CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Southend-on-Sea Borough Council
Cabinet, Tuesday 25 February 2020 at 2.00pm

Southend Crematorium Refurbishment

Decided Executive 3 papers

Cabinet decided this item on Tuesday 25 February 2020. Below is the council's own wording, with the papers it was decided on.

Item861

Resolved

The Cabinet considered a report of the Deputy Chief Executive and Executive Director (Growth and Housing) highlighting the limited remaining operational lifespan of the cremators and associated equipment at Sutton Road Crematorium and the potential use of electric cremators along with the funding requirements for the refurbishment of the facility.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To highlight the limited remaining operational lifespan of the cremators and associated equipment at Sutton Road Crematorium.

1.2To seek approval on the approach to be taken regarding securing cremation services over the next twenty-five years.

1.3To highlight the potential use of electric cremators as an alternative to gas cremators and the potential benefits these can have in reducing carbon emissions.

1.4To highlight the existing funding within the capital programme for refurbishing the facility, subject to business case, and the requirement for additional funding if electric cremators are the preferred option.

Recommendations

2.1Agree to continue to provide crematorium facilities within Southend-on- Sea.

2.2Note the problems with the existing facilities as set out in Appendix 1.

2.3Note that without the replacement of the cremators and works to the building the provision of a crematorium service in the short to medium term will not be possible.

Refurbishment of Crematorium and Replacement of Page 1 of 8 Report Number: 20/010 Cremators 2.4 Note the potential environmental benefits that the installation of electric cremators could bring and the additional capital expenditure that this would require (exact level of investment to be determined).

2.5Agree that the option of electric cremators and other options that would have environmental benefits can be considered during the project development.

2.6Note the predicted cost to fund the replacement of the cremators, associated plant and building refurbishments as outlined in paragraph 6.3.

2.7Delegate authority to the Executive Director of Neighbourhoods and Environment to carry out the refurbishment and replacement of the cremators.

Background

3.1The Crematorium at Southend-on-Sea was constructed in November 1953 and contained three cremators. In 1986/87 the cremators were replaced and the number increased to six. In 1999/2000 the cremators were replaced again but the number reduced to five, this replacement was as a result of changes in legislation, which meant the existing cremators could no longer be used.

3.2In 2009 after an inspection of the chimney, it was reported that the structure was starting to decline. The condition of the stack was monitored, and the condition was confirmed as declining. In 2018 the structure of the stack had declined to such an extent that temporary props needed to be installed. At this time, plans were also considered for its rebuild. However, due to other issues with the cremators and plant, it was decided to postpone any works and to consider a more coordinated project.

3.3In April 2010 the cremation facilities were reviewed again, and the number of cremators reduced to three. However, at this time one of the cremators was replaced with a larger cremation unit to facilitate the increasing number of requests to accommodate larger coffins. At this time an abatement system was installed to address mercury emissions.

3.4In 2010, works were also undertaken to some of the front of house facilities, namely the chapels.

3.5The change in cremator units and associated plant over the years, including the need to install a refrigeration unit has resulted in the layout of the building, especially back of house, becoming fragmented causing inefficient operation and problems such as lack of suitable storage for cremated remains.

3.6Surveys have raised a number of problems with the existing facilities including structural problems with the buildings and two of the cremators that are at end of life and no longer have guaranteed supported by the manufactures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
8: Appendix 1: Crematorium Refurbishment.docxAppendix 20 MB Download
PDF
8: Appendix 2: Crematorium RefurbishmentAppendix 48 KB Download
PDF
Southend Crematorium RefurbishmentReport 116 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 28 attended
SB
Sarah BakerOfficer, expected
AG
Alison GriffinOfficer, in attendance
JW
John WilliamsOfficer, in attendance
SL
Simon LeftleyOfficer, expected
AL
Andrew LewisOfficer, in attendance
AA
Andrea AthertonOfficer, expected
JC
Joe ChestertonOfficer, in attendance
JR
Joanna RuffleOfficer, in attendance
CG
Colin GambleOfficer, in attendance
IG
Councillor Ian GilbertChair, present
RW
Councillor Ron WoodleyVice-Chair, present
TH
Councillor Trevor HarpCommittee Member, present

All 28 on the meeting page

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies