Southend-on-Sea Borough Council
Planning Committee, Wednesday 22 July 2026 at 5.00pm

24/01845/BC3M - Leigh Port, High Street, Leigh-on-Sea (Leigh Ward)

Approved Planning 2 papers

AI summarySouthend Planning Committee grants permission for a new quay wall, dredging, and resurfacing at Leigh Port. The 18-month scheme will increase mooring capacity from 11 to 12 fishing vessels and secures the future of the cockling industry.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMajor council application, Regulation 3, approved by Planning Committee
MoneyNot stated
What happens nextBegin within three yearsPre-commencement conditions require discharge first
Who it affectsLeigh Port, fishing industry, conservation areaLeigh Old Town Conservation Area and protected mudflat habitats

What was decided

Planning permission was granted subject to conditions covering three-year commencement, approved plans, materials, lighting, signage, drainage, construction method, biodiversity net gain, and habitat monitoring. Report P13

The committee accepted officers' assessment that less than substantial harm to the Leigh Old Town Conservation Area is outweighed by public benefits including port safety, long-term viability of cockling, improved drainage, and removal of unauthorised containers. Report 4.3, 4.7, 8.1, 8.4, 8.6, P171

Members agreed conditions to remove unauthorised containers, prevent perimeter fencing that would block views, retain public access across the quayside, and require removal of security gates at Bell Wharf once cockle unloading returns to the port. Report 4.3, P75

Why

The existing quay wall is in critical condition, deteriorating, and a safety risk to people and vessels. Its cockle shell surface is uneven and requires heavy maintenance, and the narrow access restricts larger vehicles needed for port operations. Report P46, 1.2, 8.8

The scheme secures the long-term future of the cockling industry, supports local jobs and the maritime economy, improves drainage that reduces pollution into the estuary, and increases climate and tidal resilience of the port. Report P47, P48, 2.4

Dredging the berthing pocket and widening the channel from 12 metres base width to a consistent 4.1 metres below mean high water will improve access and safety, raising mooring capacity from 11 to 12 cockle boats. Report 2.4, 2.7

What happens next

The applicant must discharge pre-commencement conditions including the Construction Environmental Management Plan, Biodiversity Net Gain Plan, Habitat Monitoring and Management Plan, archaeology watching brief, materials details, and Anglian Water asset protection scheme before starting work. Report 4.4, 4.10, P102, P127

A Section 61 Agreement with the council's Regulatory Services is required to control noise and working hours, and a Marine Management Organisation licence is needed for marine works below Mean High Water Springs. Report 4.6, P83, 4.9, P97

A Basic Asset Protection Agreement must be entered with Network Rail, and a Flood Risk Activity Permit progressed with the Environment Agency, before any construction starts. Report 4.8, P96, P144

Options considered

  • Chosen: Grant planning permission subject to conditions. Public benefits of port regeneration and long-term safety outweigh less than substantial harm to the conservation area, and consultee concerns can be addressed by conditions and informatives. Report P13, 4.3, 4.7, 8.7
  • Rejected: Refuse planning permission. The reports set out no reasonable basis to refuse given the policy support for retaining and regenerating Leigh Port and the need to address the deteriorating quay wall. Report 8.4, 8.5, 8.6, P171

Implications

  • Legal: Requires Section 61 noise agreement, MMO marine licence, Network Rail asset protection agreement, Anglian Water Sewer protection scheme, and a Section 106 notice under the Water Industry Act 1991 for trade effluent connection. Report 4.6, P83, 4.9, P97, 4.10, P101, 4.8, P96
  • Equalities: Improved accessibility of the quayside for wheelchair users and a safer surface for all port users, with works timed to avoid main cockling seasons where reasonably possible. Report P48, 2.10
  • Climate: Lower long-term maintenance, increased resilience to climate and tidal impacts, diversion of trade effluent from the estuary to the foul system, and new quay wall set to flood safely as water compatible development. Report P48, 2.3, P144
  • Risk: Construction risks include HGV movements on local roads, contaminated dredged material requiring testing, and noise during out-of-hours dredging. These are to be controlled by the CEMP, Section 61 agreement, and Environment Agency supervision. Report 4.6, P82, 4.7, P86, P87
  • Other: Protected habitats including Benfleet and Southend Marshes SPA, SSSI, and RAMSAR site require habitat monitoring, an ornithological clerk of works during dredging, and 30-year biodiversity net gain monitoring under the Habitat Monitoring and Management Plan. Report 4.12, P118, P119, P120, P121
  • Other: Sediment sampling and suspended solids monitoring required to protect bathing and shellfish waters, with shellfish waters to stay within 30 percent of ambient suspended sediment levels in unaffected areas. Report P137, P138

Who and where

  • Leigh cockle fishermen and the local fishing industry, including 11 existing mooring users Report 1.2, 2.4, P48
  • Leigh Old Town Conservation Area and its visitors, with views across the port and public access to the quayside Report 4.3, P68, P72
  • Owners and operators of the 16 modern cockle sheds fronting the High Street Report 1.3, 2.10
  • Wildlife of Benfleet and Southend Marshes SPA, SSSI, and RAMSAR site, including overwintering birds and seagrass beds Report 1.5, P26, 4.12, P116
  • Residents and businesses on Leigh High Street, including Belton Way Small Craft Clubhouse users Report 1.4, 2.9
  • Highways users on Thames Drive, Belton Way, and the A13 London Road construction route Report 4.7, P86, P87

Timeline

  • 2026-07-22: Planning Committee resolves to grant planning permission subject to conditions Report P13
  • Within three years of the decision: Development must begin, or permission will lapse
  • Before commencement: Discharge of pre-commencement conditions including CEMP, BNG Plan, HMMP, materials, and Anglian Water protection scheme Report 4.4, 4.10, P127
  • Around 18 months: Expected construction period, with the site compound at Leigh Marshes Car Park Report 1.6, 2.11
  • During the dredging phase, around 4 months: Approximately 150 HGV movements per week, totalling around 2,400 vehicle movements Report P87

Plain English for the jargon

  • AOD: Above Ordnance Datum, the standard UK height measurement relative to mean sea level.
  • Berthing pocket: An area of water dredged next to a quay so boats can moor and rest on the seabed at low tide.
  • BNG: Biodiversity Net Gain, a requirement that development delivers measurable improvements to habitats.
  • CEMP: Construction Environmental Management Plan, setting out how construction impacts on the environment will be controlled.
  • Grouted macadam: A hybrid paving material combining open-graded asphalt filled with a cementitious or asphaltic grout, giving both flexibility and strength.
  • HMMP: Habitat Monitoring and Management Plan, the long-term document that secures and monitors biodiversity gains, usually over 30 years.
  • MMO: Marine Management Organisation, the body that issues marine licences under the Marine and Coastal Access Act 2009.
  • Section 61 Agreement: A formal prior consent under the Control of Pollution Act 1974 setting agreed noise limits, working hours, and mitigation before noisy construction begins.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item119

Resolved

- That PLANNING PERMISSION be GRANTED subject to the following conditions: 1. The development hereby permitted shall begin no later than three years from the date of this decision Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990 2. The development hereby permitted shall be carried out in accordance with the following approved plans: 100419439-MMD-LP-XX-DR-C-Y1-13-7001-P02 (Site Plan, Location Plan and Drawing List Sheet 01 of 01), 100419439-MMD-LP-XX-DR-C-Y1-13-7002-P02 (Existing Site Plan Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7003-P02 (Existing Site - Sections Sheet 01 of 01), 100419439-MMD-LP-XX-DR-C-Y1-13-7004-P02 (Existing Site - Demolition Plan Sheet 01 of 01), 100419439-MMD-LP-XX-DR-C-Y1-13-7005-P02 (Proposed Site Plan Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7006-P02 (Proposed Site – Sections Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7008-P02 (Proposed Site – Typical Quay Wall Section Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7009-P02 (Typical Details Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7010-P02 (Berting Pocket Dredging Plan and Logditudal Profile Sheet 01 of 01 (Section A-A)), 100419439-MMD-LP-XX-DR-C-Y1-13-7011-P02 (Berting Pocket Dredging Plan and Cross Sections Sheet 01 of 01 (Sections B-B and C-C)), 100419439-MMD-LP-XX-DR-C-Y1-13-1200-P02 (Foul Drainage Network General Arrangement Sheet 01 of 01), 100125486_MMD_LPR_ZZ_DR_C_2000 T02 (Surface Water Drainage Sheet 01 of 02); 100125486_MMD_LPR_ZZ_DR_C_2001 T02 (Surface Water Drainage Sheet 02 of 02). Reason: To ensure that the development is carried out in accordance with the Development Plan. Materials, Details and Heritage 3. A) The external surface materials for the quay subject of this permission shall not be installed unless and until full product details and surface finishes have been submitted to and agreed in writing with the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details and retained as such for the lifetime of the development. B) The materials and details for the capping beam, fenders, ladders and mooring facilities for the development hereby approved shall be installed in full accordance with the details set out in the approved plan reference 100419439-MMD-LP-XX-DR-C-Y1-13-7009-P02 (Typical Details Sheet 01 of 01); or in accordance with alternative details which have first been submitted to and approved in writing by the Local Planning Authority under the scope of this planning condition. Reason: To ensure that the materials are appropriate to the character and appearance of the site and the Leigh Old Town Conservation Area, in accordance with Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1, DM3, DM5 and DM6 and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009) and Leigh Old Town Conservation Area Appraisal (2021). 4. A) No external lighting, signage, bollards, refuse storage, CCTV ... view the full minutes text for item 119.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Planning Committee

Reference: 24/01845/BC3M

Application Type: Borough Council Regulation 3 – Major

Ward: Leigh

Proposal: Erect new quay wall with associated fittings and carry out improvement works to the existing Leigh Port quay area, including resurfacing and access enhancements. Install upgraded utility connections and drainage systems for surface water and trade waste, undertake dredging to cover the berth pocket in front of the new quay wall to maintain appropriate operational depths, and complete other associated works to support the long term resilience of Leigh Port

Address: Leigh Port, High Street, Leigh-on-Sea, Essex, SS9 2EB

Applicant: [name removed] of Southend City Council

Agent: N/A

Consultation Expiry: 30th June 2026

Expiry Date: 24th July 2026

Case Officer: Abbie Greenwood / Oliver Hart

Plan Nos: 100419439-MMD-LP-XX-DR-C-Y1-13-7001-P02 (Site Plan, Location Plan and Drawing List Sheet 01 of 01), 100419439-MMD-LP-XX-DR-C-Y1-13-7002-P02 (Existing Site Plan Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7003-P02 (Existing Site - Sections Sheet 01 of 01), 100419439-MMD-LP-XX-DR-C-Y1-13-7004-P02 (Existing Site - Demolition Plan Sheet 01 of 01), 100419439-MMD-LP-XX-DR-C-Y1-13-7005-P02 (Proposed Site Plan Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7006-P02 (Proposed Site – Sections Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7008-P02 (Proposed Site – Typical Quay Wall Section Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7009-P02 (Typical Details Sheet 01 of 01); 100419439-MMD-LP-XX-DR-C-Y1-13-7010-P02 (Berting Pocket Dredging Plan and Logditudal Profile Sheet 01 of 01 (Section A-A)), 100419439-MMD-LP-XX-DR-C-Y1-13-7011-P02 (Berting Pocket Dredging Plan and Cross Sections Sheet 01 of 01 (Sections B- B and C-C)), 100419439-MMD-LP-XX-DR-C-Y1-13-1200-P02 (Foul Drainage Network General Arrangement Sheet 01 of 01), 100125486_MMD_LPR_ZZ_DR_C_2000 T02 (Surface Water Drainage Sheet 01 of 02); 100125486_MMD_LPR_ZZ_DR_C_2001 T02 (Surface Water Drainage Sheet 02 of 02).

Additional information: Design and Access Statement by Mott Macdonald dated September 2024; Planning Statement by Mott Macdonald dated November 2024; Environmental Statement Chapters 1-20 by Mott Macdonald dated August 2024; Chapters below; - 1-4 Introductory Chapters; - Chapter 5 Archaeology and Cultural Heritage; - Chapter 6 Biodiversity; - Chapter 7 Commercial Fisheries and Shellfish; - Chapter 8 Coastal Processes; - Chapter 9 Landscape; - Chapter 10 Noise and Vibration - Chapter 11 Water and Flooding - Chapter 12 Ground Conditions - Chapter 13 Climate Resilience - Chapter 14 Carbon - Chapter 15 Materials and Waste - Chapter 16 Major Accidents and Disasters - Chapter 17 Navigation - Chapter 18 Traffic and Transport - Chapter 19 Cumulative and in-combination Effects - Chapter 20 Summary Leigh Port Infrastructure Regeneration Technical Note ‘Non- Consequential Changes to the Environmental Statement’ by Mott Macdonald dated 16 March 2026; Leigh Port Infrastructure Regeneration Technical Note ‘Differences between the Amended Scheme and the Initially Proposed Scheme’ by Mott Macdonald dated 16 March 2026; Water Framework Directive (WFD) Assessment by Mott Macdonald dated September 2024; Habitats Regulations Assessment (HRA) including Bird Surveys and Sediment Sampling Results by Mott Macdonald dated October 2024; Habitat Monitoring and Management Plan (HMMP) by Mott Macdonald Rev. A dated April 2026; Biodiversity Net Gain Design Stage Report by Mott Macdonald dated March 2026 Statutory Biodiversity Metric [Excel Spreadsheet & Condition Assessments]; Historic Environment Desk-Based Assessment by Mott Macdonald dated August 2024; Leigh Port Regeneration Project Dredged Channel CH 0+000 - 0+640 Ref. FRA 100419439-MML-LP-ZZ-CN-FL-Y1-13-001; Flood Risk Assessment Ref. 100419439-MML-LP-ZZ-CN-FL-Y1- 13-001A Anglian Water Combined 375mm Pipe Options 08.06.26 100125486_MMD_LPR_ZZ_SK_C_0023_P01 Anglian Water Sewer and Pipe Exclusion Zone

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/01845/BC3M: Leigh Port, High Street, Leigh-on-Sea (Leigh Ward)Report 680 KB DownloadRead as text
PDF
Leigh Port Plans and PhotosPlan 824 KB Download

At this meeting

Whole meeting

Who was there

10 of 25 attended
MB
Councillor Margaret BortonChair, present
SH
Councillor Stephen HabermelVice-Chair, present
MB
Councillor Martin BerryCommittee Member, present
DG
Councillor David GarstonCommittee Member, present
AJ
Councillor Anne JonesCommittee Member, present
RL
Councillor Richard LongstaffCommittee Member, present
RM
Councillor Robert McMullanCommittee Member, present as substitute
JN
Councillor Jane NormanCommittee Member, present
DP
Councillor Dave PoultonCommittee Member, apologies, sent representative
SW
Councillor Steven WakefieldCommittee Member, present
SA
Councillor Stephen AylenCouncillor, in attendance
MD
Councillor Matt DentCouncillor, in attendance

All 25 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. 24/01845/BC3M - Leigh Port, High Street, Leigh-on-Sea (Leigh Ward)This decision
  2. Leigh Port Development- Main Works ContractAgreed
  3. West Leigh Area – Report on Ward Councillor Consultation for Parking ControlsNoted
  4. West Leigh Area – Report on Ward Councillor Consultation for Parking ControlsDecided
  5. West Leigh Area – Report on Ward Councillor Consultation for Parking ControlsDecided

More from Southend-on-Sea Planning Committee

All decisions
MeetingDecisionOutcome
26 Aug 2026 Minutes of the meeting held on Wednesday 22nd July 2026- That the Minutes of the meeting held on Wednesday 22 nd July 2026 be confirmed as a correct record and signed. Decided Open
26 Aug 2026 Minutes of the special meeting held on Wednesday, 12th August, 2026- That the Minutes of the special meeting held on Wednesday 12 th August 2026 be confirmed as a correct record and si... Decided Open
26 Aug 2026 25/01792/OUTM - Land North of Bournes Green Chase, Southend-on-Sea (Southchurch Ward)- That PLANNING PERMISSIOIN be REFUSED for the following reason: The proposed development is inappropriate developmen... Refused Open
12 Aug 2026 26/00429/FUL - 141 Broadway, Leigh-on-Sea (Leigh Ward)- That PLANNING PERMISISON be GRANTED subject to the following conditions: 01 The development hereby permitted shall ... Approved Open
12 Aug 2026 26/00499/FUL - 556 Rayleigh Road, Eastwood (Eastwood Park Ward)- That PLANNING PERMISSION be REFUSED for the following reason: 01 The extraction system, due to its size, height and... Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies