Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sites

Agreed Executive 7 papers

AI summarySouthwark Cabinet agreed a response objecting to Thames Water's proposed shaft sites at King's Stairs Gardens and Alfred Salter Playground [D]. The Leader will make final amendments and sign it [D]; the council paper identified no specific financial implications [P78].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedObjection to King's Stairs Gardens and Alfred Salter Playground [P3]
MoneyNo specific financial implications [P78]The Finance Director identified none for this council paper [P78]
What happens nextAmend and sign response [D]The Leader may make final amendments and then sign [P6]
Who it affectsTwo Southwark shaft sites [P3]Open space, nature, heritage, play and homes [P39] [P52] [P60]

What was decided

Cabinet agreed the council's consultation response, including the grounds for objecting to Thames Water's proposed use of King's Stairs Gardens and Alfred Salter Playground as shaft construction sites. Report P3

The Leader will make any final amendments to and sign the council's response to Thames Water. Report P6

Why

The site selection method did not clearly compare sites or explain the order of preference. Southwark wanted a systematic and transparent method that tests sites in sequence. Report P34

King's Stairs Gardens is metropolitan open land of regional importance. Losing much of it over approximately 7 years and leaving permanent structures would worsen open space and access to nature. The council also identified harm to heritage and enjoyment of the Thames and Southwark Park, so it strongly objects and wants alternative sites and routes. Report P17, P39, P43, P45, P50, P52, P54, P57

Losing Alfred Salter Playground would leave 79 homes on St John's Estate without adequate play facilities. A post medieval burial ground would require significant archaeological excavation and recording before construction. Southwark therefore strongly objects and asks for a review of sites along the sewage overflow alignment. Report P59, P60, P61, P62

What happens next

The Leader will make any final amendments and sign the council's response to Thames Water. Report P6

Southwark asked Thames Water to use a transparent site comparison, consider routes and sites that avoid King's Stairs Gardens, and review sites along the sewage overflow alignment. Southwark also planned to consult on a conservation area for King's Stairs Gardens and Edward III's Manor House. Report P34, P54, P57, P62

A second stage of consultation was planned for 2011, and planning applications were anticipated in mid 2012. Southwark would be invited to make formal observations and comment on environmental assessment scoping. The council's separate response to the draft National Planning Statement for Waste Water was to go to Cabinet for approval at its January meeting. Report P25, P26, P28

The money

  • £700m Approximate saving claimed for Thames Water's preferred route Report P20

Options considered

  • Rejected: King's Stairs Gardens as the tunnel reception shaft site. Southwark strongly objects because the scheme would harm protected open space, nature conservation, heritage and river amenity. It wants alternative sites and routes. Report P39, P43, P50, P52, P54, P57
  • Rejected: Alfred Salter Playground as a smaller shaft for the Shad Thames combined sewer overflow. Loss of play would leave 79 homes without adequate facilities, and the burial ground would require substantial archaeological excavation and recording. Report P59, P60, P61, P62
  • Chosen: Thames Water's preferred Abbey Mills Route. Thames Water said it was 9kms shorter and approximately £700m cheaper, minimised the number of shaft sites needed and met Environment Agency objectives, while capturing slightly less sewage. Report P14, P15, P20
  • Rejected: Thames Water's non preferred River Thames route Report P18
  • Rejected: Thames Water's non preferred Rotherhithe route Report P18
  • Chosen: Thames Tideway Tunnel as the strategic infrastructure solution. The 2005 study considered retrofitting drainage, separating sewers and using cleaning boats, but deemed the tunnel preferred. Thames Water said it was the only practicable strategy to fully meet the environmental objectives. Report P11, P12
  • Rejected: Thames Water's alternative reception sites for the tunnel. King Edward Memorial Park was rejected for open space and conservation impacts, Shadwell Basin for engineering reasons, and Chambers Wharf because planning permission and construction were assumed. Durand's Wharf and South Dock Marina were concluded not to be needed. Report P22
  • Rejected: Thames Water's alternative sites for the Shad Thames combined sewer overflow shaft. The foreshore was rejected for conservation, townscape and tourism effects. The garages would need a connecting culvert affecting traffic and lie close to homes. The pumping station was too small for construction while remaining open, and the railway viaduct could not be used because of the Jubilee line. Report P24

Implications

  • Financial: The Finance Director said there were no specific financial implications associated with the paper. Report P78
  • Other: Much of King's Stairs Gardens could be lost over approximately 7 years, with permanent structures left behind. This would worsen open space deficiency, remove the existing playground and reduce amenity for local people. Report P17, P39
  • Other: The gardens contain habitat combinations not commonly found elsewhere in Southwark and form an unbroken green chain. Their loss would worsen access to nature in Bankside and part of Bermondsey. Report P43, P45
  • Other: Permanent structures could harm the setting of listed and locally listed buildings, Edward III's Manor House and Southwark Park. The council considered a conservation area designation meritorious. Report P52, P53, P54
  • Other: Losing Alfred Salter Playground would leave 79 homes without adequate play facilities. Report P59, P60
  • Risk: Any planning application at King's Stairs Gardens would need an archaeological assessment, impact evaluation and mitigation. Alfred Salter Playground would require significant excavation and recording because of a post medieval burial ground. Report P56, P61
  • Legal: Future proposals would be subject to environmental impact assessment. Southwark would also expect an air quality assessment, satisfactory noise and odour mitigation and a transport assessment. Report P64, P65, P66
  • Other: The tunnel was expected to have significant social, economic and environmental effects. These include loss of open space and play, noise, dust and odour, which Thames Water would need to mitigate. Report P64, P72

Who and where

  • The River Thames Report P9
  • Local people using King's Stairs Gardens Report P39
  • People using the Thames Path and river frontage Report P48
  • 79 homes on St John's Estate Report P60
  • Residents of Bankside and part of Bermondsey Report P45
  • Local economy, jobs, education and community facilities Report P64
  • People affected by changes to nearby heritage settings Report P52
  • People affected by noise, dust and odour Report P72

Timeline

  • February 2005: Thames Water's strategic study considered several options and preferred a tunnel under the Thames. Report P11
  • 2008: Southwark was consulted on the site selection methodology. Report P13
  • December 2009: Southwark was consulted on possible shaft sites and ranked King's Stairs Gardens as its least preferred option. Report P13
  • September 2010: Public consultation on the preferred route and sites commenced. Report P14
  • 3 December 2010: The final report was dated. Report P83
  • 2011: A second consultation was planned for detailed proposals, mitigation, permanent structures and compensation. Report P25
  • mid 2012: Planning applications were anticipated, with Southwark invited to provide observations. Report P26
  • 2013: Tunnel construction start, with completion in 2020. Report P27

Plain English for the jargon

  • Thames Tideway Tunnel: A proposed large sewerage tunnel along the River Thames to help clean the river. [P9]
  • Combined sewer overflow (CSO): An overflow of untreated sewage through London's combined drainage system. [P9]
  • Metropolitan open land (MOL): Greenfield open space of regional importance with the highest policy protection. [P39]
  • Reception shaft: A shaft where tunnel boring machines would be extracted and smaller tunnels driven toward overflow sites. [P15]
  • Thames Policy Area (TPA): A designation recognising the Thames's role in maintaining an exemplary, sustainable world city. [P47]
  • Environmental impact assessment (EIA): An assessment of the environmental impacts of a particular development. [P68]
  • Infrastructure Planning Commission (IPC): The body then expected to determine tunnel planning applications until a replacement process or organisation was put in place. [P26]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Decision of the Cabinet 1. That the response to the consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sites (appendix 1 of the report), in particular the council’s grounds for objection to the proposed use of King’s Stairs gardens and Alfred Salter Playground as shaft construction sites for the Thames Tideway tunnel, as set out in this report and appendix 1 be agreed. Decision of the Leader of the Council 2. That the leader make any final amendments to and sign the council’s response to Thames Water (appendix 1 of the report).
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 11 pages

Recommendations

Recommendation for the Cabinet

That cabinet

5. Agrees the response to the consultation by Thames Water on the proposed the Thames Tideway Tunnel routes and sites (appendix 1), in particular the council’s grounds for objection to the proposed use of King’s Stairs gardens and Alfred Salter Playground as shaft construction sites for the Thames Tideway tunnel, as set out in this report and appendix 1.

Recommendation for the Leader of the Council

That the Leader

1 6. Makes any final amendments to and signs the council’s response to Thames Water (appendix 1).

BACKGROUND INFORMATION

7. Thames Water is consulting in relation to its preferred route for the proposed Thames Tideway Tunnel and selection of sites. This report sets out the relevant background to the proposals and relevant considerations for members in agreeing the council’s consultation response.

8. The Thames Tideway Tunnel is a proposal by Thames Water to construct a large sewerage tunnel along the route of the River Thames to help clean up the river. Thames Water state that in an average year, 39 million cubic metres of untreated sewage overflows into the Thames through London’s combined sewer overflows (CSOs). Thames Water needs to address this issue to comply with the EU Urban Waste Water Directive.

Thames Tideway Strategic Study 2005

9. According to the Thames Water Tideway Strategic Study of February 2005 (2005 Study), Thames Water considered several options for achieving the objectives of the project, including retrofitting sustainable urban drainage systems (SUDs) across all of London’s streets, converting the existing combined drainage system into a separated sewage system, making greater use of bubbler and skimmer boats to clean the river and intercepting overflows from the CSOs and diverting them into a main tunnel under the Thames. The proposed Thames Tunnel was deemed to be the preferred infrastructure solution to the environmental problems posed by the CSOs. The preferred route for the tunnel would run from the Acton Storm tanks in west London to the Beckton Sewage Treatment plant in East London, intercepting the majority of the 34 CSOs on its route which have the worst environmental impact. Whilst it is noted that the 2005 Study included a regulatory impact assessment, it is not clear whether the identified options were subjected to any sustainability or environmental appraisal before selecting the Thames Tideway Tunnel or preferred route.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesAppendix 1 7 pages Download
PDF
Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesAppendix 2 1 pages Download
PDF
Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesAppendix 3 1 pages Download
PDF
Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesAppendix 4 1 pages Download
PDF
Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesAppendix 5 1 pages Download
PDF
Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesAppendix 6 8 pages Download
PDF
Report: Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, apologies
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present

On this subject at Southwark

Search all
  1. Response to consultation by Thames Water on the proposed Thames Tideway Tunnel routes and sitesThis decision
  2. Thames Tunnel - Response to Phase Two Public ConsultationAgreed
  3. Consultation Responses (Key Themes) on a Draft Vision for Southwark Day Opportunities for Adults with Learning DisabilitiesNoted
  4. Approval of the Council's Response to the Transport for London (TfL) Bakerloo Line Extension ConsultationAgreed
  5. The Outcome of the Consultation Exercise on Changes to Day Centre Provision at Queens Road and Riverside and the Development of a Disability Hub: Response to Decisions from Call-inNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open