The Cabinet considered a report of the Deputy Chief Executive and Executive Director (Growth & Housing) presenting a revised and updated Local Development Scheme (LDS), which set out the future programme for the preparation of the Southend New Local Plan. Recommended: 1. That, in order to take forward the in a timely, coordinated and efficient manner the updated and revised Local Development Scheme (set out at Appendix 1 to the submitted report), be approved. 2. That authority be delegated to the Deputy Chief Executive and Executive Director Growth and Housing, in consultation with the Cabinet Member for Environment and Planning, to agree any future updates to the Local Development Scheme (Appendix 1 to the report) as required. Reasons for decision: To ensure the expeditious production of a New Local Plan for Southend and associated evidence base to manage and guide future growth and development in the Borough and its hinterland in a positive and timely manner, where the Council has control of decision making in the public interest as representatives of the local community. Other options: 1. The failure to prepare a new local plan for Southend would result in its current plans becoming increasingly out of date and the Council becoming increasingly unable to positively influence the scale, nature and location of development within the Borough. 2. An out-of-date local plan also brings the potential risk of “planning by appeal” with the responsibility for decision making increasingly being passed from the Council and the local community to the Planning Inspectorate and the Secretary of State, as the Council’s existing local plan becomes further out of date. Note: This is a Council Function Eligible for call-in to: Place Scrutiny Committee Cabinet Member: Cllr Mulroney
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To seek Member approval of a revised and updated Local Development Scheme (LDS) which sets out the future programme for the preparation of the Southend New Local Plan.
Recommendations
2.1In order to take forward the Southend New Local Plan in a timely, coordinated and efficient manner that Members approve the updated and revised Local Development Scheme (Appendix 1).
2.2That Members agree to delegate authority to the Deputy Chief Executive and Executive Director Growth and Housing, in consultation with the Cabinet Member for Environment and Planning, to agree any future updates to the Local Development Scheme (Appendix 1) as required.
Background
3.1Local Development Scheme
3.1.1 The Local Development Scheme (LDS) sets out a timetable for preparing and reviewing the Southend New Local Plan and related Development Plan documents to provide:
an up-to-date statutory basis for determining planning applications (unless material considerations indicate otherwise); and a long-term spatial planning framework for the Borough’s development, within which the Council, other agencies and key stakeholders can coordinate their investment programmes.
Report Title: Southend New Local Plan Report Number: 21/001 Revised and Updated Local Development Scheme 3.1.2 In the light of the proposed changes to the preparation of the Southend New Local Plan revisions will be required to the Local Development Scheme.
3.1.3 Appendix 1 sets out a revised and updated Southend Local Development Scheme to facilitate the preparation of the Southend New Local Plan.
3.2Southend New Local Plan Preparation
3.2.1 In early 2019 an ‘Issues and Options’ document was published for public comment as part of the first stage in the preparation of the Southend New Local Plan. Details of feedback to the Issues and Options consultation were published in August 2019 in a Consultation Report 1 .
3.2.2 This consultation feedback continues to be invaluable in informing the next stage of local plan preparation, ‘Refining the Options’, proposed for summer 2021. Thereafter, the Plan will be subject to further consultation stages in 2022 and 2023, in accordance with statutory procedures before being submitted to be examined by an independent Inspector.
3.2.3 The forthcoming stages of local plan preparation are depicted in the Figure 1 below. Ongoing plan preparation may also need to embrace any changes that are legislated in response to the Governments recently published White Paper, ‘Planning for the Future’2. The White Paper proposes a package of measures which seek to radically reform the planning system including how Local Plans are prepared and presented.
Figure 1: Stages of Local Plan Preparation
Calendar Year (action listed commencing)
1 Southend New Local Plan Issues and Options Consultation Report Southend on Sea Borough Council,
August 2019 2 Planning for the Future, Ministry of Housing, Communities and Local Government, March 2020
Report Title: Southend New Local Plan Report Number: 21/001 Revised and Updated Local Development Scheme 3.2.4 Once adopted the Southend New Local Plan will be a key document in guiding and facilitating new development and growth in the Borough, helping to deliver some of the key aspirations of Southend 2050 and acting as a catalyst to assist economic recovery from the Covid pandemic. When adopted, the new local plan will replace the existing suite of documents that currently comprise the Local Development Framework, including the Southend Core Strategy (2007), Development Management Document (2015) and Southend Central Area Action Plan (2018).
3.3Strategic Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.