Southwark Schools for the Future: Update to Cabinet and Delegation of Award of Phase 3b Contracts
NotedExecutive1 paper
AI summarySouthwark Cabinet noted Phase 3a’s financial close, while the Leader delegated Phase 3b award for St Michael and All Angels and Highshore, subject to funding confirmation. [D] Phase 3b expects £31,246,720 from Partnerships for Schools; Table 3 records Nil council capital and revenue investment. [P51][P56]
Written from the decision and the officer reportPDF Pro
OutcomeNotedPhase 3b covers St Michael and All Angels and Highshore. [P45]
Money£31,246,720 expected PfS funding. [P51]Diocesan contribution £500,000; anticipated council capital and revenue investment Nil. [P51][P56]
What happens nextCabinet member to approve award. [D]Partnerships for Schools confirmation and Table 3 limits are required. [D]
Who it affectsNot stated
What was decided
Cabinet noted that Phase 3a had reached financial close within the affordability parameters previously approved. [P2] It also noted the current status of the Building Schools for the Future programme. [P3] Report P2, P3
The Leader delegated the Cabinet Member for Children’s Services, consulting the Strategic Director of Children’s Services, to approve the Phase 3b contract award. [P5] Approval is subject to Partnerships for Schools confirming funding and the council contribution staying within the Table 3 parameters. [P6] Report P5, P6
The Leader delegated the same officers to enter into the school interface agreements with the counterparties in Table 2. [P7] Report P7
Why
Delegation was needed because of short timescales, the review of Southwark’s Final Business Case, and confirmation of Partnerships for Schools funding. [P41] Awarding the contract was needed to enable works for the school year in September 2013. [P41] Report P41
The contracts are based on national standard form documents and will receive detailed review from Southwark Legal Services, with advice from Trowers and Hamlins. [P42] Report P42
The interface agreements secure school counterparties’ obligations and financial contributions. [P43] They allow construction and delivery of ICT equipment and facilities management on school sites, and give property and human resources warranties to the council. [P43] Report P43
What happens next
The Cabinet Member for Children’s Services, in consultation with the Strategic Director, will approve the contract award once the funding and financial conditions are met. [D][P5][P6] Report P5, P6
The same officers will enter into the school interface agreements with the Table 2 counterparties. [D][P7] Report P7
A full value for money assessment will be completed before contract award. [P61] The Final Business Case will be submitted for Partnerships for Schools and Department for Education approval immediately before award. [P51] Report P61, P51
The money
£31,246,720 Expected Partnerships for Schools funding for Phase 3b contracts and agreements. [P51] Report P51
£500,000 Diocesan Board of Education commitment for the new church. [P51] Report P51
£1.2m Maximum value authorised for a long term interest at the St Michael and All Angels site, funded through SSF Contingency. [P30] Report P30
£200,000 pa Annual Executive affordability gap commitment for lifecycle and facilities management services across design and build community schools. [P52] No call on it is expected for Phase 3b. [P53] Report P52, P53
£179m Partnerships for Schools funding allocation underpinning the SSF programme. [P9] Report P9
£20m Southwark capital amount initially made available for SSF for 2007 to 2016, later reduced to £17.5m. [P10] Report P10
Options considered
Chosen: Delegate Phase 3b contract award to the Cabinet Member for Children’s Services. Short timescales, the Final Business Case review and funding confirmation required contract award to enable works for September 2013. [D][P41] Report P41
Chosen: Enter school interface agreements through delegated authority. The agreements secure site access, ICT and facilities management delivery, warranties and school financial contributions. [D][P43] Report P43
Chosen: Smaller St Michael and All Angels school with alternative sponsorship. Falling roll evidence had raised concerns about the original expansion, and the Academy and Department for Education agreed a smaller school and alternative sponsorship. [P25] Report P25
Rejected: Refurbish part of Southwark College’s Camberwell Site for Key Stage 4 inclusive learning services. Southwark College has alternative plans for the site, so the proposal was no longer viable. [P37] Report P37
Implications
Financial: Table 3 records Nil anticipated council construction capital and ongoing services revenue investment. [P56] The council still bears risk if Highshore’s school roll and budget share fall, covering shortfalls in facilities management and lifecycle costs above the agreed contribution. [P54][P69] Report P56, P54, P69
Legal: Contracts will be entered concurrently as linked agreements based on national standard forms. [P42] Southwark Legal Services will review the documents, with advice from Trowers and Hamlins. [P42] Report P42
Legal: School interface agreements allow construction on sites not owned by the council and delivery of ICT equipment and facilities management. [P43] They also secure warranties and financial contributions from counterparties. [P43] Report P43
Risk: For Academies and Voluntary Aided schools, the council will require commitments covering the full cost of any facilities management service and will not bear falling roll risk. [P54] Report P54
Financial: Highshore is to be granted a lease for up to 125 years. [P30][P45] Any annual lease charge is expected to be met from the dedicated schools grant. [P31] Report P30, P45, P31
Risk: Southwark’s own funding for unconfirmed projects will need to be considered against existing commitments, risks and other priorities. [P58] Report P58
Risk: A full value for money assessment must be completed before Phase 3b contracts are awarded. [P61] Report P61
Equalities: The equalities impact assessment was approved for the whole SSF project. [P63] It says schemes should ensure higher quality learning and teaching environments, support community access and provide flexible spaces for integrated children’s services. [P64] Report P63, P64
Who and where
Pupils at St Michael and All Angels and Highshore Report P25, P45, P64
The governing body of each participating school Report P47
ARK Schools and the Highshore School Academy Trust Report P25, P45
The Diocesan Board of Education and church authority Report P28, P45, P51
4 Futures Report P45
The Phase 3a schools at Bredinghurst, St Saviour’s, St Olave’s, The Charter and Notre Dame Report P22
Partnerships for Schools and the Department for Education Report P51
Southwark communities Report P63, P64
Timeline
28 November 2006: Southwark Executive made £20m available in the capital programme for SSF for 2007 to 2016. [P10] Report P10
2 May 2007: Southwark Executive approved the SSF Outline Business Case, which set out £179m of Partnerships for Schools funding. [P9] Report P9
May 2009: Southwark entered into a Strategic Partnering Agreement with 4 Futures to deliver the BSF programme. [P11] Report P11
Financial close: The project stage at which funding is confirmed and contracts are entered. [P41][P51]
ICT: School equipment and services, including infrastructure. [P45]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Decisions of the Cabinet 1. That it be noted that phase 3a of Southwark’s Schools for the Future (SSF) programme ‘investment at Bredinghurst , St Saviour’s and St Olave’s , The Charter and Notre Dame’ has reached financial close within the affordability parameters previously approved by cabinet. 2. That the current status of the Building Schools for the Future (BSF) programme be noted. Decisions of the Leader of the Council 3. That authority be delegated to the cabinet member for children’s services in consultation with the strategic director of children’s services to approve the contract award for the contracts set out in Table 1 of the report, relating to the financial close of Phase 3b - a new Academy at St Michael’s and All Angel’s in Camberwell and the co-location of Highshore Special School, subject to: · confirmation of funding from Partnerships for Schools; · the council’s financial contribution being within the parameters set out in Table 3 of the report. 4. That authority be delegated to the cabinet member for children’s services in consultation with the strategic director of children’s services to enter into the school interface agreements with the school counterparties set out in Table 2 of the report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 9 pages
Recommendations
Recommendation for the Cabinet
1. Cabinet note that Phase 3a of Southwark’s SSF programme - investment at Bredinghurst, St Saviour’s and St Olave’s, The Charter and Notre Dame - has reached financial close within the affordability parameters previously approved by Cabinet.
2. Cabinet note the current status of the BSF programme.
Recommendations for the Leader of the Council
3. That the Leader delegates authority to the Cabinet Member for Children’s Services in consultation with the Strategic Director of Children’s Services to approve contract award for the contracts set out in Table 1, relating to the financial close of Phase 3b – a new Academy at St Michael’s and All Angel’s in Camberwell and the co-location of Highshore Special School, subject to:
• confirmation of funding from Partnerships for Schools; • the council’s financial contribution being within the parameters set out in Table 3.
4. That the Leader delegates authority to the Cabinet Member for Children’s Services in consultation with the Strategic Director of Children’s Services to enter into the school interface agreements with the school counterparties set out in Table 2.
BACKGROUND INFORMATION
5. On 2 May 2007, Southwark Executive approved the Southwark Schools for the Future Outline Business Case (OBC). This OBC outlined a programme of investment in Southwark’s secondary school estate enabled by funding from Partnerships for Schools (PfS) of £179m.
6. On 28 November 2006, Southwark Executive made available £20m in Southwark’s capital programme for 2007 to 2016 for Southwark Schools for the Future. This was subsequently reduced to £17.5m in the Capital Refresh report in July 2011.
7. In May 2009 Southwark entered into a Strategic Partnering Agreement with 4 Futures to deliver the Building Schools for the Future (BSF) programme.
8. The BSF programme was to be procured in three phases. The £179m funding allocation is based at 1 Quarter 2008 and excludes VAT. It is subject to inflation and deflation over the life of the programme and to formal approval by PfS ahead of project development and financial close of individual schemes.
KEY ISSUES FOR CONSIDERATION
Phase 1
9. Phase 1 projects are Tuke Special School and St Michael’s Catholic College. Tuke School was a design and build project and opened in September 2010. St Michael’s Catholic College is a PFI project and opened in January 2011. Works for the second Phase of demolition and landscaping were completed in Summer 2011.
10. Both schools are now receiving facilities management and ICT services through 4 Futures.
Phase 2
11. Phase 2 projects (St Thomas the Apostle College, Sacred Heart and New School Aylesbury and Spa) reached financial close on August 17 2010.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.