Award of Contract for Highway, Infrastructure and Maintenance
ApprovedExecutive1 paper
AI summaryCabinet approves award of Southend highway infrastructure and maintenance contract to preferred bidder, starting 1 April 2026 for seven years with a possible seven-year extension.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedHighway infrastructure and maintenance term services contract
MoneyFinancial details withheld in Part 2 Exempt Appendix
What happens nextContract starts 1 April 2026Executive Director to finalise contract documents
Who it affectsHighway and coastal services in SouthendReplaces current Marlborough Highways contract
What was decided
Cabinet approved the award of the highway infrastructure and maintenance contract to the preferred bidder for a 7-year term from 1 April 2026, with an option to extend by a further 7 years. Report 2.1
Authority was delegated to the Executive Director for Environment and Place to finalise and enter into all necessary documentation. Report 2.1
The decision is not eligible for call-in.
Why
The current contract with Marlborough Highways Ltd ends on 31 March 2026, and the new contract is needed to continue statutory highway functions. Report 3.1, 3.2
Market engagement showed a 7-year term delivers the best efficiencies for items such as vehicle and plant depreciation, and bundling services into one contract improves coordination and reduces network disruption. Report 3.3, 3.4
The contract is needed to incorporate additional services not previously included, such as gully emptying, winter maintenance and verge maintenance. Report 3.5, 6.2
What happens next
The Executive Director for Environment and Place will finalise and sign the contract documentation. Report 2.1
The successful contractor will deliver the contract from 1 April 2026, with KPIs set from both the tender requirements and the bidder's quality submission. Report P17
The contract includes a clause to vary, transfer or terminate it in response to Local Government Reorganisation. Report 3.6
Options considered
Chosen: Award contract to preferred bidder. Tender evaluation completed under 60% Quality and 40% Cost split; preferred bidder identified. Report 3.9, 4.1
Rejected: Do not award and restart the tender process. Would need a further contract extension, risk legal challenge as original contract value exceeded, and incur additional staff and legal costs. Report 5.1
Implications
Financial: Existing service budgets for the new elements (gully emptying, winter gritting, verge maintenance) will be amalgamated into a single contract budget. The report states the overall contract cost is expected to be contained within existing service budgets. Report 6.2, 6.3
Legal: The procurement was run under the Public Contract Regulations 2015, and the contract value exceeds £500k, making this a key decision. The contract must comply with the Local Government Act 1999 best value duty and the Council's Contract Procedure Rules. Report 3.8, 7.3, 7.4
Climate: The contractor will deliver an annual carbon management plan, and the contract will introduce a new fleet of maintenance vehicles with a move to electric vehicles where possible. Report 9.1
Risk: The contract contains a clause allowing the Council to vary terms, change scope, novate, transfer or terminate the contract to respond to Local Government Reorganisation. Report 3.6
Staffing: Restarting the tender would attract further staff and legal support costs. Report 5.1
Equalities: All works give equal consideration, and officers will look for specific areas for equality improvement where possible. Report 10.1
Who and where
Residents and road users in Southend-on-Sea using the highway and coastal network Report 3.4
The current contractor, Marlborough Highways Ltd, whose contract ends on 31 March 2026 Report 3.1, 3.2
The preferred bidder and their staff, who will deliver the new contract from 1 April 2026 Report 2.1
Timeline
10th September 2025: Tender submissions received from bidders Report 1.3, 3.9
3.10.2025: Report authorised by Executive Director, S151 Officer, Monitoring Officer and Cabinet Member Report P38
31st March 2026: Current highway term services contract ends Report 3.1
1st April 2026: New contract commences for 7-year term Report 2.1
Plain English for the jargon
KPI: Key Performance Indicator, used to measure the contractor's performance.
Novate: Transfer a contract from one party to another.
Local Government Reorganisation: Structural changes to local authority boundaries or functions, which the contract allows for.
Schedule of Rates: Pre-agreed unit prices used to value work under the contract.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item56
Resolved
It is recommended that Cabinet: 1. Approves the award of the contract for highway infrastructure and maintenance to the preferred bidder. The contract will commence on 1st April 2026 for a period of 7 years with an option to extend the contract by a further 7 years. 2. Delegates authority to the Executive Director for Environment and Place to finalise and enter into all necessary documentation to facilitate this contract. This decision is not eligible for call-in.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1The current highway term service maintenance contract contractual end was 31st July 2025. This was extended via cabinet approval in July 2025 until 31st March 2026.
1.2This was due to the additional level of scope to be included within one overall contract (e.g. the inclusion of additional elements like gully emptying/winter maintenance), the finalisation of suitable contract documents delayed the initial planned release of the tender documents.
1.3Final tender submissions were received by 10th September 2025 and have been evaluated in accordance with the evaluation criteria set out in the tender documents.
1.4This report seeks authority to award the contract to the preferred bidder with the relevant delegated authority to proceed to the completion of contracts.
Recommendations
It is recommended that Cabinet:
2.1Approves the award of the contract for highway infrastructure and maintenance to the preferred bidder. The contract will commence on 1st April 2026 for a period of 7 years with an option to extend the contract by a further 7 years. 2.2. Delegates authority to the Executive Director for Environment and Place to finalise and enter into all necessary documentation to facilitate this contract.
Background
3.1The current highways contract was for a 7-year term, with the contractual option of a 3-year extension, based on performance against key indicators, which were achieved and the extension activated. A further extension was approved in July 2025, and the contract comes to an end on 31st March 2026.
3.2The current incumbent contractor is Marlborough Highways Ltd.
3.3The procurement process included early market engagement to help shape the new contract. From this process it was clear that a 7-year term would deliver the best efficiencies for key elements such as vehicle/plant depreciation etc. Therefore, it is proposed to procure a 7 plus 7-year contract term, with the extension based on contract performance and key performance indicator (KPI) outcomes.
3.4In addition, rather than multiple smaller value contracts, all elements of highway and coastal works will be delivered via one contractor. This option will deliver improved efficiencies and quality of service, support more robust contract management and further help to reduce disruption to the network by being able to effectively deliver multiple services at the same time when appropriate.
3.5The new contract also includes additional services which include gully emptying, winter maintenance, verge maintenance, and an extended level of potential professional services.
3.6The tender documents acknowledge that the Service Period will be impacted by Local Government Reorganisation, and a clause has been added that will allow the contract to maximise the efficiency and benefits of such changes. This includes varying the terms of the contract, a change of scope, the right to novate or transfer the contract and termination.
3.7Following the market engagement exercise four bidders submitted expressions of interest and following evaluation two bidders were invited to submit the required tender.
3.8The tender process was undertaken under the Public Contract Regulations 2015 as it was started prior to the release of the new Procurement Act 2023 requirements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.