Approval of the Council's Transport for London Funded Work Programme for 201/112 and Indicative Programme 2013/14 for Submission to Transport for London

Agreed Executive 3 papers

AI summarySouthwark Cabinet approved the TfL funded transport programme for 2011/12 and indicative work for 2012/13 and 2013/14. [D] TfL must receive it by 8 October 2010; it will be implemented, with the transport cabinet member deciding the use of £100k discretionary funding. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedIdentifies 2011/12 projects and indicative 2012/13 and 2013/14 work. [D]
Money£100k discretionary funding [D]Transport cabinet member determines its use. [D]
What happens nextDue 8 October 2010 [D]It goes to the Mayor of London for approval. [P26]
Who it affectsSouthwark residents and workers [P31]Funded schemes should provide a tangible benefit. [P31]

What was decided

Approved the content of the TfL submission, covering projects for 2011/12 funding and indicative work for 2012/13 and 2013/14 in appendices A and B, and agreed its implementation. Report P3, P5

Required the agreed programme to be submitted to TfL by 8 October 2010. Report P4

Authorised the cabinet member for transport, environment and recycling to vary the 2011/12 programme, consult community council chairs about changes, and determine the use of £100k discretionary funding. Report P8, P9, P10

Why

The limited funding and number of possible projects required officers to prioritise schemes against local priorities, borough wide priorities, and strategic policies and objectives. Report P21, P22, P23

Community councils ranked known transport issue areas and suggested alternatives, and their feedback significantly shaped scheme selection. Report P21, P22, P39

The programme is consistent with the existing Local implementation plan, emerging transport plan, council policies, and the Mayor's Transport Strategy. Report P28, P29

What happens next

Submit the agreed programme to TfL by 8 October 2010 for consideration and approval by the Mayor of London. Report P4, P26

Implement the agreed programme, following formal consultation after TfL confirmation and before detailed design or implementation. Report P5, P41

Have the cabinet member consult community council chairs about any programme variations and decide the use of £100k discretionary funding for transport purposes consistent with the Mayor's Transport Strategy. Report P8, P9, P10, P47

The money

  • £100k TfL discretionary funding for 2011/12, with its use delegated to the cabinet member for transport, environment and recycling. Report P9, P10, P16
  • £3.126m Southwark's total TfL Local implementation plan allocation for 2011/12. Report P16
  • £2.774m Corridors and neighbourhoods funding within the 2011/12 allocation. Report P16
  • £352k Smarter travel funding within the 2011/12 allocation. Report P16
  • £26m Available across London for area based schemes in 2011/12. Report P17
  • £354k Provisional allocation for principal road network maintenance in 2011/12. Report P18
  • £3.349m Council funding allocation for 11/12. Report P20
  • £3.537m Equivalent funding received in 2010/11, excluding area based schemes and principal road renewal. Report P20

Options considered

  • Chosen: Approve the proposed TfL submission.. It identifies projects for 2011/12 and indicative work for 2012/13 and 2013/14. Report P3
  • Chosen: Submit the programme to TfL by 8 October 2010.. The submission is required for consideration and approval by the Mayor of London. Report P4, P26
  • Chosen: Implement the agreed programme. Report P5
  • Chosen: Delegate programme variations to the cabinet member.. Community council chairs must be consulted about scheme changes. Report P8
  • Chosen: Delegate the £100k discretionary funding decision.. The funding must support transport purposes consistent with the Mayor's Transport Strategy. Report P9, P10, P47

Implications

  • Financial: No adverse resource implications were identified because funding will come entirely from TfL budgets. Report P51
  • Financial: Indicative management and implementation costs for each scheme were taken into account in the submission. Report P37, P38
  • Legal: Section 145 of the GLA Act 1999 requires each London council to prepare a Local implementation plan. Report P12
  • Equalities: An equality impact assessment was completed, with ongoing monitoring to identify adverse effects and minimise them where possible. Report P32, P33
  • Climate: An environmental assessment was completed as part of developing the Local implementation plan. Report P32
  • Risk: The allocation excludes major schemes, principal road network maintenance, and bridge strengthening and assessment works; major schemes can be bid for separately, while the other works are funded on a needs basis. Report P17, P18
  • Other: Several projects improving child safety are included and support the council's sustainable travel aims. Report P35
  • Other: Formal consultation after TfL confirmation gives community councils and residents opportunities to influence detailed design. Report P41

Who and where

  • People living and working in Southwark Report P31
  • All Southwark residents Report P33
  • Children Report P35
  • People in community council areas across the borough Report P21, P22
  • Community councils and residents affected by cross borough proposals Report P24, P40, P41
  • Transport for London and the Mayor of London Report P26

Timeline

  • February 21 2007 and March 20 2007: The Mayor of London approved the Local implementation plan, and the council's cabinet adopted it. Report P12
  • July 2009: Officers sought local feedback on the proposed three year programme. Report P39
  • May 2010: The Mayor published a revised transport strategy, requiring boroughs to revise their Local implementation plans. Report P13
  • September 2010: Community council meetings were used to seek local views on the refreshed programme. Report P24, P40
  • 10 September 2010: The final report was dated. Report P58
  • October 2010: Southwark planned to resubmit the Camberwell town centre scheme for separate funding. Report P17
  • 8 October 2010: The agreed programme was due to be submitted to TfL. Report P4
  • December 2010: The council's transport plan was due for public consultation. Report P13

Plain English for the jargon

  • TfL: Transport for London. [P3]
  • Lip: Local implementation plan, detailing how a council will assist in delivering the Mayor's Transport Strategy. [P12]
  • GLA 1999: Greater London Authority Act 1999. [P12]
  • APR: The Local implementation plan annual progress report, which forms part of the annual TfL funding process. [P14]
  • Major and area based schemes: Large urban realm and accessibility projects that councils can bid for separately from the main allocation. [P17]
  • Principal road renewal: Maintenance of the principal road network. [P18]
  • Hot spots: Transport issue areas identified from available data and community reports. [P21]
  • Mayor's Transport Strategy: The transport strategy that borough Local implementation plans must support and respond to. [P12] [P13]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Decisions of the cabinet 1. That the content of the council’s proposed submission to Transport for London ( TfL ) identifying transport projects to be delivered with TfL Local implementation plan (Lip) funding in 2011/12 and the indicative programme of work for the years 2012/13 and 2013/14 as contained in appendices A and B of the report be agreed. 2. That the identified programme be submitted to TfL by 8 October 2010. 3. That the agreed programme as set out in appendices A and B of the report be implemented. Decisions of the leader of the council 4. That the authority of the cabinet member for transport, environment and recycling to amend the programme for 2011/12 should any variations to the proposed programme be required be confirmed. The cabinet member shall consult community council chairs regarding scheme changes in their area. 5. That authority be delegated to the cabinet member for transport, environment and recycling to determine the most appropriate use of the £100k discretionary funding allocated by TfL for 2011/12.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 6 pages

Recommendations

Recommendations for Cabinet

That the Cabinet

4. Agrees the content of the council’s proposed submission to Transport for London (TfL) identifying transport projects to be delivered with TfL Local implementation plan (Lip) funding in 2011/12 and the indicative programme of work for the years 2012/13 and 2013/14 as contained in appendices A and B.

5. Agrees that the identified programme be submitted to TfL by October 8 2010.

6. Agrees to the implementation of the agreed programme as set out in appendices A and B.

Recommendations for Leader of the Council

That the leader

7. Confirms the authority of the Cabinet member for transport, environment and recycling to amend the programme for 2011/12 should any variations to the proposed programme be required. The cabinet member shall consult community council chairs regarding scheme changes in their area.

8. Delegates authority to the cabinet member for transport, environment and recycling to determine the most appropriate use of the £100K discretionary

1 funding allocated by TfL for 2011/12.

BACKGROUND INFORMATION

9. Section 145 of the Greater London Authority Act 1999 (GLA 1999) requires each council in London to prepare a Local implementation plan (Lip) to detail how the authority will assist in delivering the Mayor’s Transport Strategy.. The council’s Lip was approved by the Mayor of London on February 21 2007 and adopted by the council’s cabinet on March 20 2007.

10. In May 2010, the Mayor of London published his revised transport strategy all boroughs are required to revise their Local implementation plan in response to the new strategy. The council’s transport plan (incorporating the requirements of the local implementation plan) is due for public consultation in December 2010.

11. TfL provides financial assistance to boroughs, sub-regional partnerships and cross-borough initiatives under section 159 of the GLA Act 1999. All councils within London are able to obtain funding on an annual basis to deliver schemes identified in the Lip. This process is part of the Lip annual progress report (APR).

12. The overall TfL Lip budget remains similar with £155 million of transport funding for London authorities in 2011/2012 and £150m for 2011/12 and 2012/13.

13. Southwark’s allocation for 2011/12 is £3.126m comprising of £2.774m for corridors and neighbourhoods, £352k for smarter travel and £100k of discretionary funding to be spent as the council sees fit. This is the total funding that the borough should expect to receive for the integrated transport programme.

14. The above allocation does not include major schemes (large urban realm and accessibility projects). The council can still bid for area based schemes separately with £26m available for allocation across London in 2011/12. The council will be resubmitting the Camberwell town centre scheme in October 2010 for funding through this programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval of the Council's TfL funded work programmeAppendix A 1 pages Download
PDF
Approval of the Council's TfL funded work programmeAppendix B 1 pages Download
PDF
Report: Approval of the Council's TfL funded work programmeReport 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, apologies due to council business
VW
Councillor Veronica WardCommittee Member, present

On this subject at Southwark

Search all
  1. Approval of the Council's Transport for London Funded Work Programme for 201/112 and Indicative Programme 2013/14 for Submission to Transport for LondonThis decision
  2. Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonAgreed
  3. Approval of the Council's Transport for London funded work programme for 2013/14 and indicative programme to 2014/15 for submission to Transport for LondonAgreed
  4. Gateway 1 - Procurement Strategy Approval: Special Educational Needs and/or Disability School Bus TransportApproved
  5. Approval of the Council's Response to the Transport for London (TfL) Bakerloo Line Extension ConsultationAgreed
  6. Gateway 2 - Contract Award Approval - Special Educational Needs and/or Disabilities (SEND) School Bus TransportApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open