Southwark 2012 Capital Legacy Group: Recommendations for a £2m package of Capital Investment
NotedExecutive2 papers
AI summaryCabinet noted that the finance cabinet member had agreed £2m for ten capital projects to improve sport facilities, access and participation across Southwark.
Written from the decision and the officer reportPDF Pro
OutcomeNoted£2m supports sport, activity and facility improvements.
Money£2mAgreed capital allocation for ten projects.
What happens nextImplementation and monitoringExisting resources will support delivery and oversight.
Who it affectsResidents and sport facilitiesProjects seek wider access and participation in sport.
What was decided
The cabinet member for finance, resources and community safety agreed £2m of capital legacy funding for ten projects. Report P1
Ten of the fourteen stage two proposals were recommended for full or part funding, while four were unsuccessful. Report P8
Funding will be distributed as grants, with grant conditions allowing funds to be recovered if project specifications or targets are not met. Report P35, P36
Why
The fund was intended to create a lasting Olympic and Paralympic legacy by improving access to physical activity and encouraging participation in Southwark communities. Report P5
The assessment considered feasibility and risk, moving from forty first stage submissions to fourteen detailed stage two applications with a combined value of £3.61m. Report P6, P7
The ten recommended projects were spread across the borough, offered a wider range of sports, and were said to have no adverse impact on any Southwark community. Report P28, P29, P30
What happens next
Environment and Leisure staff will implement the projects using existing departmental resources. Report P33
Officers will manage tailored payment schedules so changes to the required budget profile do not cause adverse cash flow effects. Report P42
A commissioning officer will monitor performance, with grant agreements and tailored conditions used to protect value for money. Report P36, P41
The money
£2m Budget agreed within the current capital programme. Report P39, P40
£2,000,600 Combined value of the ten successful applications. Report P32
£600 Amount by which successful applications exceeded the fund. Report P32
£400K Part funding for the Herne Hill Velodrome track. Report P15
£370K Award for the Southwark Park Sports complex redevelopment. Report P20
£200k Part funding for Peckham Rye pitches and changing rooms. Report P19
£100K Match funding secured for the Homestall Road sports ground. Report P16
£25K Match funding secured for the Bethwin Road playground. Report P12
Options considered
Chosen: Full awards for six projects, including playgrounds, sports grounds, a disability court, a pool hoist and an outdoor sports area. The proposals were considered likely to improve access, participation or the sporting legacy. Report P11, P12, P13, P16, P17, P18, P21
Chosen: Part awards for four refurbishment, capacity and athletics projects. The capital legacy fund would meet defined parts of the proposed work. Report P11, P14, P15, P19, P20
Rejected: London Southbank University’s new entrance to its sports centre. It improved access to an existing facility but did not directly increase the sporting legacy through new or refurbished sporting facilities. Report P23
Rejected: The Peckham Settlement’s Southwark run training facility. No match funding was sought, and no clear link was identified between the event and the proposed facility. Report P24
Rejected: Sustrans’ Connect2 and South Bermondsey Link projects. Their benefits and value for money were difficult to measure, and other projects with similar values focused more directly on sport. Report P25
Rejected: Tideways Sailability’s ability centre and pontoon access project. The proposal was considered high risk, difficult to deliver, technically weak and affected by many hurdles. Report P26
Chosen: Grant funding for projects led by external organisations. Grant conditions can be tailored to each successful project and used to manage project risks. Report P35
Chosen: Performance monitoring and clawback conditions. These measures are intended to ensure value for money and recover funds where project specifications and targets are not met. Report P36, P41
Implications
Financial: The successful applications totalled £2,000,600, which was £600 above the allocated fund. Report P32
Staffing: Existing Environment and Leisure resources will cover implementation and monitoring work. Report P33, P34
Legal: External projects will use grant agreements and tailored conditions, including provisions for recovering funds. Report P35, P36, P41
Equalities: Projects include measures intended to improve access for disabled people, people with special needs and other local groups. Report P17, P18, P29
Risk: Payment schedules and performance monitoring will be used to manage financial, delivery and grant compliance risks. Report P36, P42
Other: The report said approval would not cause adverse impacts on any community in Southwark. Report P30
Disabled people and people with special needs Report P17
Disability groups using the swimming pool Report P18
Children and families using cycle tracks Report P15
Children and young people using outdoor sports facilities Report P21
People taking part in sport and physical activity Report P29
External organisations leading funded projects Report P35
Timeline
November 2010: The capital legacy group was formed. Report P4
October 2011: The finance cabinet member took the individual decision maker decision on the fund. Report P1
6 October 2011: The final officer report was dated. Report P48
June 2012: The Bethwin Road playground project aimed to complete upgrade works. Report P12
September 2012: Construction works at the Herne Hill Velodrome were not proposed to begin until this date. Report P15
Plain English for the jargon
IDM: Individual Decision Maker decision.
Capital legacy group: Group established to allocate capital funding for a lasting sporting legacy.
Grant conditions: Requirements attached to grant funding, including recovery provisions.
Commissioning officer: Council officer responsible for monitoring funded projects.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That it be noted that the cabinet member for finance, resources and community safety has taken an October 2011 individual decision maker (IDM) report in respect of the Southwark 2012 Capital Legacy Fund, which agrees £2m funding to ten capital projects.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 6 pages
Recommendation
1. That the Cabinet notes that the Cabinet Member for Finance, Resources and Community Safety will take an October 2011 Individual Decision Maker (IDM) report in respect of the Southwark 2012 Capital Legacy Fund, which agrees £2m funding to ten capital projects.
BACKGROUND INFORMATION
2. ‘Southwark 2012’ is the name given to the project for delivering the Council’s objectives in preparing for the upcoming London 2012 Olympic and Paralympic Games. Several distinct work streams exist in the Southwark 2012 project structure, one of which is the capital legacy group.
3. The capital legacy group was formed in November 2010 and is chaired by the Leader of the Council. The group is composed of external delegates from the local business community, London Southbank University and Sport England, the MP for Dulwich and West Norwood, Southwark Council cabinet members and senior Council officers.
4. The objective of the capital legacy group is to invest £2m in capital projects that support a lasting Olympic and Paralympic legacy in Southwark from the 2012 games, improving access to and increasing participation in physical activity and encouraging the development of the Olympic values in the borough’s communities.
5. The capital legacy funding process was split over two stages. The first stage invited project proposals from Southwark residents and organisations based on the criteria agreed by the capital legacy group. The second stage centered on gaining more detailed information from applicants in order to make assessments for feasibility and risk.
6. From forty original and unique submissions at stage one, fourteen stage two applications with a combined value of £3.61m were considered by the capital legacy group for stage two.
7. The capital legacy group has recommended that ten of the fourteen stage two project proposals be funded either in full or in part. Four projects have been unsuccessful in their application for capital legacy funding.
KEY ISSUES FOR CONSIDERATION
8. The IDM recommendations are summarised in the table as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.