The Cabinet considered a report of Deputy Chief Executive & Executive Director (Growth and Housing) providing an update on the progress of the HRA Land Review Phase (Lundy Close) following the Public Notice for the appropriation of land on the North Site of Lundy Close and set out the next steps for this development for consideration..
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To update members on the progress of the HRA Land Review Phase (Lundy Close) following the Public Notice for the appropriation of land on the North Site of Lundy Close and to agree the next steps for this development following the consideration of the responses received.
Recommendations
2.1To note responses received following a Public Notice and the considerations and mitigations in regards to these as detailed in section 3.6-3.14 of this report.
2.2To agree to proceed with the development of the north site of Lundy Close for Council Housing based on the conclusion detailed in section 3.15 of this report.
Background
3.1Cabinet on 17th January 2019 considered and agreed the recommendations of a report titled Future Phases of Affordable Housing Development Programme Update which outlined Phases 3 and 4 of the HRA Land Review project. This detailed Phase 3 in Shoeburyness ward and Phase 4 in St Laurence ward (Lundy Close).
3.2Cabinet on 15th September 2020 considered a further report entitled HRA Land Review Phase 4 (Lundy Close) Update which contained an Options Appraisal for the development of the sites in Lundy Close for Council Housing. Cabinet agreed to proceed with the proposed Option 3 which would see the north site in Lundy Close developed and would yield between 9-12 council homes.
HRA Land Review Phase 4(Lundy Close) Cabinet Report Report Number Fig 1 – North site in Lundy Close
3.3Following Cabinet agreement to proceed with the development of the north site in Lundy Close, and in keeping with advice from the Council’s Legal team, the Strategic Housing team published a Public Notice to advertise the appropriation of land as required by section 122 of the Local Government Act 1972. This is a necessary procedural step as, even though the Site is held as HRA land, it is possible that it has become open space as well, due to its use by the public. Therefore a Public Notice in the local paper was published on weeks commencing 10th and 17th November 2020 with responses considered for up to 28 days after the final publication.
3.4The advert advised people who objected to the appropriation of the land, to send their objections to the Council in writing, and provided a contact and address.
3.5Public Notice Responses
3.5.1 15 responses to the Public Notice were received in the 28 days following publication. 9 of these were written by Lundy Close residents (1 respondent signed a letter written by another resident to express their objection), 2 were from ward members, 2 objections were from individuals who live within the borough but not in Lundy Close, and 2 individuals did not express their connection to Lundy Close. 3.5.2 Type of Respondent Count Lundy Close Residents 9* Ward Members 2 Individuals who live within the 2 borough but not in Lundy Close Unknown 2 Total 15 *1 respondent signed a letter written on their behalf by another resident
HRA Land Review Phase 4(Lundy Close) Cabinet Report Report Number 3.5.3 In terms of a response rate to the Public Notice, there are 85 properties in Lundy Close, and 9 residents in total sent an objection to the Council, therefore the Lundy Close resident response rate is 11%.
3.6Public Notice Response Themes
3.6.1 A number of responses received were not in regards to the appropriation of the land for housing and were focused on the design and future planning considerations however they will be covered in detail within this report. The table below provides an overview of the key themes of the responses received to the Public Notice.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.