That the 2018/19 and the Quarter 3 updates outlined in Appendix 1 to the submitted report, be noted. Reasons for decision: To receive the Corporate Risk Register. Other options: None. Note: This is an Executive Function Referred direct to: all three Scrutiny Committees. Cabinet Member: Cllr Lamb
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
Southend-on-Sea Borough Council Agenda Item No. Report of Chief Executive and Town Clerk To Cabinet On 17 January 2018
Report prepared by: Louisa Thomas – Data & Insights Analyst
2018-19 Corporate Risk Register - Quarter 3 update Relevant Scrutiny Committee(s): Policy & Resources, People and Place Scrutiny Committees
Cabinet Member – Cllr Lamb A Part 1 Public Agenda Item
1 Purpose of Report 1.1 To consider the 2018/19 Corporate Risk Register Quarter 3 update.
2 Recommendations 3 That Cabinet considers the 2018/19 Corporate Risk Register and the Quarter 3 updates outlined in Appendix 1.
3.1Corporate Risk Register 2018/19 3.1.1 The Council’s Corporate Risk Register sets out the key risks to the successful delivery of the Council’s corporate aims and priorities and outlines the key controls and actions to mitigate and reduce risks, or maximise opportunities.
3.1.2 Updates on the Corporate Risk Register are reported to CMT quarterly and to Cabinet twice a year in June and January.
3.1.3 The Corporate Management Team (CMT) has undertaken a review of the current content. This in the context of the proposed work to further develop and align work on risk across the Council so that the approach to risk management is better embedded, supports the governance framework, the transformation agenda and integrated decision making.
3.1.4 The Corporate Management Team have considered the new wording for Corporate Risk 2, and its risk action (number 4). To reflect the transition period between our existing recruitment contract and new recruitment contract with Hays.
The rewording of Corporate Risk 2 – Recruiting and retaining staff. This has been amended from: ‘Risk that failure to have the appropriate staffing resources, with the right skills, will lead to a failure to achieve the Council’s ambitions’. To – ‘Risk that the Council will not have the appropriate staffing resources, with the right skills, resulting in part, from a failure to effectively manage the transition from our existing recruitment partner to the new partner, will lead to a failure to achieve the Councils ambitions’
The rewording of the risk action 4, under Recruiting and retaining staff, has been amended from: ‘Develop a framework contract to deliver profession/interim resources to supplement the Reed contract’. To – ‘Develop a framework to deliver professional recruitment resources, including a robust implementation plan which is jointly owned by SBC and Hays and which is appropriately managed’.
3.1.5 The format of the Corporate Risk Register follows a 3 stage process:
1st stage: An ‘inherent score’ with the risk assessed with no controls, assurance or actions in place.
2nd stage: The ‘current score’ where the risk is assessed with controls, assurances and progress against identified actions. The current score is adjusted in light of progress against actions.
3rd stage: The target score which is the risk with the controls, assurances and actions, as if they have been completed
The current score is then adjusted in light of progress against actions.
3.1.6 Updates on the Corporate Risk Register are reported to CMT quarterly and now to Cabinet every 6 months.
3.1.7 Deputy Chief Executives and Directors ensure service specific risks are managed within their departments, within service plans and in accordance with the risk management strategy and processes. ‘Red’ rated risks with corporate implications can be escalated to CMT via Corporate Directors. Actions for all these risks are updated and reviewed by Departmental Management Teams.
3.1.8 Operational risks, managed within departments, are also assessed as part of reviews undertaken by Internal Audit and project risks are monitored by the CMT where applicable.
3.1.9 A review of the Council’s corporate risk framework will be undertaken in the New Year with a view to ensuring the approach to risk management supports the Southend 2050 and the transforming together programme.
4 Corporate Implications:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.