Southend-on-Sea Borough Council
Cabinet, Monday 7 September 2026 at 6.00pm

Leigh Port Development- Main Works Contract

Agreed Executive 2 papers

AI summaryCabinet approves direct award of Leigh Port main works contract via the SCAPE framework to the sole provider, with a £21.801m total project budget, starting October 2026 for completion in June 2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedVia SCAPE Civil Engineering Gen3 Framework
Money£21.801m total project budgetIncluding £14.901m LUF grant and £6.9m council match
What happens nextConstruction starts October 2026Target completion June 2028
Who it affectsLeigh Port and cockle industryQuay infrastructure, leaseholders, local businesses

What was decided

Cabinet approved the direct award of the main works contract via the SCAPE Civil Engineering Gen3 Framework to the sole provider, starting October 2026 with completion aimed for June 2028. Report 2.1

Cabinet delegated authority to the Executive Director for Environment and Place, in consultation with the Section 151 Officer and the Leader and Cabinet Member for Regeneration and LGR, to decide on use of contingency within the approved project budget, including the £6.9m match funding. Report 2.2

Why

The current Principal Contractor, Balfour Beatty, has already undertaken design development, value engineering and early works, so retaining the same firm is judged to provide better value and reduce risk and delay. Report 1.3, 3.4

Using the SCAPE framework is compliant with the Public Contract Regulations 2015 and avoids the risk of a procurement challenge. Report 3.5, 7.3

Doing nothing would risk having to repay the Levelling Up Fund grant and would allow the port structure to continue to deteriorate, threatening cockle industry jobs. Report 4.1

What happens next

Construction of the main works is scheduled to run from October 2026 to June 2028, with remaining LUF funding to be spent before 31 March 2028.

A desktop evaluation will be carried out to confirm best value from the sole provider on the SCAPE framework. Report 3.5

The contract will be managed through the CEMAR system, with progress monitored against milestones and performance indicators.

The money

  • £21.801m Total approved project budget Report 6.1
  • £14.901m LUF grant funding including £880k of match funding Report 6.1
  • £6.9m Council match funding from the capital investment programme Report 2.2, 6.1
  • £2.8m Spend to date
  • £15.6m Current forecast target cost of the construction contract
  • £3.0m Risk and contingency budget within the approved project budget

Options considered

  • Chosen: Direct award via the SCAPE Civil Engineering Gen3 Framework to the sole provider. Maintains programme certainty within grant funding timetable and reduces risk and duplication of effort Report 1.3, 2.1, 3.4
  • Rejected: Do nothing. Would risk the Council having to repay the LUF grant and would allow the port to deteriorate, threatening cockle industry jobs Report 4.1
  • Rejected: Issue a separate bespoke tender. Would duplicate effort, require revalidation of work already done and introduce delays and additional costs Report 4.2

Implications

  • Financial: Total approved project budget is £21.801m, with £3.0m held as risk and contingency and the construction contract target cost currently forecast at about £15.6m. Report 6.1
  • Legal: The contract value exceeds the £500,000 Key Decision threshold, so Cabinet approval is required; procurement is compliant with the Public Contract Regulations 2015 and uses the SCAPE framework as a lawful route to market. Report 7.3
  • Risk: Key risks include regulatory delays from Natural England and the Marine Maritime Organisation, leaseholder objections, programme slippage affecting the LUF funding deadline, and incomplete environmental assessments. Report 8.1, 8.2, 8.3, 8.4
  • Climate: Construction carbon impacts are intended to be offset through use of recycled and low carbon materials and modern vehicles with the latest engine types. Report 11.1
  • Equalities: No full Equality Impact Assessment is considered necessary at this stage, but equalities will be kept under review and an assessment will be carried out if any material change is proposed. Report 13.1
  • Other: Biodiversity Net Gain will be monitored over the next 30 years through a conservation covenant under the Environment Act 2021. Report 12.1

Who and where

  • Cockle and fishing industry at Old Leigh Report 1.2, 10.2
  • Port leaseholders and local businesses at Leigh Port Report 8.2, 3.2
  • Visitors and residents using the Leigh waterfront and tourism economy Report 1.2, 4.1
  • Statutory consultees including Natural England and the Marine Maritime Organisation Report 8.1

Timeline

  • 22nd July 2026: Planning permission for the scheme granted Report 3.2
  • 4 August 2026: Investment Board considered the £6.9m match funding Report 6.1
  • October 2026: Main works construction scheduled to commence Report 2.1
  • 31 March 2028: Deadline for spending remaining LUF funding
  • June 2028: Target completion of main works Report 2.1

Plain English for the jargon

  • LUF: Levelling Up Fund, a UK government grant programme
  • SCAPE Civil Engineering Gen3 Framework: A public sector procurement framework for civil engineering works
  • NEC4 ECC Option C: Target Cost contract with activity schedule and a pain and gain mechanism, using the New Engineering Contract form
  • CEMAR: A widely used online contract management system for recording instructions, compensation events and early warnings
  • CDM 2015: Construction (Design and Management) Regulations 2015, setting duties for managing health, safety and welfare on construction projects
  • UXO: Unexploded ordnance, surveyed for before construction works
  • Biodiversity Net Gain: A requirement under the Environment Act 2021 that development delivers measurable improvements for habitats
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29

Resolved

That it be agreed that Cabinet: 1. Approve, the direct award of a new contract to a Principal Contractor by way of call-off via the SCAPE Civil Engineering Gen3 Framework to the sole provider on the SCAPE framework, commencing in October 2026 aiming for completion in June 2028 within the approved overall project budget. 2. Delegates authority to the Executive Director for Environment and Place, in consultation with the Section 151 Officer and Leader and Cabinet Member for Regeneration & LGR, to agree and authorise decisions regarding use of contingency within the approved overall project budget, including the £6.9m match funding allocated in the capital investment programme to the project.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report seeks authority to award the main works contract and to delegate authority to the Executive Director for Environment and Place in consultation with the Section 151 Officer and Leader and Cabinet Member for Regeneration & LGR to manage contingency within the approved overall project budget.

1.2The Leigh Port Regeneration Project directly supports three of the Council’s Corporate Plan priorities by addressing critical infrastructure, sustaining a long‑established local industry and protecting the community’s relationship with its historic working waterfront. The port has long been central to Southend’s maritime identity and economy, and the project helps preserve this by securing the future of the cockling and fishing industry, which relies on safe and reliable quay infrastructure to operate. In this way, the project strongly aligns with the aspiration for a ‘proud and prosperous’ Southend, as it strengthens economic resilience and helps maintain the livelihoods and supply chains that depend on a functioning port.

1.3The direct award route has been selected following consideration of the project’s current stage, the contractor’s existing involvement in design development, value engineering and early works planning, and the need to maintain programme certainty within the grant funding timetable.

1.4The recommendations in this report seek Cabinet Member approval to (a) award the new NEC4 Engineering and Construction (ECC) call-off contract via SCAPE Civil Engineering Gen3 Framework commencing in October 2026 aiming for completion in June 2028 and (b) to delegate authority to the Executive Director for Environment and Place, in consultation with the Section 151 Officer and Leader and Cabinet Member for Regeneration & LGR, to agree and authorise decisions regarding use of contingency within the approved overall project budget, including the £6.9m match funding allocated in the capital investment programme to the project.

Recommendations

It is recommended that Cabinet:

2.1Approve, the direct award of a new contract to a Principal Contractor by way of call-off via the SCAPE Civil Engineering Gen3 Framework to the sole provider on the SCAPE framework, commencing in October 2026 aiming for completion in June 2028 within the approved overall project budget.

2.2Delegates authority to the Executive Director for Environment and Place, in consultation with the Section 151 Officer and Leader and Cabinet Member for Regeneration & LGR, to agree and authorise decisions regarding use of contingency within the approved overall project budget, including the £6.9m match funding allocated in the capital investment programme to the project.

Background

3.1This report seeks approval from Cabinet to award the Leigh Port Regeneration Project main works contract to commence in October 2026.

3.2Planning permission for the scheme was granted on 22nd July 2026 (see confirmation letter at Appendix 1).

3.3The project has moved through the design, value engineering and early works stages and now requires the appointment of the Principal Contractor for the construction to commence and discharge of Principal Contractor duties under the Construction (Design & Management) Regulations 2015 (CDM). This includes taking responsibility for piling, dredging, temporary works, general civil engineering work, undertaking necessary surveys including unexploded ordnance (UXO), traffic management and logistics.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24-01845-BC3M DNAppendix 1 180 KB Download
PDF
Leigh Port Development- Main Works ContractReport 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
DC
Councillor Daniel CowanChair, present
MS
Councillor Maxine SadzaVice-Chair, apologies
PC
Councillor Paul CollinsCommittee Member, present
MD
Councillor Matt DentCommittee Member, present
IF
Councillor Irene FergusonCommittee Member, present
CN
Councillor Cheryl NevinCommittee Member, present
MO
Councillor Mandy O'ConnorCommittee Member, present
KR
Councillor Kevin RobinsonCommittee Member, present
CW
Councillor Chris WebsterCommittee Member, present
RW
Councillor Ron WoodleyCommittee Member, present
CA
Colin AnsellOfficer, in attendance
JC
Joe ChestertonOfficer, in attendance

All 19 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Leigh Port Development- Main Works ContractThis decision
  2. 24/01845/BC3M - Leigh Port, High Street, Leigh-on-Sea (Leigh Ward)Approved
  3. West Leigh Area – Report on Ward Councillor Consultation for Parking ControlsNoted
  4. West Leigh Area – Report on Ward Councillor Consultation for Parking ControlsDecided
  5. West Leigh Area – Report on Ward Councillor Consultation for Parking ControlsDecided

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies