Thames Tunnel - Response to Phase Two Public Consultation
AgreedExecutive5 papers
AI summarySouthwark Cabinet agreed the council's response to Thames Water's Phase Two consultation on the proposed Thames Tideway Tunnel, objecting to use of Chambers Wharf, King's Stairs Gardens and Druid Street, with the Leader to make final amendments and sign.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedObjections to Chambers Wharf, King's Stairs Gardens, Druid Street
MoneyNo immediate financial implicationsWork to be done within existing budgeted resources
What happens nextLeader to sign final responseLeader authorised to make any final amendments before signing
Who it affectsThames Water and nearby residentsSites in Southwark and one adjoining Lewisham
What was decided
Cabinet agreed the response to Thames Water's Phase Two public consultation on the preferred route and sites for the Thames Tideway Tunnel, as set out in Appendix A. Report P1
Cabinet noted that the Leader will make any final amendments to and sign the council's response, including an amendment to the wording under point 3, Shad Thames Pumping Station. Report P2
Officers recommend the council objects to the use of Chambers Wharf as a main tunnel drive shaft for the reasons summarised in the report and set out in Appendix A. Report P39
Why
The independent Thames Tunnel Commission, sponsored by five London boroughs including Southwark, recommended reconsidering the full-length tunnel until environmental and economic reassessment of alternatives had been carried out. Report P17, P20, P21
Officers raised concerns about escalating costs and the impact on Thames Water customers, and about the lack of iterative sustainability testing of options. Report P25, P83, P120
The proposed use of Chambers Wharf was considered likely to cause harm to residential amenity, heritage assets, the Thames Policy Area, a nearby primary school, and the local road network. Report P40, P41, P52, P55, P65
What happens next
The Leader is to make any final amendments and sign the council's consultation response for submission to Thames Water. Report P2
Thames Water will take account of consultation responses in preparing the Development Consent Order application, with DCO consultation due in mid 2012 and submission to the Major Infrastructure Planning Unit in late 2012. Report P11, P12
If approved by the Secretary of State, construction of the tunnel would start in 2016 and the project is due to be completed by 2022/23. Report P11
Options considered
Rejected: Chambers Wharf as main tunnel drive shaft (Thames Water's preferred site). Harm to residential amenity, heritage, Thames Policy Area, nearby school and traffic impacts Report P28, P39, P52, P55, P65
Rejected: King's Stairs Gardens as alternative shaft site. Loss of open space and harm to nature conservation and heritage Report P85, P86, P87
Rejected: Druid Street as alternative CSO construction site. Loss of children's play facility and residential amenity on St John's Estate Report P88, P89, P90
Chosen with concerns: Shad Thames Pumping Station for storm flow management works. Generally supported in principle but concerns about amenity, heritage, archaeology and transport Report P68, P69, P75, P77, P79, P82
Chosen with concerns: Earl Pumping Station (in Lewisham, adjoining Southwark). Objection raised over noise, vibration and pedestrian or cyclist safety for Southwark residents at Chilton Grove Report P91, P92, P93, P95
Implications
Legal: Development Consent Order process expected mid to late 2012, with public hearings in 2013 and final decision by the Secretary of State under the National Policy Statement on Waste Water. Report P11
Financial: No immediate financial implications, but long term financial implications of the scheme cannot yet be quantified and will be reported separately. Report P124, P125, P127
Equalities: Community impacts on residential amenity, local schools, and the transport network are identified; Thames Water will need to demonstrate mitigation. Report P122
Climate: Potential groundwater and surface water flood risk from shaft and tunnel construction, including from climate change, requires assessment in the Environmental Statement. Report P104, P105, P106, P107
Risk: At Shad Thames Pumping Station, inhibiting pump flows and using upstream storage could increase flood risk in the event of pump failure; residual risk must be identified and mitigated. Report P108
Other: Adequate planning obligations (S106) should be sought to mitigate heritage, open space, community, transport, sustainability, employment and public realm impacts if consent is granted. Report P110, P111
Staffing: Further work on the response will be carried out by Planning Policy team staff within existing resources, without a call on additional funding. Report P126
Who and where
Residents near the Chambers Wharf site, including at Luna House and Axis Court and on nearby streets Report P28, P41
Riverside Primary School and St Michael's Roman Catholic Secondary School, close to Chambers Wharf Report P28, P42
Thames Water bill payers, who could be pushed into water poverty by escalating scheme costs Report P25
Residents of the 79 homes on the St John's Estate, who could lose access to playground if Druid Street is used Report P90
Residents of Chilton Grove adjoining Earl Pumping Station, exposed to noise and vibration impacts Report P92, P93
Owners of heritage assets near Chambers Wharf and Shad Thames Pumping Station, including grade II listed buildings Report P55, P56, P79
Timeline
4 November 2011 to 10 February 2012: Thames Water Phase Two public consultation period Report P12
mid 2012: Consultation on the Development Consent Order application Report P11
late 2012: Development Consent Order application to be submitted to the Major Infrastructure Planning Unit Report P11
2013: Public hearings on the Development Consent Order application Report P11
2016: Construction of the tunnel due to start, if approved Report P11
2022/23: Project due to be completed; part of Chambers Wharf not available for development until this date Report P11, P52
Plain English for the jargon
Combined Sewer Overflow (CSO): A point where combined stormwater and sewage can overflow into the river to prevent flooding of the sewer network.
Development Consent Order (DCO): The planning consent required for nationally significant infrastructure projects, decided by the Secretary of State.
National Policy Statement (NPS) on Waste Water: Government policy statement on wastewater infrastructure, designated under section 5(2) of the 2008 Act.
Thames Policy Area (TPA): An area along the Thames in London where development is expected to protect and enhance the river's character and support sustainable growth.
Major Infrastructure Planning Unit (MIPU): The part of the Planning Inspectorate that handles applications for nationally significant infrastructure projects.
EFRA Committee: The House of Commons Environment, Food and Rural Affairs Select Committee.
PIER / PEIR: Preliminary Environmental Information Report, published by Thames Water to inform consultation on the Thames Tunnel.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the response to the consultation by Thames Water on the proposed preferred route and sites for the Thames Tideway Tunnel be agreed (Appendix A of the report). 2. That it be noted that the Leader will make any final amendments to and sign the council’s response to Thames Water (Appendix A of the report), including an amendment to the wording under point 3, Shad Thames Pumping Station. Councillor Catherine McDonald returned to the meeting at 5.53pm at the conclusion of this item.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 15 pages
Recommendations
1. That cabinet agrees the response to the consultation by Thames Water on the proposed preferred route and sites for the Thames Tideway Tunnel (Appendix A).
2. That the cabinet notes that the Leader will make any final amendments to and sign the council’s response to Thames Water (Appendix A).
BACKGROUND INFORMATION
3. Thames Water is consulting on its second stage of public consultation in relation to the proposed Thames Tideway Tunnel preferred route and selection of sites. This report sets out the relevant background to the proposals and relevant considerations for members in agreeing the council’s consultation response.
4. The Thames Tideway Tunnel is a proposal by Thames Water to construct a large sewerage tunnel along the route of the River Thames to help clean up the river. Thames Water states that in an average year, 39 million cubic metres of untreated sewage overflows into the Thames through London’s combined sewer overflows (CSOs). Thames Water needs to address this issue to comply with the EU Urban Waste Water Directive.
1 5. Thames Water previously consulted on the first stage of public consultation in September 2010, this consultation set out the preferred tunnel route and sites. The preferred tunnel route at the time included a main reception site at King’s Stairs Gardens and a smaller Combined Sewer Overflow (CSO) site at Alfred Salter Playground on the St John’s Estate. Southwark council responded to the consultation objecting to the use of these two sites.
6. Following a review of the tunnelling strategy, Thames Water is now re-consulting on their preferred route and providing further details about proposals for individual sites. The preferred route remains the “Abbey Mills” route (see Appendix B), which is largely the same route as the one identified in the Phase One public consultation.
7. However, following a reassessment of available sites, Chambers Wharf has been identified as the preferred site for a main tunnel shaft. King’s Stairs Gardens remains a possible site, but is not preferred. It is envisaged that Thames Water will drive towards Chambers Wharf from Battersea and drive from Chambers Wharf to Abbey Mills. Material which is extracted from the tunnel between Chambers Wharf and Abbey Mills will be extracted from the Chambers Wharf shaft. This is change to the tunnelling strategy. At the first stage of consultation it was envisaged that tunnels would be driven from east and west towards King Stairs Gardens. However, Thames Water report that due to difficulties associated with moving the excavated material off-site by river at Abbey Mills, it has been concluded that it is preferable to use this site to receive the main tunnel, rather than as a drive site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.