Procurement of Additional Technology Services for MySouthend Phase 2
ApprovedExecutive1 paper
AI summarySouthend Cabinet approved varying the Jadu contract to continue MySouthend Phase 2 development, taking cumulative spend past the £500k key decision threshold. The variation's value is in a confidential appendix not supplied.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedVariation with Jadu for MySouthend Phase 2
MoneyCumulative spend over £500kVariation value held in confidential appendix
What happens nextPhase 2 development beginsBuilds on Phase 1 minimum viable product
Who it affectsResidents, businesses, visitors, officers, councillorsAll users of the MySouthend portal
What was decided
Cabinet approved varying the existing Jadu contract so third party services can continue developing MySouthend Phase 2, with the value and extent set out in the Confidential Appendix. Report 2.1
The decision is not eligible for call-in because it relates to a contract variation with a single supplier where cumulative spend exceeds £500k. Report 4.1, 7.5
Why
Phase 1 of MySouthend delivered a minimum viable product in 2024, replacing over 200 forms and integrating six back-office systems, but usability problems remain that Phase 2 is designed to address. Report 1.2, 3.2
Phase 2 planning was delayed to ensure effective integration with SUEQ for waste, and is now restarting to improve accessibility, data access, case management feedback, and highways integration. Report 1.3, 1.4, 3.3, P11
Cabinet approval is required because cumulative spend with the single supplier will exceed £500k, meeting the council's Key Decision threshold. Report 1.5, 4.1, 7.5
What happens next
Officers will enter the necessary contractual documentation to vary the Jadu contract under the existing legal and procurement framework. Report 7.1, 7.6
Phase 2 work will be funded from the approved Capital Investment Programme Budget, with skills transfer to internal council teams built in. Report 6.1, 3.3
The money
more than £500k Cumulative contract value with Jadu after the variation, triggering key decision rules Report 1.5, 4.1, 7.5
Options considered
Rejected: Do nothing and continue with the minimum viable product platform. Would slow improvements and limit skills uplift for internal teams Report 5.1
Rejected: Buy services from an alternative supplier. Would create higher costs and a longer delivery time
Implications
Financial: The variation is funded from the approved Capital Investment Programme Budget, and cumulative spend with Jadu will exceed £500k, triggering Key Decision thresholds. Report 6.1, 4.1, 7.5
Legal: The variation is a direct continuation of Phase 1 under the same legal and contractual framework, with powers drawn from the Local Government (Contracts) Act 1997, Localism Act 2011 and Local Government Act 1972; contract procedure rules are met because the variation is under 50% of the original contract value. Report 7.1, 7.2, 7.3, 7.6
Equalities: Design is guided by accessible design experts, with regular feedback from diverse user groups, and the platform will continue to offer alternative contact channels such as telephone support. Report 10.1, 10.2
Climate: Continued digitisation of paper forms and smarter case management may reduce officer and contractor travel, supporting the council's sustainability aims. Report 9.1
Who and where
Residents using MySouthend for council services and enquiries Report 1.4, 3.1, 3.3
Local businesses and visitors interacting with the portal Report 3.1, 10.1
Council officers and councillors who handle enquiries through the system Report 3.1, 3.3
Supplier Jadu, holder of the MySouthend core platform contract Report 1.1, 1.5
Timeline
2023: Original Jadu contract for MySouthend procured Report 1.1
January 2025 (originally planned): Phase 2 start was originally scheduled but was delayed to allow SUEQ waste integration Report 1.2, 1.3
20/10/2025: Report authorised for publication by the S151 Officer, Monitoring Officer and Cabinet Member Report P35
10/11/2025: Cabinet decision date
End March 2027: Current Jadu contract runs to this date Report 1.1
Plain English for the jargon
MySouthend: Southend-on-Sea Borough Council's core resident-facing digital portal for accessing services
MVP (minimum viable product): An initial working version of a digital service with enough features to be usable, delivered in Phase 1
Key Decision: A decision above council-set financial thresholds, here triggered by cumulative contract spend exceeding £500k with a single supplier
Phase 2: The next stage of MySouthend development, adding enhanced functionality, better accessibility, and further back-office integration
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55
Resolved
That the contract variation for third party services by Jadu to enable the continuation of the development of MySouthend , be approved. The value and extent of the variation is set out in the Confidential Appendix. This decision is not eligible for call-in.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1MySouthend is the core resident-facing portal of the Council which was procured in 2023 via a contract with the supplier: Jadu, which runs to end March 2027.
1.2The previous unstable MySouthend platform was replaced in 2024. The intention was to enhance the functionality and integration with back-end solutions by means of a Phase 2, originally planned to start in January 2025.
1.3Phase 2 planning was delayed by the need to ensure an effective integration with SUEZ for Waste. It is therefore only now that the planning for Phase 2 of MySouthend has picked up again.
1.4The additional work needed to support the delivery of MySouthend Phase 2 aims to improve accessibility and access to data within the system. Making these changes will enable us to tackle the day-to-day frustrations people experience in using MySouthend.
1.5This report seeks Cabinet approval to vary the existing contract with the supplier of the core Jadu platform used for MySouthend. The additional expenditure will take the cumulative spend to more than £500k and requires a Key Decision to proceed.
Recommendations
It is recommended that Cabinet:
2.1Approve the contract variation for third party services by Jadu to enable the continuation of the development of MySouthend. The value and extent of the variation is set out in the Confidential Appendix. 3 Background
3.1The MySouthend platform is intended to be a critical digital entry point for services to residents, businesses, officers, and Councillors, enabling streamlined access to council services and case management.
3.2Phase 1 delivered a minimum viable product (MVP). This delivery included replacement of over 200 forms and workflows; as well as integration with six back-office systems. There remain challenges to ease of use and legacy processes which cause frustration for residents, which are planned to be addressed through Phase 2.
3.3Phase 2 will build on the original implementation and focus on modules and work packages which will bring the following benefits:
• Improved resident experiences via enhanced functionality, and workflows • Simplifying the way in which appointments scheduling and payments work to improve the resident experience. • Modernise legacy processes, to improve service. • Improving feedback in enquiries case management – enhancing visibility and tracking of resident and councillor enquiries. • Further strengthening our data protection and access controls. • Integration with the highways system, thereby improving the responses to queries and complaints and enhancing the communication to residents. • Skills transfer to internal teams which will enhance the internal ability to continue a programme of improvement.
3.4The project aligns with the council’s digital transformation strategy, particularly the priorities around “Data, Insight & Artificial Intelligence” and “Service Digitisation & Intelligent Automation” and supports the broader Council “Connected and Smart” strategic theme.
4 Reasons for Decisions
4.1Approval to spend more than £500k with a single supplier is required as a key decision.
4.2This additional investment is required to unlock functionality enhancement and consultancy services to enable the delivery of improved resident and visitor experience with better usability an accessibility.
5 Other Options
5.1Do nothing and continue with platform in the minimum viable product state. This option is not recommended as this will result in slower improvements and limited skills uplift for internal council teams. 5.2 Purchase services from an alternative supplier. This option would create higher costs and a longer time to deliver and so is not recommended.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.