Southend-on-Sea Borough Council
Place Overview & Scrutiny Committee, Tuesday 2 December 2025 at 6.30pm

Partnership Working: Southend-on-Sea City Council and Anglian Water

Decided Scrutiny 3 papers

AI summaryScrutiny committee welcomes Anglian Water partnership report, which proposes £90 million of investment over 5 to 10 years to cut sewer spills and surface water flooding across Southend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPlace Overview and Scrutiny Committee noted partnership proposals
Moneycirca £90 million from Anglian WaterOver 5 to 10 years, schemes on 11 named overflows
What happens nextCabinet to consider recommendationsCross-party group and delegations to be agreed
Who it affectsSouthend residents, businesses, visitorsPublic realm, bathing water, flood risk

What was decided

The committee welcomed the report to Cabinet, which proposes a cross-party councillor working group chaired by the Cabinet Member for Climate, Environment and Waste to advise on scheme locations. Report P5, 3.12

Cabinet is asked to delegate authority to the Executive Director for Environment and Place, in consultation with the Cabinet Member, to agree scheme locations after informal discussions with ward councillors and affected residents. Report 2.2

Why

The partnership is intended to cut spills from 11 Combined Sewer Outfalls, reduce surface water flooding and lift civic pride, with most council involvement through small-scale works such as converting grass verges to rain gardens. Report 3.9, 3.10

Anglian Water values its existing relationship with the council through the Catchment to Coast programme and the Water Summit, which is why Southend was chosen for the Advanced WINEP pilot. Report 1.1, 3.3

The programme is expected to improve bathing water quality, road safety, biodiversity and air quality, though specific carbon and equalities impacts will be assessed scheme by scheme. Report 8.1, 8.3, 9.1, 10.1

What happens next

Cabinet will be asked to set up the cross-party working group and approve the delegated authority arrangements described in the recommendations. Report P5, 2.2

A Project Steering Group and Project Operational Group will be formed, with proposed locations and interventions discussed with ward councillors and residents before schemes are implemented. Report 3.12, 11.2

Schemes outside the public highway, and most major interventions, are expected to require full planning applications determined by the Planning Committee. Report 7.3

The money

  • circa £90 million Anglian Water contribution to Southend A-WINEP over the lifetime of the programme

Options considered

  • Rejected: Anglian Water proceeds with limited council involvement using traditional engineered solutions. Would lack significant public realm enhancements and progress on reducing spills and flooding would be slower and less impactful Report P21, 5.1
  • Chosen: Partnership with the council using the A-WINEP framework, including small-scale SuDS interventions and rain gardens. Delivers broader public realm, biodiversity and civic pride benefits alongside spill and flood reductions Report 3.4, 3.6, 3.9, 3.10

Implications

  • Financial: Anglian Water will fund the additional A-WINEP works where they align with planned council schemes; existing capital funds such as the footway and carriageway programme and LTP act as co-funding, with officer time capitalised to projects. Report 6.1, 6.2
  • Legal: Specific scheme legal implications will be assessed case by case; some elements of the governance and most major interventions outside the public highway will need planning applications and possible legal input. Report 7.1, 7.2, 7.3
  • Equalities: An Equalities Impact Assessment will be completed at project level as individual projects progress. Report 10.1
  • Climate: Individual schemes and the overall project are expected to deliver positive carbon reduction and air quality benefits, to be quantified once designs are modelled. Report 9.1
  • Risk: No formal council consultation on the A-WINEP has yet taken place; future schemes will be discussed with ward councillors, businesses and residents before implementation. Report 11.1, 11.2
  • Other: Anglian Water will provide consultant support to the council's engineering team and secretariat support to the councillor working party, plus training and grants to maximise joint highway interventions. Report 4.3, 6.2

Who and where

  • Residents and businesses across the Southend area, particularly those near the 11 named Combined Sewer Outfalls Report 3.5
  • Ward councillors, who will be consulted on proposed scheme locations Report 2.2, 3.12
  • The council's Parks and engineering teams, who will receive training and consultant support Report 3.11, 4.3, 6.2
  • Visitors and tourists, through enhanced public realm, green infrastructure and cleaner bathing waters Report 3.5, 8.1

Timeline

  • Next 5 to 10 years: Anglian Water to deliver circa £90 million of A-WINEP schemes on 11 named sewer overflows in Southend
  • Report approved for publication on 19, 21 and 22 November 2025: Executive Director, S151 Officer and Monitoring Officer signed off the report Report P39

Plain English for the jargon

  • WINEP: Water Industry National Environment Programme, a regulatory programme setting out environmental obligations for water companies in England.
  • A-WINEP: Advanced WINEP, an evolution of the framework aimed at earlier, more innovative and partnership-driven environmental investment.
  • CSO: Combined Sewer Outfall, a point where combined sewage and rainwater overflow into the sea or a watercourse.
  • SuDS: Sustainable Drainage Systems, such as rain gardens, that manage surface water close to where it falls.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43

Resolved

- That the report to Cabinet be welcomed.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Place Overview & Scrutiny Committee

Executive summary

1.1Water companies are required to have a Water Industry National Environment Programme (WINEP). Anglian Water is the water company for the Southend area and it chose to bid for, and obtained, an Advanced WINEP (A-WINEP). The A-WINEP aims to apply a more innovative and collaborative approach with key local authority partners. Southend-on-Sea was chosen because Anglian Water already has an established relationship via Catchment to Coast and the Water Summit.

1.2The A-WINEP will target the elimination of Combined Sewer Outfall (CSO) spills and a reduction in surface water flooding via a number of differing type and location interventions.

1.3A cross-party forum will be established to advise the team along with a steering board and operational board to ensure oversight, consistency and to monitor effectiveness.

1.4This A-WINEP programme is a demonstration of the excellent partnership working between the Council and Anglian Water which has supported and developed innovative solutions to a range of issues providing the confidence for Anglian Water to focus large scale funding in to the Southend area and to work in partnership to support the delivery of a range of cutting-edge innovations and investments to improve water management across the city.

Recommendations

It is recommended that Cabinet: 2.1. Agrees that a cross-party councillor working group is established, chaired by the Cabinet Member for Climate, Environment and Waste, to discuss and recommend to the Project Executive suitable interventions and locations for the implementation of schemes that would benefit from funding under the A-WINEP Programme.

2.2Delegates authority to the Executive Director for Environment & Place in consultation with the Cabinet Member for Climate, Environment and Waste to agree the locations and appropriate intervention following informal discussions with stakeholders including ward councillors and residents directly affected by the scheme.

Background

3.1The Water Industry National Environment Programme (WINEP) is a regulatory programme developed by the Environment Agency, Defra, Natural England, and Ofwat. It sets out the environmental obligations for water companies in England.

3.2The Advanced WINEP (A-WINEP) is an evolution of the traditional WINEP framework. It aims to unlock earlier, more innovative, and partnership-driven environmental investment, going beyond statutory obligations to deliver broader benefits for communities and the environment.

3.3Anglian Water places significant value on the mature and collaborative relationship it has developed with Southend-on-Sea City Council through initiatives such as the Catchment to Coast programme and the Water Summit. This shared commitment to innovation and enhancing the public realm for the benefit of Southend’s residents, businesses, and visitors that aptly links to Civic Pride has reinforced Anglian Water’s view that Southend is an ideal location for future investment. This intent is further evidenced in the letter from Anglian Water included in Appendix B.

3.4The Anglian Water A-WINEP programme will continue and expand the current Catchment to Coast programme through widescale roll-out of Sustainable Drainage Systems (SuDS) interventions.

3.5The ambition is for the A-WINEP funding and initiatives to benefit all local residents and businesses by supporting economic development, enhancing tourism and delivering the health and wellbeing benefits of green infrastructure and clean bathing waters.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 2.8 MB Download
PDF
Appendix BAppendix B 197 KB Download
PDF
Partnership Working: Southend-on-Sea City Council and Anglian WaterReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
CM
Councillor Carole MulroneyChair, apologies, sent representative
KB
Councillor Kevin BuckVice-Chair, in the Chair, present
SB
Councillor Susan BadgerCommittee Member, present
MB
Councillor Margaret BortonCommittee Member, present
SH
Councillor Stephen HabermelCommittee Member, present
RL
Councillor Richard LongstaffCommittee Member, present
JM
Councillor Judith McMahonCommittee Member, present
SN
Councillor Shahid NadeemCommittee Member, present
CN
Councillor Cheryl NevinCommittee Member, present
RM
Councillor Robert McMullanCommittee Member, present as substitute
DC
Councillor Daniel CowanCouncillor, in attendance
LH
Councillor Lydia HydeCouncillor, in attendance

All 16 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Partnership Working: Southend-on-Sea City Council and Anglian WaterThis decision
  2. Partnership Working: Southend-on-Sea City Council and Anglian WaterAgreed

More from Southend-on-Sea Place Overview & Scrutiny Committee

All decisions
MeetingDecisionOutcome
18 Jun 2026 Minutes of the Meeting held on Tuesday, 10th February, 2026That the Minutes of the meeting held on Tuesday, 10 February 2026 be confirmed as a correct record. Decided Open
18 Jun 2026 Better Queensway Underpass Closure Impact Assessment UpdateThat the update on the closure of the Better Queensway underpass and associated impact assessment, be noted. Note: Th... Noted Open
18 Jun 2026 Parks and Playgrounds UpdateThat the parks and playgrounds update be noted. Noted Open
18 Jun 2026 Work Programme 2026/27That the work programme of the Committee be noted. This is a Scrutiny function. Noted Open
10 Feb 2026 Minutes of the Meeting held on Tuesday, 2nd December, 2025That the Minutes of the meeting held on Tuesday 2 nd December 2025 be confirmed and signed as a correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies