That ENFORCEMENT ACTION be AUTHORISED to secure the installation of permanent obscure glazing to the north and south balconies in accordance with approved plan b500 and condition 3 of appeal decision APP/D1590/W/16/3144896 dated 18th May 2016. The authorised enforcement action to include (if/as necessary) the service of an Enforcement Notice under Section 172 of the Act or a Breach of Condition Notice and the pursuance of proceedings whether by prosecution or injunction to secure compliance with the requirements of the Enforcement Notice or Breach of Condition Notice. When serving an Enforcement or Breach of Condition Notice the local planning authority must ensure a reasonable time for compliance. In this case a compliance period of 8 weeks is considered reasonable for the installation of suitable obscured glass. Taking enforcement action in this case may amount to an interference with the owners’ and/or occupiers’ Human Rights. However, it is necessary for the local planning authority to balance the rights of the owners and/or occupiers against its legitimate aims to regulate and control land within its area. In this particular case it is considered reasonable, expedient, and proportionate and in the public interest to pursue enforcement action on the grounds set out in the formal recommendation.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
3.1On 16th January 2017 an enforcement case was opened following a complaint that the property did not comply with planning conditions requiring that the balconies be fitted with obscure glazed side screens pursuant to planning permission having been granted on appeal by the Planning Inspectorate in 2016 including for modified balconies to be created on the dwelling’s north and south elevations. The original dwelling was granted planning permission in 2010. The planning application history is set out in section 6 of this report.
3.2On 30th March 2017 Enforcement staff emailed the planning agent asking when the required screens would be installed.
3.3On 3rd April 2017 Enforcement staff received an email from the property owner advising that access works on site would be completed soon to enable scaffolding to be erected in order to install the screens. The owner further stated that “The glazed screens have been surveyed by a specialist London glass company and will be installed soon”
3.4On 26th July 2017, following further complaints, Enforcement staff emailed the property owner asking for an update.
3.5On 3rd August 2017 Enforcement staff received an email from the property owner who apologised for the delay but explained the enabling works had been delayed due to contractor holidays but anticipated the scaffolding to be in place in September 2017.
3.6On 27th September 2017 following further contact from complainants, Enforcement staff again emailed the property owner asking for a detailed update on timings for the installation of the obscure glazed balcony sides and reminding the owner of the terms of his planning permission and warning that enforcement action would be considered to seek resolution.
3.7On 4th October 2017 Enforcement staff received an email from the property owner advising that the property was occupied on a part time basis. He further advised that, following a meeting with the relevant contractors, assurances had been given that the screens would be installed within 4 weeks. 3.8 On 30th October 2017 following a series of email exchanges between the owner and Enforcement staff, the owner advised that the scaffolding would be erected the following week and other trades would complete pre installation works for the screens that week.
3.9On 21st November 2017 Enforcement staff emailed the property owner asking what stage had been reached with regards to the balcony screen installation.
3.10On 26th November 2017 Enforcement staff received an email from the property owner advising completion of works on 4th & 5th December 2017.
3.11On 7th December 2017 Enforcement staff received an email from the property owner advising the glazed screens had been installed to the balconies.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.