Corporate Asset Management Strategy 2010 - Planning for a Smaller Sustainable Operational Estate

Approved Executive 3 papers

AI summarySouthwark Council approved AMP 2010 as its central property strategy, with an approximately 30% reduction in the estate's present size, excluding dwellings and schools. [D][P2][P3] The plan sets out an estimated £377 million in property sale receipts over the next 10 years. [P26]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCentral property strategy; approximately 30% estate reduction [P2][P3]
Money£377 million [P26]Estimated property sale receipts over the next 10 years [P26]
What happens nextDepartmental asset strategy work [P24][P31]Individual services will develop strategies, with wider consultation [P24][P31]
Who it affectsCouncil operational property estate [D][P3]Dwellings and schools are excluded from the reduction [D][P3]

What was decided

The refreshed Asset Management Plan, AMP 2010, in Appendix 1 was approved as a key strategic document alongside the council's other resource policies. It is the central strategy for managing council property holdings. Report P2

The objective of reducing the estate by approximately 30% of its present size, excluding dwellings and schools, was approved. The means of achieving it were noted. Report P3

Why

A detailed condition survey and review of occupation costs found a substantial resource gap compared with available accommodation budgets. Reducing the operational portfolio by approximately 30% by floor area was intended to help bridge it. Report P14

Since AMP 2008, asset use, the resource position and future service delivery choices had changed, although its general principles still held good. Central government funding cuts had increased pressure on limited local resources. Report P8, P38

Acting now would avoid lengthy reconfiguration delays and unmanageable statutory compliance risk. It would allow coherent planning for an affordable, sustainable estate. Report P18

What happens next

Detailed work with individual departments and services will develop asset strategies, identify efficiencies and support innovative service delivery. The process will incorporate wider consultation. Report P24, P31

The council will conclude the final phase of Modernise 1 office accommodation sales and increase use of the Tooley Street administration building. Modernise 2 will change how specialised activities operate and where they are located. Report P23

Proposed sales of council property and acquisitions of third party property interests will be handled separately at the relevant time, under appropriate statutory powers and Southwark's Constitution. Report P35

The money

  • £377 million Estimated receipts from sales of surplus and no longer required properties over the next 10 years. Report P26
  • £35 million Estimated disposal receipts this year to fund the council's priorities. Report P12
  • c.£12+ million per annum Income from shops, business premises and other property held for income generation. Report P12
  • approximately £3 Billion Estimated aggregate value of the council's property interests. Report P12

Options considered

  • Chosen: Approve AMP 2010 and pursue an approximately 30% estate reduction. The reduction was intended to bridge the resource gap and support an affordable portfolio, lower maintenance and better value for money. Report P3, P14, P17
  • Rejected: Take no immediate action. Reconfiguration lead times are lengthy, and waiting would create unmanageable statutory compliance risk without an affordable, sustainable estate. Report P18

Implications

  • Financial: Reducing the operational portfolio by approximately 30% by floor area, excluding schools and dwellings, is intended to help bridge the resource gap. Report P14
  • Financial: Modernise programmes will release up to 65,000 m2 of operational floor space, with more immediate running and maintenance savings. Report P27
  • Financial: Sales of surplus and no longer required properties are programmed to generate an estimated £377 million over the next 10 years. Report P26
  • Other: The office estate will need approximately 4,000 to 5,000 m2 of new accommodation, mainly in the centre of the borough. Report P27, P28
  • Legal: The estate change is intended to help meet specified statutory compliance requirements. Report P17
  • Legal: Future property sales and third party acquisitions will be dealt with separately under appropriate statutory powers and Southwark's Constitution. Report P35
  • Risk: Waiting for later action would expose the council to unmanageable statutory compliance risk and would not deliver an affordable, sustainable estate. Report P18
  • Staffing: Estate rationalisation is intended to support front line service delivery, new working practices, cross service working, co location, value for money and sustainability. Report P16, P17

Who and where

  • Operational property estate, excluding dwellings and schools Report P3, P14
  • Front line council services Report P16
  • Council staff and service teams Report P7, P17, P24
  • Office estate Report P22
  • Tooley Street administration building Report P23
  • Specialised council activities Report P23
  • Shops, business premises and other income generating property Report P12

Timeline

  • May 2008: The Corporate Property Management Arrangements background paper carried this date. Report P40
  • May 2009: The Voluntary and Community Sector Asset Management Strategy background paper carried this date. Report P40
  • this year: The disposal programme was estimated to generate £35 million in receipts. Report P12
  • Over the next 10 years: Property sales were programmed to generate an estimated £377 million. Report P26
  • 2 December 2010: The final report was dated. Report P43
  • 2008: The council adopted AMP 2008 and its policy framework for property stewardship. Report P5
  • 2026-05-28: Cabinet approved AMP 2010 and the estate reduction objective.

Plain English for the jargon

  • AMP: Asset Management Plan [P5]
  • AMP 2008: Earlier plan and policy framework for efficient stewardship of the authority's property assets [P5]
  • AMP 2010: Refreshed plan for managing property holdings and reducing the operational estate [P8][P41]
  • Corporate estate: Council operational and investment properties [P7]
  • Operational portfolio: Operational property portfolio subject to the reduction, excluding schools and dwellings [P8][P14]
  • Resource gap: Substantial difference between available accommodation budgets and property occupation costs [P14]
  • Modernise 1: Office Accommodation Project [P23]
  • Modernise 2: Programme changing how specialised council activities operate and where they are located [P23]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That the refreshed asset management plan (“AMP 2010”) contained in Appendix 1 of the report be approved as a key strategic document alongside the council’s other resource policies, and the central strategy for the management of the council’s property holdings. 2. That the objective of reducing the estate by approximately 30% of its present size (excluding dwellings and schools), and the means of achieving this be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 5 pages

Recommendations

That Cabinet

4. Approves the refreshed Asset Management Plan (“AMP 2010”) contained in Appendix 1 of this report as a key strategic document alongside the council’s other resource policies, and the central strategy for the management of the council’s property holdings;

5. Approves the objective of reducing the estate by approximately 30% of its present size (excluding dwellings and schools), and notes the means of achieving this.

BACKGROUND INFORMATION

6. In 2008 the council adopted a new Asset Management Plan (“AMP 2008”) and policy framework for the efficient stewardship of the authority’s property assets. AMP 2008 emphasised the strategic significance of a multi-billion pound property portfolio deployed in the fulfillment of the council’s corporate priorities.

1 7. The strategy drew together core activities underlying Southwark Council’s approach to property management:

 The role of the Asset Management Plan as a corporate planning document central to the management of the council’s operational and investment properties;  Implementation of comprehensive Facilities Management arrangements;  Asset-supported organisational change programmes, including Modernise  An extensive disposal programme;  Management arrangements for investment and Voluntary and Community Sector assets.

8. Although the general principles of the 2008 Asset Management Plan continue to hold good, much has changed in the intervening period in relation to the way assets are used now, the resource position, and the choices that need to be made about how assets will support service delivery in the future. Moving forward the new AMP 2010 proposes a 30% rationalisation across the operational property portfolio (excluding dwellings and schools) to ensure that what is retained is affordable. AMP 2010 sets the strategic framework for delivering the changes required.

KEY ISSUES FOR CONSIDERATION

The Corporate Property Portfolio

9. Southwark Council is a major inner-city property owner. Through this ownership it has a significant impact on domestic and working life across the borough. As the landlord of approximately 40,000 dwellings, 15,000 residential leaseholds and more than 5,000 other interests including commercial, industrial, and operational property the council owns in the region of 40% of all the freehold land situated within its boundaries.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Asset Management Strategy (spreadsheet)Appendix 1 1 pages Download
PDF
Corporate Asset Management StrategyAppendix 1 33 pages Download
PDF
Report: Corporate Asset Management StrategyReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, apologies
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open