Update of CIL and Cycle Network

Noted Scrutiny 1 paper

AI summarySouthend Place Overview & Scrutiny Committee notes update on CIL-funded cycle projects including completed seafront refurbishment, Bournes Green Chase track, and upcoming LCWIP consultation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the update report on cycle schemes
MoneyNot stated
What happens nextJanuary 2026LCWIP consultation due to go live
Who it affectsCyclists and pedestriansAcross Southend-on-Sea, particularly eastern and western seafront

What was decided

The committee noted the update on CIL Main Fund cycle infrastructure and the LCWIP. Report 1.1

Why

The report provides a progress update on funded cycle infrastructure projects for scrutiny oversight. Report 1.1, P2

Some sections of the network, particularly east of the pier, were in poor condition with cracked tarmac and failed drainage. Report P4

What happens next

A safety risk assessment on western seafront bus stops will be submitted in December 2025, prompted by a letter from the Minister for Roads and Buses Simon Lightwood. Report P7

Two quieter mixed traffic routes (Leigh to Southend and Southend Victoria to Shoeburyness) are due to be delivered before the end of FY 25/26. Report P9, P10

A citizens panel of around 20 members will be recruited via Your Say Southend, with invites sent w/c 24th November and first panel meetings w/c 15th December, ahead of the LCWIP consultation launching in January 2026. Report P16

Options considered

  • Chosen: Note the report

Implications

  • Other: The LCWIP forms part of the council's Capability Rating, affecting the amount of central government funding available. Report P19
  • Risk: Shared use bus boarders on the western seafront create a potential safety issue for bus users and cyclists, prompting a safety risk assessment. Report P5, P6, P7

Who and where

  • Cyclists and pedestrians using the eastern and western seafront cycle track Report P4, P5, P7
  • Residents in Southchurch, Bournes Green and Shoebury using the new 2.5km offroad cycle track Report P12, P13
  • Around 20 residents recruited to the LCWIP citizens panel Report P16
  • Bus passengers and operators on Western Esplanade Report P6, P7

Timeline

  • April 2025: Seafront cycle track refurbishment east of pier completed over two weeks. Report P5
  • w/c 24th November 2025: Invites for citizens panel to be sent out. Report P16
  • December 2025: Safety risk assessment request for western seafront bus stops to be submitted. Report P7
  • Late November / Early December 2025: Construction of Bournes Green Chase and North Shoebury Rd cycle track due to start. Report P13
  • w/c 15th December 2025: First citizens panel meetings due to take place. Report P16
  • January 2026: LCWIP consultation due to go live. Report P16
  • End of FY 25/26: Two quieter mixed traffic routes due to be delivered. Report P9, P10
  • Summer 2026: Expected completion of Bournes Green Chase cycle track. Report P13

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure.
  • LCWIP: Local Cycling and Walking Infrastructure Plan, a document identifying gaps and proposals for walking and cycling networks.
  • MMA: Methyl Methacrylate, a material used for anti-slip markings on the cycle track.
  • A13 Safer Roads Fund: A Department for Transport funded programme for safety improvements on the A13.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item46

Resolved

- That the report be noted.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Place Overview & Scrutiny Committee

Executive summary

1.1This report is to provide an update of the CIL Main Fund Enhancing Cycle Infrastructure and Cycle Network projects, including the Sea Front cycle track refurbishment, Bournes Green Chase cycle track and Local Cycling and Walking Infrastructure plan

2. Update

2.1CIL Main Fund Enhancing Cycle Infrastructure

2.1.1. Seafront Cycle Track refurbishment. East of pier – Eastern Esplanade, Thorpe Esplanade and Shoebury Common Rd. The cycle track along this section was in a poor state, years of works and repairs had left the tarmac surface missing or cracked, and many areas the drainage was no longer working to reduce pooling after heavy rainfall, as shown in Figure 1. Figure 1. Showing signs of the poor state of the cycle track.

The refurbishment took place at the beginning of April 2025. Over a two-week period, the cycle track was resurfaced using black asphalt. New lining and green anti-slip MMA (Methyl Methacrylate) rectangles with reflective cycle symbols were added to designate the cycle track from the adjacent footway. Examples can be seen in Figure 2. Figure 2. The refurbished cycle track 2.1.2. Seafront Cycle Track refurbishment. West of Pier – Western Esplanade, The Leas and Chalkwell Esplanade. The cycle track surface on west of the pier being newer than the east of the pier has not suffered such degradation to it’s surface, but a potential safety issue with the bus stops along this stretch has been highlighted as the bus stops here are classed as Shared Use Bus Boarders, this is where passengers board/alight directly from or into the cycle track as shown in Figure 3 below.

Figure 3. The bus stop and shared use bus border near Genting Casino on Western Esplanade.

Investigations into possible safety improvements around bus stops on the western section of the seafront cycle track and following recent letter from Minister for Roads and Buses Simon Lightwood a Safety Risk Assessment will be carried out. The Safety Risk Assessment request will be submitted in December 2025. Bus operators mounting the kerb and driving into the cycle track to ensure that passengers are boarding/alighting onto the footway will also be assessed in this request. The outcome of this Safety Risk Assessment will inform potential designs into removing risk for bus users and cyclists alike on this section of the cycle track.

2.1.3. Quieter Mixed Traffic Streets Routes Utilising streets with good wayfinding to establish suitable routes.

Using the CIL funding 2 routes will be delivered in Financial Year 25/26 these routes will be Leigh to Southend (Victoria and Central stations) and Southend Victoria to Shoeburyness and are shown in Figure 4 below. Figure 4. Quieter Mixed Traffic Streets Routes

These routes are now in the final stages of design, and we plan to check/sign off by end of November 2025. With a view to deliver before end of FY 25/26.

2.2Cycle Network

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update of CIL and Cycle NetworkReport 2.8 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
CM
Councillor Carole MulroneyChair, apologies, sent representative
KB
Councillor Kevin BuckVice-Chair, in the Chair, present
SB
Councillor Susan BadgerCommittee Member, present
MB
Councillor Margaret BortonCommittee Member, present
SH
Councillor Stephen HabermelCommittee Member, present
RL
Councillor Richard LongstaffCommittee Member, present
JM
Councillor Judith McMahonCommittee Member, present
SN
Councillor Shahid NadeemCommittee Member, present
CN
Councillor Cheryl NevinCommittee Member, present
RM
Councillor Robert McMullanCommittee Member, present as substitute
DC
Councillor Daniel CowanCouncillor, in attendance
LH
Councillor Lydia HydeCouncillor, in attendance

All 16 on the meeting page

More from Southend-on-Sea Place Overview & Scrutiny Committee

All decisions
MeetingDecisionOutcome
18 Jun 2026 Minutes of the Meeting held on Tuesday, 10th February, 2026That the Minutes of the meeting held on Tuesday, 10 February 2026 be confirmed as a correct record. Decided Open
18 Jun 2026 Better Queensway Underpass Closure Impact Assessment UpdateThat the update on the closure of the Better Queensway underpass and associated impact assessment, be noted. Note: Th... Noted Open
18 Jun 2026 Parks and Playgrounds UpdateThat the parks and playgrounds update be noted. Noted Open
18 Jun 2026 Work Programme 2026/27That the work programme of the Committee be noted. This is a Scrutiny function. Noted Open
10 Feb 2026 Minutes of the Meeting held on Tuesday, 2nd December, 2025That the Minutes of the meeting held on Tuesday 2 nd December 2025 be confirmed and signed as a correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies