Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sites
AgreedExecutive7 papers
AI summarySouthwark Cabinet agreed a response objecting to Thames Water's proposed shaft sites at King's Stairs Gardens and Alfred Salter Playground [D]. The Leader will make final amendments and sign it [D]; the council paper identified no specific financial implications [P78].
Written from the decision and the officer reportPDF Pro
OutcomeAgreedObjection to King's Stairs Gardens and Alfred Salter Playground [P3]
MoneyNo specific financial implications [P78]The Finance Director identified none for this council paper [P78]
What happens nextAmend and sign response [D]The Leader may make final amendments and then sign [P6]
Who it affectsTwo Southwark shaft sites [P3]Open space, nature, heritage, play and homes [P39] [P52] [P60]
What was decided
Cabinet agreed the council's consultation response, including the grounds for objecting to Thames Water's proposed use of King's Stairs Gardens and Alfred Salter Playground as shaft construction sites. Report P3
The Leader will make any final amendments to and sign the council's response to Thames Water. Report P6
Why
The site selection method did not clearly compare sites or explain the order of preference. Southwark wanted a systematic and transparent method that tests sites in sequence. Report P34
King's Stairs Gardens is metropolitan open land of regional importance. Losing much of it over approximately 7 years and leaving permanent structures would worsen open space and access to nature. The council also identified harm to heritage and enjoyment of the Thames and Southwark Park, so it strongly objects and wants alternative sites and routes. Report P17, P39, P43, P45, P50, P52, P54, P57
Losing Alfred Salter Playground would leave 79 homes on St John's Estate without adequate play facilities. A post medieval burial ground would require significant archaeological excavation and recording before construction. Southwark therefore strongly objects and asks for a review of sites along the sewage overflow alignment. Report P59, P60, P61, P62
What happens next
The Leader will make any final amendments and sign the council's response to Thames Water. Report P6
Southwark asked Thames Water to use a transparent site comparison, consider routes and sites that avoid King's Stairs Gardens, and review sites along the sewage overflow alignment. Southwark also planned to consult on a conservation area for King's Stairs Gardens and Edward III's Manor House. Report P34, P54, P57, P62
A second stage of consultation was planned for 2011, and planning applications were anticipated in mid 2012. Southwark would be invited to make formal observations and comment on environmental assessment scoping. The council's separate response to the draft National Planning Statement for Waste Water was to go to Cabinet for approval at its January meeting. Report P25, P26, P28
Rejected: King's Stairs Gardens as the tunnel reception shaft site. Southwark strongly objects because the scheme would harm protected open space, nature conservation, heritage and river amenity. It wants alternative sites and routes. Report P39, P43, P50, P52, P54, P57
Rejected: Alfred Salter Playground as a smaller shaft for the Shad Thames combined sewer overflow. Loss of play would leave 79 homes without adequate facilities, and the burial ground would require substantial archaeological excavation and recording. Report P59, P60, P61, P62
Chosen: Thames Water's preferred Abbey Mills Route. Thames Water said it was 9kms shorter and approximately £700m cheaper, minimised the number of shaft sites needed and met Environment Agency objectives, while capturing slightly less sewage. Report P14, P15, P20
Rejected: Thames Water's non preferred River Thames route Report P18
Rejected: Thames Water's non preferred Rotherhithe route Report P18
Chosen: Thames Tideway Tunnel as the strategic infrastructure solution. The 2005 study considered retrofitting drainage, separating sewers and using cleaning boats, but deemed the tunnel preferred. Thames Water said it was the only practicable strategy to fully meet the environmental objectives. Report P11, P12
Rejected: Thames Water's alternative reception sites for the tunnel. King Edward Memorial Park was rejected for open space and conservation impacts, Shadwell Basin for engineering reasons, and Chambers Wharf because planning permission and construction were assumed. Durand's Wharf and South Dock Marina were concluded not to be needed. Report P22
Rejected: Thames Water's alternative sites for the Shad Thames combined sewer overflow shaft. The foreshore was rejected for conservation, townscape and tourism effects. The garages would need a connecting culvert affecting traffic and lie close to homes. The pumping station was too small for construction while remaining open, and the railway viaduct could not be used because of the Jubilee line. Report P24
Implications
Financial: The Finance Director said there were no specific financial implications associated with the paper. Report P78
Other: Much of King's Stairs Gardens could be lost over approximately 7 years, with permanent structures left behind. This would worsen open space deficiency, remove the existing playground and reduce amenity for local people. Report P17, P39
Other: The gardens contain habitat combinations not commonly found elsewhere in Southwark and form an unbroken green chain. Their loss would worsen access to nature in Bankside and part of Bermondsey. Report P43, P45
Other: Permanent structures could harm the setting of listed and locally listed buildings, Edward III's Manor House and Southwark Park. The council considered a conservation area designation meritorious. Report P52, P53, P54
Other: Losing Alfred Salter Playground would leave 79 homes without adequate play facilities. Report P59, P60
Risk: Any planning application at King's Stairs Gardens would need an archaeological assessment, impact evaluation and mitigation. Alfred Salter Playground would require significant excavation and recording because of a post medieval burial ground. Report P56, P61
Legal: Future proposals would be subject to environmental impact assessment. Southwark would also expect an air quality assessment, satisfactory noise and odour mitigation and a transport assessment. Report P64, P65, P66
Other: The tunnel was expected to have significant social, economic and environmental effects. These include loss of open space and play, noise, dust and odour, which Thames Water would need to mitigate. Report P64, P72
Local people using King's Stairs Gardens Report P39
People using the Thames Path and river frontage Report P48
79 homes on St John's Estate Report P60
Residents of Bankside and part of Bermondsey Report P45
Local economy, jobs, education and community facilities Report P64
People affected by changes to nearby heritage settings Report P52
People affected by noise, dust and odour Report P72
Timeline
February 2005: Thames Water's strategic study considered several options and preferred a tunnel under the Thames. Report P11
2008: Southwark was consulted on the site selection methodology. Report P13
December 2009: Southwark was consulted on possible shaft sites and ranked King's Stairs Gardens as its least preferred option. Report P13
September 2010: Public consultation on the preferred route and sites commenced. Report P14
3 December 2010: The final report was dated. Report P83
2011: A second consultation was planned for detailed proposals, mitigation, permanent structures and compensation. Report P25
mid 2012: Planning applications were anticipated, with Southwark invited to provide observations. Report P26
2013: Tunnel construction start, with completion in 2020. Report P27
Plain English for the jargon
Thames Tideway Tunnel: A proposed large sewerage tunnel along the River Thames to help clean the river. [P9]
Combined sewer overflow (CSO): An overflow of untreated sewage through London's combined drainage system. [P9]
Metropolitan open land (MOL): Greenfield open space of regional importance with the highest policy protection. [P39]
Reception shaft: A shaft where tunnel boring machines would be extracted and smaller tunnels driven toward overflow sites. [P15]
Thames Policy Area (TPA): A designation recognising the Thames's role in maintaining an exemplary, sustainable world city. [P47]
Environmental impact assessment (EIA): An assessment of the environmental impacts of a particular development. [P68]
Infrastructure Planning Commission (IPC): The body then expected to determine tunnel planning applications until a replacement process or organisation was put in place. [P26]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Decision of the Cabinet 1. That the response to the consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sites (appendix 1 of the report), in particular the council’s grounds for objection to the proposed use of King’s Stairs gardens and Alfred Salter Playground as shaft construction sites for the Thames Tideway tunnel, as set out in this report and appendix 1 be agreed. Decision of the Leader of the Council 2. That the leader make any final amendments to and sign the council’s response to Thames Water (appendix 1 of the report).
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 11 pages
Recommendations
Recommendation for the Cabinet
That cabinet
5. Agrees the response to the consultation by Thames Water on the proposed the Thames Tideway Tunnel routes and sites (appendix 1), in particular the council’s grounds for objection to the proposed use of King’s Stairs gardens and Alfred Salter Playground as shaft construction sites for the Thames Tideway tunnel, as set out in this report and appendix 1.
Recommendation for the Leader of the Council
That the Leader
1 6. Makes any final amendments to and signs the council’s response to Thames Water (appendix 1).
BACKGROUND INFORMATION
7. Thames Water is consulting in relation to its preferred route for the proposed Thames Tideway Tunnel and selection of sites. This report sets out the relevant background to the proposals and relevant considerations for members in agreeing the council’s consultation response.
8. The Thames Tideway Tunnel is a proposal by Thames Water to construct a large sewerage tunnel along the route of the River Thames to help clean up the river. Thames Water state that in an average year, 39 million cubic metres of untreated sewage overflows into the Thames through London’s combined sewer overflows (CSOs). Thames Water needs to address this issue to comply with the EU Urban Waste Water Directive.
Thames Tideway Strategic Study 2005
9. According to the Thames Water Tideway Strategic Study of February 2005 (2005 Study), Thames Water considered several options for achieving the objectives of the project, including retrofitting sustainable urban drainage systems (SUDs) across all of London’s streets, converting the existing combined drainage system into a separated sewage system, making greater use of bubbler and skimmer boats to clean the river and intercepting overflows from the CSOs and diverting them into a main tunnel under the Thames. The proposed Thames Tunnel was deemed to be the preferred infrastructure solution to the environmental problems posed by the CSOs. The preferred route for the tunnel would run from the Acton Storm tanks in west London to the Beckton Sewage Treatment plant in East London, intercepting the majority of the 34 CSOs on its route which have the worst environmental impact. Whilst it is noted that the 2005 Study included a regulatory impact assessment, it is not clear whether the identified options were subjected to any sustainability or environmental appraisal before selecting the Thames Tideway Tunnel or preferred route.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.