Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for London
AgreedExecutive3 papers
AI summarySouthwark Cabinet approved transport projects for 2012/13 and an indicative 2013/14 programme, with £3.445m allocated. [D] [P14] Submit the programme to TfL by 7 October 2011; authority over £100,000 discretionary funding was delegated. [D] [P3]
Written from the decision and the officer reportPDF Pro
OutcomeAgreed2012/13 projects plus indicative 2013/14 work [P2]
Money£3.445m TfL allocation [P14]For 2012/13, including £2.875m, £471k and £100,000 [P14] [D]
What happens nextSubmit to TfL [D] [P3]Due by 7 October 2011 [P3]
Who it affectsSouthwark’s residents and workers [P28]Funded schemes should provide a tangible positive benefit [P28]
What was decided
The Cabinet agreed the TfL submission for 2012/13 and the indicative 2013/14 programme. It must be submitted by 7 October 2011. Report P2, P3
The Cabinet approved implementation of the programme set out in Appendices A and B. Report P4
The Leader of the Council delegated authority to the cabinet member for transport, environment and recycling to determine the use of the £100K discretionary funding. Report P7
Why
London councils must prepare a Local implementation plan to show how they will help deliver the Mayor’s Transport Strategy. Report P9, P10
Officers assessed transport issues using available data and community reports. They then prioritised projects because funding was limited. Report P19, P20
The programme is consistent with the council’s transport plan, wider policy framework and the Mayor’s Transport Strategy. Report P25
What happens next
Submit the identified programme to TfL by 7 October 2011. Report P3
The cabinet member must consult the relevant community council chair when considering variations. For cross borough schemes, the chairs of both community councils must be consulted. Report P5
After TfL confirms the projects, undertake formal consultation before detailed design or implementation. Report P39
The money
£3.445m Southwark’s integrated transport programme allocation for 2012/13 Report P14, P52
£2.875m Corridors, neighbourhoods and supporting measures Report P14
£471k Provisional principal road renewal or bridge strengthening funding Report P14, P15
£100,000 Discretionary funding whose use was delegated Report P7
£3.349m Equivalent 2011/12 funding, excluding area based schemes and principal road renewal Report P18
£28m Available across London for major schemes in 2012/13 Report P16
£147.8 million Overall TfL Lip budget for London authorities in 2012/2013 Report P13
£155m London authorities’ transport funding for 2010/11 Report P13
Implications
Financial: TfL’s final approval is required for the £3.445m allocation. If the submission is restricted, officers will prepare a further report. Report P52
Financial: Major schemes are outside this allocation. The council can bid for them separately, and further funding will be sought for Camberwell town centre streetscape improvements. Report P16
Legal: After the Mayor approves the LIP, the council must implement it according to the timetable. If the council does not perform proposals satisfactorily, the Mayor may act at the council’s expense. Report P45, P46
Legal: The Mayor may give legally binding directions. TfL may impose conditions on financial assistance. Report P46, P47
Equalities: All six equality strands were assessed, and equalities will continue to be monitored during delivery. Report P48
Risk: Annual monitoring will assess impacts across different groups and minimise adverse implications where possible. Report P31
Other: A strategic environmental assessment was completed and the community impact was considered. Report P29
Staffing: Officer time needed to implement the recommendations is within existing budgeted resources. Report P52
Who and where
People living and working in Southwark Report P28
All Southwark residents Report P30
People affected by transport issues in community council areas Report P19
May 2010: The Mayor of London published the revised transport strategy. Report P10
late 2010/early 2011: The Transport Plan consultation ran for twelve weeks. Report P35
July 2011: The council adopted its transport plan. Report P10
September: Officers planned to advise community councils of the programme and seek local views. Report P21, P38
8 September 2011: The report was finalised. Report P59
7 October 2011: The programme was due to be submitted to TfL. Report P3
2012/13: Delivery of the agreed programme. Report P2, P4, P14
2013/14: The indicative programme of work was agreed. Report P2
Plain English for the jargon
TfL: Transport for London, which provides financial assistance and confirms borough programmes [P11] [P12]
Local implementation plan (LIP): A council plan showing how it will help deliver the Mayor’s Transport Strategy [P9]
Mayor’s Transport Strategy: The strategy that London council LIPs must help implement [P9] [P44]
Annual progress report (APR): The annual process through which councils obtain TfL funding for LIP schemes [P11]
s106 contributions: Contributions used to mitigate effects of new development on nearby infrastructure [P22]
Corridors and neighbourhoods: One of two formula funding categories, alongside supporting measures [P13]
Principal road renewal: Needs based funding for maintenance of the principal road network [P12] [P15]
Community Project Bank: Prioritised community proposals considered in developing the transport programme [P22]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Decisions of the Cabinet 1. That the content of the council’s proposed submission to Transport for London ( TfL ) identifying transport projects to be delivered with TfL Local implementation plan (Lip) funding in 2012/13 and the indicative programme of work for 2013/14 as contained in Appendices A and B of the report be agreed. 2. That the identified programme be submitted to Transport for London by 7 October 2011. 3. That implementation of the agreed programme as set out in Appendices A and B of the report be approved. 4. That if the cabinet member needs to consider variations to the proposed programme, that these are discussed with the relevant community council chair or in the case of cross community council border schemes, the chairs of these community councils. Decision of the Leader of the Council 5. That authority be delegated to the cabinet member for transport, environment and recycling to determine the most appropriate use of the £100,000 discretionary funding allocated by Transport for London for 2012/13.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 7 pages
Recommendations
Recommendations for the Cabinet
1. Agrees the content of the council’s proposed submission to Transport for London (TfL) identifying transport projects to be delivered with TfL Local implementation plan (Lip) funding in 2012/13 and the indicative programme of work for 2013/14 as contained in Appendices A and B.
2. Agrees that the identified programme be submitted to TfL by 7 October 2011.
3. Agrees to the implementation of the agreed programme as set out in Appendices A and B.
4. Requests the relevant cabinet member when considering variations to the proposed programme to consult with community council chairs regarding schemes in their area.
Recommendation for the Leader of the Council
5. Delegates authority to the Cabinet Member for Transport, Environment and Recycling to determine the most appropriate use of the £100K discretionary funding allocated by TfL for 2012/13.
1 BACKGROUND INFORMATION
6. Section 145 of the Greater London Authority Act 1999 (GLA 1999) requires each council in London to prepare a Local implementation plan (Lip) to detail how the authority will assist in delivering the Mayor’s Transport Strategy.
7. In May 2010, the Mayor of London published his revised transport strategy and all boroughs are required to revise their Local implementation plan in response to the new strategy. The council’s transport plan (incorporating the requirements of the local implementation plan) was adopted by the council in July 2011 and sets out how the council works with partners to coordinate and improve its transport infrastructure and services in the borough.
8. TfL provides financial assistance to boroughs, sub-regional partnerships and cross-borough initiatives under section 159 of the GLA Act 1999. All councils within London are able to obtain funding on an annual basis to deliver schemes identified in the Lip. This process is part of the Lip annual progress report (APR).
9. The borough is responsible for identifying a programme of transport improvements to reflect the integrated transport programme funding allocation. This programme is then submitted to TfL for confirmation based on compatibility with the Mayor’s policy framework.
10. The formula funding is allocated under two categories, corridors and neighbourhoods and supporting measures. The overall TfL Lip budget is £147.8 million of transport funding for London authorities in 2012/2013 down from £155m for 2010/11.
11. Southwark’s allocation for 2012/13 is £3.445m comprising of £2.875m for corridors and neighbourhoods and supporting measures, £471k of principal road renewal or bridge strengthening funding and £100k of discretionary funding to be spent as the council sees fit. This is the total funding that the borough should expect to receive for the integrated transport programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonAppendix A
Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonAppendix B
Report: Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonReport
11Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonThis decision
Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonThis decision
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.