DB
Councillor David BurzottaCommittee Member, present
MD
Councillor Meg DavidsonCommittee Member, present
NF
Councillor Nigel FolkardCommittee Member, present
DG
Councillor David GarstonCommittee Member, present
IG
Councillor Ian GilbertCommittee Member, present
RH
Councillor Roger HadleyCommittee Member, present
DJ
Councillor Derek JarvisCouncillor, present
DM
Councillor David McGloneCommittee Member, present
JM
Councillor Judith McMahonCommittee Member, present

All 35 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Transport Review (Delivery Models)This decision
  2. Transport Review (Policy)Decided
  3. Transport Review (Policy)Approved
  4. Transport Review (Delivery Models)Approved

More from Southend-on-Sea Policy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Minutes of the Meeting held on Thursday, 13th February 2025That the minutes of the meeting of the Committee held on Thursday, 13 th February 2025 be confirmed as a correct reco... Decided Open
31 Mar 2025 Additional Budget Considerations - 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Minutes of the Meeting held on Thursday, 30th January 2025That the minutes of the meeting of the Committee held on Thursday, 30 th January 2025 be confirmed as a correct recor... Decided Open
13 Feb 2025 Corporate Performance Report Q3 2024/25 (October to December 2024) including Corporate Delivery Plan Actions update Q3 2024/25That the report to Cabinet be noted. Note: This is an Executive function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Approval of the Annual Procurement Plan for 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor P Collins (Portfo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies