Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers Framework

Approved Executive 1 paper

AI summarySouthwark Cabinet approved the procurement strategy for a four year barristers framework serving Southwark and Lambeth [D]. It targets at least £100k per annum in savings, and award approval is delegated, with a Southwark only framework held in reserve if the partnership cannot proceed [D] [P12].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFramework for Southwark and Lambeth over four years [D]
Moneyat least £100k per annum [P12]Targeted savings over the four year period [P12]
What happens nextAward approval delegated [D]Leader may choose the most expedient delegate [D]
Who it affectsMost council departments [P13]Barristers spending and service budgets are affected [P1] [P13]

What was decided

Cabinet approved the procurement strategy for an inter borough barristers framework serving Southwark and Lambeth over four years [D].

The Leader will delegate approval of the framework contract award to the Cabinet Member for Finance and Resources or the Strategic Director of Communities, Law and Governance, whichever is most expedient [D].

Cabinet approved a reserve position for developing a Southwark only framework if the Lambeth partnership does not proceed as envisaged [D].

Why

Southwark chose partnership with Lambeth to increase buying power and secure greater efficiencies [P16]. Report P16

Current barrister costs are around £1.5m, and the procurement targets at least £100k per annum in savings over the four year period [P12]. Report P12

Consultation feedback called for an easy to use framework, competition from a wide field of barristers chambers, and strong post award performance and contract management [P3]. Report P3

What happens next

The Leader is to delegate approval of the framework contract award to the Cabinet Member for Finance and Resources or the Strategic Director of Communities, Law and Governance, whichever is most expedient [D]. The award is to follow the reasons set out in paragraph 11 [D] [P11]. Report P11

Approval is given to hold a reserve position for developing a Southwark only framework if the Lambeth partnership does not proceed as envisaged [D].

At Gateway 2, contract award proposals should be notified to all Chief Officers for comment [P13]. The joint project board will agree all tender documentation, including evaluation methods and criteria, before the framework goes to market [P18]. An operational guidance manual defining how work is ordered will need to be included in the tender documentation [P19]. Report P13, P18, P19

The money

  • at least £100k per annum Targeted Southwark savings over the four year period [P1] [P12] Report P1, P12
  • £1.5 million Estimated annual spending on barrister services [P1] Report P1
  • around £1.5m Current cost of barristers [P12] Report P12
  • in excess of £4million Strategic procurement value threshold [P8] Report P8

Options considered

  • Chosen: Inter borough framework with Lambeth. The partnership is intended to secure greater efficiencies by increasing buying power [P16]. Report P16
  • Chosen: Southwark only framework held in reserve. Approval was given to hold this position if the Lambeth partnership does not proceed as envisaged [D].
  • Chosen: Open competitive tender with at least 5 tenders. Contract Standing Orders require public advertising and at least 5 tenders, with relevant trade journals including the Law Society Gazette and Counsel Magazine [P9]. Report P9
  • Rejected: Full application of the Public Contract Regulations 2006. Legal Services are part B services, so full application is not required, although general EU principles still apply [P9]. Report P9

Implications

  • Financial: Service departments meet barrister costs, with likely savings greatest in Children’s Services and Housing [P1]. Management costs for introducing the framework will be met from Legal Service’s operations budget [P1]. Report P1
  • Financial: Savings should be reflected in the 2010/11 revenue monitor and the 2011/12 to 2013/14 budget setting process [P12]. Framework fee rates are proposed for annual review [P1]. Report P12, P1
  • Legal: Strategic procurement approval is reserved to Cabinet because the value is in excess of £4million [P8]. The Leader’s delegation is supported by Section 14 of the Local Government Act 2000, as amended [P10]. Report P8, P10
  • Legal: The report describes the procurement as having no EU procurement implications [P21]. The tender must still seek at least 5 tenders through public advertising and satisfy general EU principles on transparency and avoiding discrimination [P9]. Report P21, P9
  • Risk: Performance management systems should improve visibility of spending and support service and budget planning [P1]. Careful management is needed to keep commissioning within budgets, monitor spend and achieve savings [P13]. Report P1, P13
  • Risk: A Southwark only framework remains available as a reserve if the Lambeth partnership does not proceed as envisaged [D].
  • Staffing: Legal Services managers and staff, together with senior managers from Children’s Services and Housing, have been engaged in developing the framework [P3]. Report P3
  • Other: Because the contract is cross cutting, all Chief Officers should comment on award proposals at Gateway 2 [P13]. Report P13

Who and where

  • Southwark Council
  • Lambeth Council
  • Southwark service departments Report P1
  • Legal Services Report P1
  • Children’s Services Report P1
  • Housing Report P1
  • Barristers chambers Report P3
  • All Chief Officers Report P13

Timeline

  • 12/04/2010: Key Decision recorded on the forward plan [P29] Report P29
  • 29/06/2010: Final report dated [P29] Report P29
  • 29.06.10: Final report sent to the Constitutional Team [P35] Report P35
  • 30th November 2010: The four year period for procuring Barristers Services is planned from this date [P11] Report P11
  • 2010/11: Savings should be reflected in the revenue monitor [P12] Report P12
  • 2011/12 to 2013/14: Savings should be reflected in the budget setting process [P12] Report P12
  • annually: Framework fee rates are proposed for review [P1] Report P1

Plain English for the jargon

  • Gateway 1: Stage at which Cabinet approves the procurement strategy [P8]
  • Gateway 2: Stage for contract award proposals [P13]
  • Strategic procurement: Procurement with a value in excess of £4million, with approval reserved to Cabinet [P8]
  • Framework: Procurement arrangement with procedures defining how work is ordered [P19]
  • Part B services: Category including Legal Services under the Public Contract Regulations 2006 [P9]
  • Contract Standing Orders: Council rules requiring at least 5 tenders following public advertising [P9]
  • Performance management systems: Systems intended to improve visibility of spending and help deliver savings [P1]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

1 That the procurement strategy outlined in the report for an inter borough Barristers framework arrangement serving Southwark and Lambeth extending over a period of 4 years be approved. 2 That the leader of the council delegate approval to the cabinet member for finance and resources or the strategic director of communities, law and governance, which ever is the most expedient, to award the framework contract for the reasons set out in paragraph 11 of the report. 3 That approval be given to there being a reserve position for the development of a unilateral, ‘Southwark only’ framework in the unlikely event that the partnership with Lambeth Council does not proceed as envisaged.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 12 pages

Classification: Open Item No Date: 07/07/2010

To Cabinet Report title Gateway 1 - Procurement Strategy Approval Southwark and Lambeth Barristers Framework Ward(s) or groups affected From Cabinet Member for Finance and Resources

FOREWORD – RICHARD LIVINGSTONE, CABINET MEMBER FOR FINANCE AND RESOURCES

This report asks the Cabinet to approve the procurement strategy for the inter-borough Barristers framework arrangement for Southwark and Lambeth. It is the first decision that the Cabinet will take to work more closely with one of our neighbours and as such is in line with the new administration’s priorities to find innovative ways to find financial efficiencies through joint working with other South London authorities. As Cabinet member, I am asking that Cabinet, after consideration, approve this decision at the meeting on 7 July so that we can proceed along the timescale agreed with our colleagues in Lambeth.

RECOMMENDATION (S)

1. That the Cabinet approve the procurement strategy outlined in this report for an inter borough Barristers framework arrangement serving Southwark and Lambeth extending over a period of 4 years.

2. That the Cabinet recommends that the Leader of the Council delegate approval to the Cabinet Member for Finance and Resources or the Strategic Director of Communities, Law & Governance, whichever is the most expedient, to award the framework contract for the reasons noted in paragraph 11 of this report.

3. That the Cabinet approve a reserve position for the development of a unilateral, ‘Southwark only’ framework in the unlikely event that the partnership with Lambeth Council does not proceed as envisaged.

BACKGROUND INFORMATION

4. Barristers are currently commissioned on a spot purchase basis from barristers’ chambers. Legal Service professionals tend to use a selected number of chambers but there is no agreed fee structure across the division. In this respect, fees vary widely from £150 for advocacy on a possession case to £750 for a full day at court. Expenditure on Barristers fees amounted to £1.35 million in 2007/8, £1.6 million in 2008/9 and at the time of writing this report on the 22nd June, it is estimated that spend will be in the region of £1.5 million when accounts are closed for the last financial year. This figure covers all expenditure incurred by Southwark’s own in-house legal team where the specialist legal advice of barristers is required but does not however take account of spend on barristers commissioned through external solicitors on particularly complex cases such as the cemeteries investigation. The table below sets out spend on barristers across Legal Services with the highest spend represented by the Children and Adults team, explained by several factors including, Southwark handling the highest proportion of child protection cases in London. Counsel spend 2009/10 as of January 2010

Section £ Planning litigation £56,977 Housing litigation £439,404 Children and adults £471,330 Property £3,209 Contracts £8,771 General litigation £ 146,555 Constitutional £9,774

Summary of the business case/justification for the procurement

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1: Procurement Strategy Approval: Southwark and Lambeth Barristers FrameworkReport 12 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
PJ
Councillor Peter John OBEChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present

On this subject at Southwark

Search all
  1. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  4. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  5. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed
  6. Gateway 1 - Procurement Strategy Approval: Consolidated Facilities Management Contract for 160 Tooley StreetApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies