Draft Capital Investment Programme 2019/20 to 2023/24

Approved Executive 6 papers

Cabinet approved this item on Thursday 17 January 2019. Below is the council's own wording, with the papers it was decided on.

Item610

Resolved

That the current approved programme for 2019/20 to 2021/22 of £153.1m as set out in Appendix 1 to the submitted report, be noted. 2. That the Capital Investment Strategy for 2019/20 to 2023/24, as set out in Appendix 2 to the report, be approved. 3. That the following be approved: ( i ) New schemes and additions to the Capital Investment Programme for the period 2019/20 to 2023/24 totalling £14.5m for the General Fund and £20.8m for the Housing Revenue Account (Appendix 6 to the submitted report); (ii) Schemes subject to external funding approval for the period 2019/20 to 2020/21 totalling £3.0m (Appendix 6 to the report); (iii) Schemes subject to viable business cases for the period 2019/20 to 2021/22 totalling £48.6m (Appendices 6 and 7 to the report). 4. That it be noted that the changes to the approved Programme will result in a proposed Capital Investment Programme of £177.0m for 2019/20 to 2023/24, as set out in Appendix 7 to the report, of which £70.7m is supported by external funding. 5. That it be noted that a final review is being undertaken on the 2018/19 projected outturn and the results will be included in the report to Cabinet on 12 February 2019. Reasons for decision: The Capital Investment Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s ambition and desired outcomes or enhance the Council’s infrastructure. Other options: The Capital Investment Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects. Note: This is an Executive Function save that approval of the final budget following Cabinet on 12 February 2019 is a Council Function. Referred direct to all three Scrutiny Committees Cabinet Member: Cllr Lamb
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1The purpose of this report is for Members to consider a draft programme of capital investment for the period 2019/20 to 2023/24 that can be submitted to Council for approval.

Recommendations

That the Cabinet:

2.1Note the current approved Programme for 2019/20 to 2021/22 of £153.1m (Appendix 1);

2.2Consider and approve the Capital Investment Strategy for 2019/20 to 2023/24 (Appendix 2);

2.3Consider and approve the proposed:

(i) new schemes and additions to the Capital Investment Programme for the period 2019/20 to 2023/24 totalling £14.5m for the General Fund and £20.8m for the Housing Revenue Account (Appendix 6);

(ii) schemes subject to external funding approval for the period 2019/20 to 2020/21 totalling £3.0m (Appendix 6);

(iii) schemes subject to viable business cases for the period 2019/20 to 2021/22 totalling £48.6m (Appendices 6 and 7);

2.4Note the changes to the approved Programme will result in a proposed capital investment programme of £177.0m for 2019/20 to 2023/24 (Appendix 7) of which £70.7m is supported by external funding;

Draft Capital Investment Programme 2019/20 Page 1 of 13 Report No: SD 09 to 2023/24 2.5 Note that a final review is being undertaken on the 2018/19 projected outturn and that the results will be included in the report to Cabinet on 12 February 2019;

2.6Refer this report as approved to all Scrutiny Committees and then to Budget Cabinet on 12 February 2019.

Background

3.1Capital expenditure is defined as expenditure incurred on the enhancement, acquisition or creation of assets needed to provide services, such as houses, schools, vehicles etc. This is in contrast to revenue expenditure which is spending on the day to day running costs of services such as employee costs and supplies and services. Capital grants, borrowing and capital receipts can only be spent on capital items and cannot be used to support the revenue budget. However, it should be noted that revenue funding can be used to support capital expenditure.

3.2Under the Local Government Act 2003, from 1 April 2004, each authority can determine how much it can borrow within prudential limits (unsupported borrowing). The Government does have powers to limit the aggregate for authorities for national economic reasons, or for an individual authority.

3.3Unsupported borrowing is not specifically financed by capital grant so any unsupported borrowing undertaken is financed from the total available resources to the Council from both grant and Council Tax.

4 Capital Investment Strategy

4.1Each year the Council agrees a Capital Investment Strategy that sets out the framework for controlling and monitoring the Capital Investment Programme. The Capital Investment Strategy is a key document for the Council. It sets out the processes and policies relating to capital expenditure and investment and includes reference to other key documents of the authority which influence capital investment such as the Medium Term Financial Strategy (MTFS) and the Corporate Asset Management Strategy (CAMS).

4.2The capital investment programme is prepared and developed in accordance with the Council’s Capital Investment Strategy, which is attached as Appendix 2 to this report. In turn, the Capital Investment Strategy has been written in the context of Southend 2050 and the five themes and all capital investment is therefore driven by the aim of contributing to the delivery of the ambition and the desired outcomes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
to Appendix 2: Capital Investment PolicyAppendix 1 70 KB Download
PDF
to Appendix 2: Capital Investment Strategy: links to other corporate strategies and plansAppendix 2 33 KB Download
PDF
to Appendix 2: Specific risks and their proposed mitigationAppendix 3 45 KB Download
PDF
Approved Capital Investment Programme: November 18Appendix 1 226 KB Download
PDF
Capital Investment Strategy 2019-20 to 2023-24Appendix 2 173 KB Download
PDF
Draft Capital Investment Programme 2019/20 to 2023/24Report 144 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 24 attended
JL
Councillor John LambChair, present
JC
Councillor James CourtenayVice-Chair, present
HB
Councillor Helen BoydCommittee Member, present
TC
Councillor Tony CoxCommittee Member, present
MF
Councillor Mark FlewittCommittee Member, present
AM
Councillor Andrew MoringCommittee Member, present
LS
Councillor Lesley SalterCommittee Member, present
AG
Alison GriffinOfficer, in attendance
JW
John WilliamsOfficer, in attendance
SL
Simon LeftleyOfficer, in attendance
AL
Andrew LewisOfficer, in attendance
JC
Joe ChestertonOfficer, in attendance

All 24 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Draft Capital Investment Programme 2019/20 to 2023/24This decision
  2. Financial Performance Report for September 2025 (Period 6) - Changes to the Capital Investment ProgrammeApproved
  3. Minutes of Transport, Capital and Inward Investment Working Party held on Thursday 7th January 2021Noted
  4. Minutes of Transport, Capital and Inward Investment Working Party held on Thursday 7th January 2021Decided
  5. Minutes of Transport, Capital and Inward Investment Working Party held on Thursday 18th February 2021Decided
  6. Minutes of the meeting of Transport, Capital, Inward Investment Working Party held on 21st November 2019Decided

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies