- That planning permission for the application be REFUSED on grounds that the development will not secure the necessary contribution for affordable housing, secondary education, highways works and RAMS and that, as such, the proposal would be unacceptable and contrary to the National Planning Policy Framework (2023), Policies KP2, KP3, CP3, CP6 and CP8 of the Core Strategy (2007) and Policies DM1, DM3, DM7 of the Development Management Document (2015) and the Essex Coast Recreational Disturbance Avoidance Mitigation Strategy (RAMS) Supplementary Planning Document (2020). .
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
Proposal: Modification of planning obligation (Section 106 agreement) dated 26th February 2021 pursuant to application 20/01227/OUTM dated 26.02.2021 (as amended by 21/01887/DOV5) to modify the affordable housing obligations
Address: Land Between Barge Pier Road and Ness Road Shoeburyness Southend-on-Sea Essex
Applicant: Bellway Homes Limited (Essex)
Agent: Giuseppe Cifaldi of Savills
Consultation Expiry: 08.08.2024
Expiry Date: 23.08.2024
Case Officer: Abbie Greenwood
Supporting information: Application Form dated 11.03.2024 Cover Letter from Savills dated 11th March 2024 Financial Viability Assessment by Arebray reference FV2 dated January 2024 a) That the Council enters into a Legal Agreement by Recommendation: Deed of Variation under Section 106A of the Town and Country Planning Act 1990 (as amended) to allow the following modifications to the Legal Agreement dated 26th February 2021 pursuant to planning permission 20/01227/OUTM (as amended by 21/01887/DOV5) to allow:
i. The affordable housing contribution to be amended from 30% units of affordable housing on site (65 units) – with a 60/40 tenure split (39 social/affordable rent and 26 intermediate units) to 21 units all of which are affordable rented. ii. The inclusion of a Late-Stage Viability Review Mechanism in regard to Affordable Housing Provision (60% of any surplus).
b) In the event that a deed of variation as outlined in recommendation a) above has not been completed by 23 August 2024 or an extension of this time as may be agreed by the Executive Director (Environment and Place), Director of Planning and Economy or Service Manager - Development Management and Enforcement, authority is delegated to the Director of Planning and Economy or Service Manager - Development Management and Enforcement, to refuse planning permission for the application on grounds that the development will not secure the necessary contribution for affordable housing, secondary education, highways works and RAMS and that, as such, the proposal would be unacceptable and contrary to the National Planning Policy Framework (2023), Policies KP2, KP3, CP3, CP6 and CP8 of the Core Strategy (2007) and Policies DM1, DM3, DM7 of the Development Management Document (2015) and the Essex Coast Recreational Disturbance Avoidance Mitigation Strategy (RAMS) Supplementary Planning Document (2020). 1 Site and Surroundings
1.1The application site consists of 2 parcels of land totalling some 8.5 hectares (ha); the larger of the two, to the west of New Barge Pier Road, is some 7.1 ha; the smaller site to the east of New Barge Pier Road is some 1.4 ha. The site is undeveloped, but access points into the site have been previously constructed. The site is relatively flat lying at 1-3m AOD (Above Ordnance Datum). The larger part of the site is roughly rectangular and is to the south of the Lidl store and to the east of dwellings in Ness Road. The smaller part of the application site is to the east of the larger site. This area is directly south of Hinguar School, to the north of the Gunners Park play area and adjacent to the rear gardens of dwellings in Ashes Road. Gunners Park is to the southeast and south of the application site and is allocated as ‘Protected Green Space’. The land to the immediate south of the main part of the site is also designated as a Local Wildlife Site (LWS), Site of Special Scientific Interest (SSSI) and Local Nature Reserve. Further south, this part of the Estuary constitutes a SSSI, Special Protection Area (SPA), RAMSAR and Local Nature Reserve. The site is mainly open scrub land with a few trees mostly along the western boundary. There are no Tree Preservation Orders (TPOs) on the site.
1.2The wider surrounding area is mixed. To the east and west of the site is predominately residential. To the north of the site are commercial uses and a school and the land to the south is undeveloped open space with the estuary beyond.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.