Peckham and Nunhead Community Council decided this item on Wednesday 21 November 2012. Below is the council's own wording, with the papers it was decided on.
That the community council supported the proposed cycle permeability schemes listed below for the Peckham and Nunhead area: Contra flow schemes Ward Brayard’s Road The Lane Friary Road Livesey Melon Road Peckham Harders Road – Cossall Park Nunhead King’s Grove Nunhead
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Peckham and Nunhead Community Council, 13 pages
Recommendations
1. That the community council note or comment on: The cycle permeability proposals as outlined in Appendix A Representations received during public consultation, as summarised in Appendix C. The impact of proposal on parking , as shown in Appendix B
BACKGROUND INFORMATION
2. Any representation received as part of public and statutory consultation will be presented to the Cabinet Member of Environment, Transport and Recycling for a decision on whether to proceed or drop a scheme
3. In accordance with Part 3H of the Southwark Constitution, community councils are to be consulted on the detail of strategic parking/ traffic/safety schemes. In practice this is carried out following public consultation.
4. The community council is now being given the opportunity to make final representations to the Cabinet Member as part of the public consultation process.
5. This scheme was identified as one which would help to deliver Southwark’s aim of increasing walking and cycling levels in the borough, and funded by Transport for London as part of the Local Implementation programme for 2012 - 2013.
6. The particular locations of focus were identified using the Cycle Skills Network Audit (CSNA) and by Southwark Cyclists / Living Streets as areas that could be improved to allow better access for pedestrians and cyclists.
7. The overall objectives of this scheme are to encourage journeys on foot or by bike by opening up new links that avoid heavily trafficked streets.
KEY ISSUES FOR CONSIDERATION
8. Contra flow: Public consultation was carried out on proposals that would remove or relocate existing parking, due to road safety concerns. Appendix B shows summary of changes to parking arrangements, which affects only 3 contra flows. Appendix C summarise representations received due to changes to parking. The public consultation took place with residents and businesses within the scheme area from September until October 2012.
9. Shared use footway / alleyway: Where it is proposed that cyclists use the exiting footway / alleyway, public consultation have been undertaken with residents, schools and business in the vicinity of the proposal. Representations received is summarised in Appendix C
10. The next stage of the scheme is statutory consultation.
Recommendations to the Cabinet Member for Environment, Transport and Recycling 11. On the basis of the results of the public consultation the Cabinet Member is recommended to :
Note representations received during public consultation process, including that from the community council
.Approve proposals that should be taken forward as part of statutory consultation process
Policy implications
12. The recommendations contained within this report are consistent with the polices of the Transport Plan 2011, particularly:
Policy 1.1 – pursue overall traffic reduction Policy 2.3 – promote and encourage sustainable travel choices in the borough Policy 4.2 – create places that people can enjoy Policy 5.1 - Improve safety on our roads and to help make all modes of transport safer.
Community impact statement
13. The implementation of any transport project creates a range of community impacts. All transport schemes aim to improve the safety and security of vulnerable groups and support economic development by improving the overall transport system and access to it.
Resource implications 14. This report is for the purposes of consultation only and there is no resource implications associated with it. 15. It is, however, noted that this project is funded by Transport for London.
Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes from the previous meetingThat the minutes be deferred until the next meeting in order to make amendments to the following: Item 7, Allocation ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.