Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking Services
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved the procurement strategy for a framework of five bailiff companies, lasting four years from 1st April 2011. [D] [P1] It covers debt collection and enforcement for Revenues and Benefits and Parking Services, with an estimated nominal total value of £5,400,000. [P23] [P24]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFive company framework for two council services [P1]
Money£5,400,000 estimated total [P23]
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet approved the procurement strategy for a framework of five suitable bailiff companies. It will provide legal enforcement and debt collection for Revenues and Benefits and Parking Services. Report P1
The first 3 months will have an equal allocation across suppliers. Later work will be based on collection rate, collection speed and quality. The framework does not guarantee work. Report P17, P18, P19, P20, P21, P22, P23
Other council services may use the framework where their requirements match. It will last for four years from 1st April 2011. Report P1, P25, P101
Why
The Revenues and Benefits service was approved to return in house. The parking contracts were due to expire on 30th June 2011 and did not include bailiff services. Report P6, P9, P11, P12
Combining the services was considered suitable because their requirements and timescales overlapped, while Revenues and Benefits had higher volumes and values. Report P13
A framework maintains competition through performance based allocations. It also lets the council stop allocating work to nonperforming suppliers without terminating a contract. Report P30
What happens next
Consult other boroughs for draft specifications, then develop the full specification, PQQ and ITT documents with service experts, procurement advisers and legal advisers. Report P56, P57, P58, P59
Advertise through OJEU and relevant trade journals, assess PQQ responses, shortlist applicants, invite tenders and evaluate the bids. Report P61, P63, P64, P65, P66, P67, P68, P70, P71, P72
Secure Gateway 2 approval for the contract award. Contract award was planned for 22/02/2011, with the contract start set for 01/04/2011. Report P52
The money
£5,400,000 Total estimated framework value Report P23
£1,350,000 Estimated annual framework value over 4 years Report P23
£750,000 Revenues and Benefits annual cost Report P23
£3,000,000 Revenues and Benefits contract cost Report P23
Chosen: Combined procurement for Revenues and Benefits and Parking Services. The requirements and timescales were compatible, and Revenues and Benefits had higher volumes and values. Report P13
Chosen: Framework agreement with five bailiff companies. Performance based allocation creates competition and allows the council to stop work to nonperforming suppliers without terminating the contract. Report P30
Chosen: Full EU restricted procedure. The route was confirmed as satisfying the council's Contract Standing Orders. It includes PQQ shortlisting before tender invitation. Report P64, P68, P100, P106
Rejected: Separate procurements for the two services. If suitable companies could not cover both services, separate procurement would need to handle both areas with double the resource expense. Report P40, P41
Rejected: Buying Solutions framework agreements. None of the available frameworks covered the specialist processing required. Report P36
Rejected: Normal contracts with one or more bailiff companies. Although possible, the report identifies valid reasons for using a framework agreement. Report P30
Chosen: Four year framework period. EU rules generally limit frameworks to four years, and the report identified no exceptional circumstances. Report P101
Chosen: 70% quality and 30% cost tender weighting. Most bailiff fees are restricted by legislation, leaving little scope for meaningful cost competition, while quality is important. Report P68, P107
Implications
Financial: Most enforcement services are cost neutral because debtors pay the fees. The council pays commission for some debt collection and VAT. Debt collection costs can be contained within existing budgets. Report P24, P80, P93, P103
Staffing: Parking plans to appoint a dedicated bailiff manager and contract monitoring officer. Identified savings within parking enforcement procurement will cover the additional resource. Report P91
Legal: TUPE could apply, but legal advisers consider it unlikely to affect these services because no supplier is guaranteed regular work and there would be no dedicated team for staff transfers. Report P54
Legal: The service is Part B under EU procurement rules, so full EU tendering requirements do not apply. OJEU advertising is voluntary, but council rules require all reasonable steps to obtain at least 5 tenders. Report P100
Risk: Monthly performance monitoring will apply. Suppliers below the collection rate threshold will receive no more work of that type, while quality failures stop all allocations until the council is satisfied with revised processes. Report P18, P19, P20, P21, P22, P86
Equalities: PQQ shortlisting includes equalities and diversity as a pass or fail criterion. The specification must set conduct standards and identify when vulnerability makes enforcement unwise. Report P65, P77
Climate: Shortlisted suppliers must meet environmental standards, including carbon reduction, fewer journeys, green vehicles and no breach of environmental law. Report P84
Staffing: Revenues and Benefits will need a new service structure with an officer covering the required activities. Report P92
People owing Council Tax or Business Rates Report P16, P27
People owing penalty charge notices or sundry debts Report P16
People owing Housing Benefit overpayments, if included Report P16
Other council services eligible to use the framework Report P25, P105
Bidders and future framework suppliers Report P61, P72
Parking and Revenues and Benefits staff Report P90, P91, P92
Timeline
20/07/2010: Planned approval of the Gateway 1 procurement strategy report Report P50
30/07/2010: Planned completion of PQQ documentation Report P50
21/09/2010: Planned invitation to tender Report P50
01/11/2010: Planned closing date for tender returns Report P50
25/01/2011: Planned Cabinet approval of the Gateway 2 contract award report Report P52
22/02/2011: Planned contract award Report P52
01/04/2011: Planned contract start Report P52
30th June 2011: Parking enforcement contracts expire. The parking framework is needed by July 2011. Report P9, P12
Plain English for the jargon
Bailiff: A company that enforces debts and collects payment under court orders and related powers. [P27] [P29]
Framework agreement: An arrangement with five companies where work is allocated by performance rather than guaranteed. [P15] [P17] [P18]
Call off: To order services from the framework when a business unit has a matching need. [P25] [P58]
Court enforcement orders: Liability Orders enforce Council Tax and Business Rates, while Warrants of Execution collect penalty charge notices, or PCNs. [P16] [P27]
MACR: Minimum Acceptable Collection Rate. A supplier below it receives no more work of that type. [P18]
OJEU: Official Journal of the European Union, where the contract will be advertised. [P61] [P100]
PQQ: The supplier shortlisting stage. A failure at any stage eliminates a supplier from the process. [P63] [P64] [P66]
TUPE: A possible staff transfer issue that legal advisers consider unlikely to affect these services. [P54]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That the procurement strategy outlined in the report for the creation of a framework of five suitable bailiff companies to provide legal enforcement and debt collection services to both the revenues & benefits service and parking services be approved. The framework to also be available to other parts of the council who may wish to call on the services provided within it. The framework to last for four years from 1 April 2011.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 13 pages
Recommendation
6. That Cabinet approve the procurement strategy outlined in this report for the creation of a framework of five suitable bailiff companies to provide legal enforcement and debt collection services to both the Revenues & Benefits service and Parking Services. The framework to also be available to other parts of the Council who may wish to call off the services provided within it. The framework to last for four years from 1st April 2011. BACKGROUND INFORMATION
History – Revenues and Benefits
7. The Council let the Revenues & Benefits contract originally in 1998 to Cipfa Services Ltd (CSL) now known as Liberata UK Ltd. In 2003 the Executive approved the renewal of the contract with a 2 year rolling contract period which has been extended year on year since then. Additional efficiencies and changes to the bonus structure were included in the contract in 2007.
8. At the Council Assembly meeting of 28th January 2009 the Executive Member for Resources addressed members concerns on recent performance. The decision not to extend the contract was taken following the partnership board on 31st March 2009. The contract provides for a two year transition period, which ends on the 31st March 2011.
9. On May 19th 2009 the Executive approved the decision to allow the Liberata contract to expire. The Executive further agreed to receive a report and Gateway 1 (as appropriate) providing a recommendation of the preferred option for delivery of the Revenues & Benefits service from 1st April 2011.
10. On September 29th 2009 the Executive received the Gateway 1 and accepted the recommendation within it to bring the Revenues and Benefits service back in house.
History – Parking Services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Report: Gateway 1: Procurement Strategy Approval, Framework Contracts to Provide Balliff Services to the Revenues & Benefits and Parking ServicesReport
14Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesThis decision
Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesThis decision
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.