CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Southend-on-Sea Borough Council
Cabinet, Monday 19 January 2026 at 6.00pm

Partnership Working: Southend-on-Sea City Council and Anglian Water

Agreed Executive 3 papers

AI summarySouthend Cabinet sets up cross-party working group to shape Anglian Water's £90 million surface water and sewer spill investment in the city.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedChaired by climate cabinet member, decisions delegated to Executive Director
MoneyAnglian Water circa £90 millionOver 5 to 10 years for Southend A-WINEP schemes
What happens nextWorking group to recommend interventions and locations. Project Executive will receive recommendations
Who it affectsSouthend residents, businesses and visitors11 named sewer overflows and wider catchment

What was decided

Cabinet agreed to establish a cross-party councillor working group, chaired by the Cabinet Member for Climate, Environment and Waste, to recommend interventions and locations to the Project Executive for A-WINEP funded schemes. Report P5

Authority was delegated to the Executive Director for Environment and Place, in consultation with the climate cabinet member, to agree scheme locations and interventions after informal discussions with ward councillors and affected residents. Report 2.2

These decisions are not eligible for call-in.

Why

The A-WINEP partnership aims to cut combined sewer outfall spills, reduce surface water flooding, and improve the public realm, building on the existing Catchment to Coast and Water Summit relationship with Anglian Water. Report 1.1, 1.2, 3.3, 3.9

Anglian Water is committed to spending circa £90 million in Southend over 5 to 10 years on schemes targeting 11 named sewer overflows and wider catchment improvements.

Without council involvement, Anglian Water would still invest but through slower, traditional engineered solutions with less public realm benefit. Report 5.1

What happens next

A cross-party forum, Project Steering Group and Project Operational Group will be set up to oversee the A-WINEP programme, with a Project Executive taking recommendations. Report 1.3, 3.12

Proposed locations and interventions will be discussed with ward councillors and affected residents before implementation. Report 3.12, 11.2

Most major interventions, and some smaller ones beyond the public highway, will need planning applications determined by the Planning Committee; an Equalities Impact Assessment will be completed at project level. Report 7.3, 10.1

The money

  • circa £90million Anglian Water contribution to Southend over the A-WINEP lifetime, 5 to 10 years

Options considered

  • Chosen: Work in partnership with the council on A-WINEP. Enables wider public realm benefits and co-funding of council works to cut CSO spills Report 5.1, 6.1
  • Rejected: Limited council involvement, Anglian Water proceeds alone. Would rely on traditional engineered solutions, with slower and less impactful delivery Report 5.1

Implications

  • Financial: Anglian Water will fund additional works where council planned schemes help cut CSO spills; council co-funding comes from existing committed capital funds such as footway and carriageway, LTP, and officer time capitalised to projects, with no new burden on the capital programme. Report 6.1, 6.2
  • Legal: Scheme-specific legal implications will be assessed case by case; some interventions will need full planning applications determined by Planning Committee. Report 7.1, 7.3
  • Equalities: An Equalities Impact Assessment will be completed at project level as individual projects progress. Report 10.1
  • Climate: Individual schemes and the overall project are expected to bring positive carbon reduction and air quality benefits, to be quantified once modelled. Report 9.1
  • Risk: Reducing surface water flooding should improve road safety, and cutting CSO spills could improve bathing water quality. Report 8.3
  • Other: Anglian Water will offer consultant support to the council's engineering team and secretariat support to the councillor working party. Report 6.2

Who and where

  • Southend residents, businesses and visitors Report 3.3, 3.5
  • Ward councillors in affected areas Report 3.12, 11.2
  • The council's engineering, parks and highways teams Report 3.10, 3.11, 6.2
  • 11 named sewer overflow locations in Southend

Timeline

  • next 5 to 10 years: Anglian Water A-WINEP delivery window for Southend schemes
  • 19.11.2025: Report approved by Monitoring Officer Report P39
  • 21.11.2025: Report approved by Executive Director Alan Richards Report P39
  • 22.11.2025: Report approved by S151 Officer Joe Chesterton Report P39
  • 24.11.2025: Report approved by relevant Cabinet Member Cllr L Hyde Report P39
  • 2026-01-19: Cabinet decision

Plain English for the jargon

  • A-WINEP: Advanced Water Industry National Environment Programme, an Anglian Water regulatory programme for innovative, partnership-driven environmental investment
  • CSO: Combined Sewer Outfall, a point where combined sewerage and surface water overflow into the sea or watercourse during heavy rain
  • SuDS: Sustainable Drainage Systems, such as rain gardens that manage surface water close to where it falls
  • WINEP: Water Industry National Environment Programme, setting environmental obligations for water companies in England
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item79

Resolved

- 1. That a cross-party councillor working group be established, chaired by the Cabinet Member for Climate, Environment and Waste, to discuss and recommend to the Project Executive suitable interventions and locations for the implementation of schemes that would benefit from funding under the A-WINEP Programme. 2. That authority be delegated to the Executive Director (Environment & Place) in consultation with the Cabinet Member for Climate, Environment and Waste to agree the locations and appropriate intervention following informal discussions with stakeholders including ward councillors and residents directly affected by the scheme. These decisions are not eligible for call-in.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1Water companies are required to have a Water Industry National Environment Programme (WINEP). Anglian Water is the water company for the Southend area and it chose to bid for, and obtained, an Advanced WINEP (A-WINEP). The A-WINEP aims to apply a more innovative and collaborative approach with key local authority partners. Southend-on-Sea was chosen because Anglian Water already has an established relationship via Catchment to Coast and the Water Summit.

1.2The A-WINEP will target the elimination of Combined Sewer Outfall (CSO) spills and a reduction in surface water flooding via a number of differing type and location interventions.

1.3A cross-party forum will be established to advise the team along with a steering board and operational board to ensure oversight, consistency and to monitor effectiveness.

1.4This A-WINEP programme is a demonstration of the excellent partnership working between the Council and Anglian Water which has supported and developed innovative solutions to a range of issues providing the confidence for Anglian Water to focus large scale funding in to the Southend area and to work in partnership to support the delivery of a range of cutting-edge innovations and investments to improve water management across the city.

Recommendations

It is recommended that Cabinet: 2.1. Agrees that a cross-party councillor working group is established, chaired by the Cabinet Member for Climate, Environment and Waste, to discuss and recommend to the Project Executive suitable interventions and locations for the implementation of schemes that would benefit from funding under the A-WINEP Programme.

2.2Delegates authority to the Executive Director for Environment & Place in consultation with the Cabinet Member for Climate, Environment and Waste to agree the locations and appropriate intervention following informal discussions with stakeholders including ward councillors and residents directly affected by the scheme.

Background

3.1The Water Industry National Environment Programme (WINEP) is a regulatory programme developed by the Environment Agency, Defra, Natural England, and Ofwat. It sets out the environmental obligations for water companies in England.

3.2The Advanced WINEP (A-WINEP) is an evolution of the traditional WINEP framework. It aims to unlock earlier, more innovative, and partnership-driven environmental investment, going beyond statutory obligations to deliver broader benefits for communities and the environment.

3.3Anglian Water places significant value on the mature and collaborative relationship it has developed with Southend-on-Sea City Council through initiatives such as the Catchment to Coast programme and the Water Summit. This shared commitment to innovation and enhancing the public realm for the benefit of Southend’s residents, businesses, and visitors that aptly links to Civic Pride has reinforced Anglian Water’s view that Southend is an ideal location for future investment. This intent is further evidenced in the letter from Anglian Water included in Appendix B.

3.4The Anglian Water A-WINEP programme will continue and expand the current Catchment to Coast programme through widescale roll-out of Sustainable Drainage Systems (SuDS) interventions.

3.5The ambition is for the A-WINEP funding and initiatives to benefit all local residents and businesses by supporting economic development, enhancing tourism and delivering the health and wellbeing benefits of green infrastructure and clean bathing waters.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A-WINEP Partnership Cabinet Paper- Appendix AAppendix 2.8 MB Download
PDF
Appendix BAppendix B 197 KB Download
PDF
Partnership Working: Southend-on-Sea City Council and Anglian WaterReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
DC
Councillor Daniel CowanChair, present
AJ
Councillor Anne JonesVice-Chair, present
LB
Councillor Laurie BurtonCommittee Member, present
PC
Councillor Paul CollinsCommittee Member, present
MD
Councillor Matt DentCommittee Member, present
LH
Councillor Lydia HydeCommittee Member, present
KR
Councillor Kevin RobinsonCommittee Member, present
MS
Councillor Maxine SadzaCommittee Member, present
MT
Councillor Martin TerryCommittee Member, present
IF
Councillor Irene FergusonCouncillor, in attendance
MO
Councillor Mandy O'ConnorCouncillor, in attendance
SW
Councillor Steven WakefieldCouncillor, in attendance

All 21 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Partnership Working: Southend-on-Sea City Council and Anglian WaterThis decision
  2. Partnership Working: Southend-on-Sea City Council and Anglian WaterDecided

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies