Delegation for contract award for Phase 2 of Building Schools for the Future
ApprovedExecutive1 paper
AI summaryCabinet recommended the Leader delegate Phase 2 contract award approval to the Children’s Services Cabinet member or Strategic Director, subject to funding confirmation and contribution limits [D][P2]. Earlier programme funding was £179m from Partnerships for Schools and £20m of council funding [P5].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase 2 contracts and school agreements [D][P3]
MoneyClosed version details [P23]Exact Phase 2 commitments are recorded there [P23]
What happens nextNot stated
Who it affectsSchools and governing bodies [P3][P20]Four named schools plus wider school groups [P16][P21][P22]
What was decided
Cabinet recommended that the Leader delegate approval of the Phase 2 contract awards to the Cabinet Member for Children’s Services or the Strategic Director of Children’s Services, whichever is more expedient [D]. The officer proposal was for Cabinet to delegate the authority directly to the Strategic Director [P1]. Report P1
The Table 1 suite covers design, build and operations for St Thomas the Apostle College and Sacred Heart School, design and build for New School Aylesbury and Spa School, Phase 2 ICT for those four schools, a facilities management umbrella contract for schools outside PFI, the management contract between LEP and the PFI Special Purpose Vehicle, the Funders Direct Agreement, deeds of variation, and associated documents and collateral warranties [P16]. Initial terms are 25 years for the Project Agreement and Funders Direct Agreement, no fixed term for the New School Aylesbury and Spa build contracts, five years for ICT, and ten years for facilities management and management [P16]. The ICT extension is five years, the facilities management extension is 5+5+5 years, the management extension is five years, the Project Agreement and Funders Direct Agreement have no extension, and the two build contracts depend on completion of build and a defects period of approx 3 years [P16]. Report P16
Authority also covers agreements with school governing bodies for construction management and ongoing revenue commitments supporting facilities management and ICT services [D][P3][P35]. Award remains conditional on Partnerships for Schools confirming funding, the council contribution staying within the closed report parameters, advice from the Finance Director and Strategic Director of Communities, Law and Governance, and consultation with the Cabinet Member for Children’s Services [D][P2][P24]. Report P2, P3, P24, P35
Why
The delegation was needed because costed proposals, Final Business Case review and funding confirmation left short timescales, with construction intended to start during the summer holiday [P25]. Report P25
The award is a strategic procurement reserved to Cabinet, but Cabinet can delegate it to a chief officer. Delegation to a chief officer was easier to explain to funders and reduced delay risk because the same approach was used for Phase 1 [P33][P34]. Report P33, P34
Partnerships for Schools guidance allows up to 8 weeks for Final Business Case approval. Delay to financial close would have significant financial and reputational implications [P40][P42]. Report P40, P42
What happens next
Submit the Final Business Case to Partnerships for Schools and the Department for Education for approval, then confirm the funding commitment immediately before contract award [P18]. Report P18
Obtain advice from the Finance Director and Strategic Director of Communities, Law and Governance, consult the Cabinet Member for Children’s Services, and check the council contribution against the closed report parameters [P2][P24][P25]. Report P2, P24, P25
Secure the governing body agreements before award, then make the delegated decision. A further Cabinet report will set out revised proposals for St Michael’s and All Angels and Highshore [P3][P11][P18][P35]. Report P3, P11, P18, P35
The money
£179m Partnerships for Schools funding enabled the programme investment [P5] Report P5
£20m Council funding supported Phase 3 projects and programme contingency [P5] Report P5
Options considered
Chosen: Delegate the Gateway 2 award to the Strategic Director of Children’s Services. The award was reserved to Cabinet for a strategic procurement, but could be delegated to a chief officer [P33]. Report P33
Rejected: Have the Leader retain the award function. Although the Leader could discharge the function, this would require a separate report and would be less familiar to funders [P34]. Report P34
Implications
Financial: At financial close, the council will commit to the Table 1 contracts and the commitments made upon establishment of the Local Education Partnership and implementation of Phase 1 schools [P23]. It will not commit to the full Local Education Partnership programme [P23]. Report P23
Financial: Most agreement funding will come from Partnerships for Schools and revenue contributions from schools. Partnerships for Schools must confirm its commitment after Final Business Case approval and immediately before award [P17][P18]. Report P17, P18
Risk: St Michael’s and All Angels and Highshore will not reach contractual close with the rest of Phase 2. Delay, deferment or change may have financial implications [P10][P11]. Report P10, P11
Risk: Delay to financial close would have significant financial and reputational implications [P42]. Report P42
Legal: The award is a strategic procurement reserved to Cabinet, but Cabinet can delegate it to a chief officer. External funders will conduct due diligence on governance and approvals before approving funding [P33][P34]. Report P33, P34
Legal: The council must enter governing body agreements with each school to confirm its authority to make commitments to 4Futures [P35]. Report P35
Equalities: The equalities impact assessment covered the entire programme and was approved by the Executive on May 2 2007 [P29]. Report P29
Other: No new policy implications were identified because the Executive had considered the wider programme in May 2007. The schemes aim to improve learning and teaching environments, support community access and provide flexible spaces for integrated children’s services [P27][P30]. Report P27, P30
Who and where
Phase 2 schools and their governing bodies [P20][P35] Report P20, P35
St Thomas the Apostle College and Sacred Heart School [P8][P16] Report P8, P16
New School Aylesbury and Spa School [P16] Report P16
Schools outside PFI, for facilities management [P21] Report P21
PFI schools, for facilities management and ICT [P22] Report P22
St Michael’s and All Angels and Highshore [P10][P11] Report P10, P11
4Futures [P35] Report P35
Young people and communities in Southwark [P29][P30] Report P29, P30
Timeline
2nd May 2007: The Executive approved the Southwark Schools for the Future Outline Business Case [P5] Report P5
May 2009: Southwark entered a Strategic Partnering Agreement with Transform Schools and established the Local Education Partnership, later rebranded as 4Futures [P6] Report P6
28 May 2010: Costed proposals were received from 4Futures [P44] Report P44
9 June 2010: The final report was dated [P48] Report P48
15 June 2010: Cabinet was due to decide whether to delegate contract award [P41] Report P41
July 2010: Phase 2 site establishment works were programmed to start, with financial close planned for the end of July [P9][P41] Report P9, P41
in due course: A Cabinet report was to set out revised proposals for St Michael’s and All Angels and Highshore [P11] Report P11
July 2011: Financial close for Phase 3 was anticipated [P23] Report P23
Plain English for the jargon
BSF: Building Schools for the Future programme [D][P5]
PfS: Partnerships for Schools [P5]
OBC: Southwark Schools for the Future Outline Business Case [P5]
FBC: Southwark’s Building Schools for the Future Final Business Case [P40]
LEP: Local Education Partnership [P6]
ICT: Information and communication technology [D]
Gateway 2: The award decision for the Phase 2 schools [P33]
PFI: A project and agreement type in this report, used for Sacred Heart and the PFI schools [P8][P22]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16
Resolved
That the cabinet recommends that the leader of the council delegate approval to the cabinet member for children’s services or the strategic director of children’s services, whichever is the most expedient, to approve the contract award for the contracts set out in table 1 of the report, subject to: · confirmation of funding from Partnerships for Schools; · the council’s financial contribution being within the parameters set out in the closed version of the report. · advice from the finance director and strategic director of communities, law and governance and consultation with the cabinet member for children’s services. 2. That the cabinet recommends that the leader of the council delegate approval to the cabinet member for children’s services or the strategic director of children’s services, whichever is the most expedient, to enter into the agreements with the school’s governing bodies as set out in table 2 of the report in regard to the management of the construction phase and ongoing revenue commitments to support facilities management and the information and communication technology (ICT) managed service.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 6 pages
Recommendation
1. That Cabinet delegate authority to the Strategic Director of Children’s Services to approve contract award for the contracts set out in table 1, subject to:
confirmation of funding from Partnerships for Schools; the council’s financial contribution being within the parameters set out in the closed version of this report. advice from the Finance Director and Strategic Director of Communities, Law and Governance and consultation with the Cabinet Member for Children’s Services.
2. That authority is delegated to the Strategic Director of Children’s Services to enter into the agreements with the school’s governing bodies as set out in Table 2 in regard to the management of the construction phase and ongoing revenue commitments to support Facilities Management and the ICT managed service.
BACKGROUND INFORMATION
3. On 2nd May 2007, Southwark Executive approved the Southwark Schools for the Future Outline Business Case (OBC). This OBC outlined a programme of investment in Southwark’s secondary school estate enabled by funding from Partnerships for Schools (PfS) of £179m and supplemented by £20m of council’s own funding to support the Phase 3 projects and provide a contingency across the programme.
4. In May 2009 Southwark entered into a Strategic Partnering Agreement with Transform Schools and a Local Education Partnership was established to deliver the BSF programme. This partnership has since been rebranded as 4Futures.
5. The BSF programme is split into three phases. Phase 1 projects are progressing on site. Current projections are that Tuke will open in September 2010 and St Michael’s in January 2011. These projections are ahead of the opening dates anticipated within the OBC.
6. By September 2009 new project request letters had been issued for the Phase 2 projects (St Michael’s and All Angels and Highshore, St Thomas the Apostle College, Sacred Heart, New School Aylesbury, Spa). These commissioning letters outlined the affordability and other constraints within which the project was to be developed by 4 Futures. 7. Sacred Heart was originally a PFI project planned to be delivered within Phase 3. In August 2009, with PfS approval, Sacred Heart was re-phased in order to mitigate challenges arising in funding of PFI projects and bring about economies through a combined PFI arrangement. It is intended that Sacred Heart is now to be delivered in Phase 2 as a joint PFI project with St Thomas the Apostle College.
8. Phase 2 projects are programmed to start on site in July 2010 in order that essential site establishment works can take place during the school holiday period so that disruption to schools is minimised.
9. St Michael’s and All Angels and Highshore forms part of Southwark’s Phase 2 programme. Concerns have been raised by the Department for Education in regard to the performance of the Academy and their falling rolls. The scheme approved at OBC was to increase the current school roll from 900 to 1200. These proposals are now under review with the Department for Education.
10. This project will no longer reach contractual close with the rest of Phase 2 in July 2010. There are potential financial implications caused by the delay to close and any deferment and/or change to the St Michael’s and All Angels project. A report will be brought to Cabinet in due course outlining revised proposals for the delivery of this project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.