CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Progress report on Abbeyfield Estate Regeneration scheme and update on delivery of Four Squares and Hawkstone Estate

Noted Executive 1 paper

AI summarySouthwark Cabinet noted Abbeyfield regeneration progress, including possession, returns, procurement and refurbishment. It also noted compulsory purchase order steps and Four Squares and Hawkstone updates. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPossession, returns, procurement and refurbishment recorded [D]
MoneyNo new financial implications identified [P55]
What happens nextCompulsory purchase and procurement continue [D]Notices, adviser appointment and scheme milestones continue [D] [P25] [P31]
Who it affectsNot stated

What was decided

For Abbeyfield, Cabinet noted Maydew possession progress, the return interest result, procurement milestones, the voids for sale programme and refurbishment work at Maydew House, Damory House and Thaxted Court. Report P2, P3, P4, P5, P6

Cabinet noted the issue of Ground 10 notices and active work towards securing a compulsory purchase order. Report P7, P8

Cabinet noted the Four Squares and Hawkstone estate progress update. Report P10

Why

The council needed legal possession steps for occupied homes to meet the March 2014 vacant possession timetable. Secure tenants would receive Notices of Seeking Possession. Report P25

Negotiation with the holders of the remaining two leasehold interests had not produced agreements. A compulsory purchase order had been approved on 25 September 2012, and advice on its powers was being sought. Report P26, P27

Refurbishment, environmental works and mixed tenure homes were expected to enable regeneration at Abbeyfield. The council said this work followed its rehousing, contract and procurement policies. Report P46

What happens next

Serve remaining secure tenants with Notices of Seeking Possession during February 2013. Continue leasehold negotiations, clarify which compulsory purchase powers apply, and then follow the steps through to making and confirming the order. Report P25, P26, P27

Put design and technical advisers in place by July 2013, then appoint the contractor in summer 2014 after an EU tender. Develop void criteria and specifications by 2013/14, and a marketing strategy by 2014/15. Report P31, P32

Develop clear concierge specifications and consult low rise residents and Maydew returners in February/March. Future Four Squares and Hawkstone updates will go through routine Major Works programmes reports. Report P35, P36, P14

Options considered

  • Chosen: Return to Maydew House after refurbishment. 24 tenants wished to return, while nine did not. Returning residents could choose an available flat, but their original flat was not guaranteed. Report P13, P22
  • Rejected: Return to the original flat. 18 tenants wanted this, but it was not offered as a right. Home loss can only be paid to a tenant who does not return to their original flat. Report P23, P24
  • Chosen: Use Ground 10 possession proceedings. The legal process may be necessary to achieve vacant possession by March 2014. Report P25
  • Chosen: Seek a compulsory purchase order. Negotiations over the remaining two leasehold interests had not reached agreement. Cabinet had approved a compulsory purchase order application on 25 September 2012. Report P26, P27
  • Chosen: Use another EU tender for the design and build contract. Another tender was required after the design and technical advisers completed their work. Report P31
  • Chosen: Refurbish selected voids for sale. Criteria and a refurbishment specification would be developed with the Resident Project Group before construction procurement. Report P32
  • Chosen: Incorporate a concierge type service in the refurbishment scheme. A concierge type service was assumed to be necessary because it was an essential factor in valuing and marketing the voids for sale. Report P35
  • Chosen: Report future estate updates through Major Works programmes. Future Four Squares and Hawkstone updates were to be included in routine Major Works programmes reports to Cabinet. Report P14

Implications

  • Financial: There were no new financial implications in this report, but progress needed close monitoring to keep costs within available resources. Report P55
  • Legal: The scheme uses Ground 10 possession proceedings, compulsory purchase powers and statutory section 20 consultation. Section 20 requires two stages, each with a 30 day observation period. Report P25, P27, P57
  • Equalities: Maydew tenants with a 1 and 2 bed need were offered the chance to return regardless of age, disability, faith or religion, gender, race and ethnicity, or sexual orientation. Report P48
  • Financial: Much of the work was service chargeable. Leaseholders paid the actual concierge cost through annual service charges, and changes and costs needed to be recorded clearly. Report P57, P59
  • Risk: Maydew garages were not in a lettable condition and were vulnerable to vandalism, fly tipping and other security hazards. This created income loss, clearance costs and health and safety risks. Report P60
  • Risk: The complexity of asbestos removal extended the Hawkstone low rise contract period, with completion estimated by October 2014. Report P44
  • Climate: The earlier Cabinet decision had noted the implications of Southwark Heat Network proposals for the estate. Report P13
  • Other: The Resident Project Group would oversee works and join contractor and consultant procurement where applicable. The Bede Centre would be consulted through the group. Report P29, P50

Who and where

  • Maydew House secure tenants and leaseholders Report P18, P26
  • Current and previous Maydew House tenants Report P20
  • Damory House and Thaxted Court tenants and leaseholders Report P29
  • Abbeyfield Estate leaseholders Report P57
  • Bradley House leaseholders Report P34
  • Residents of Abbeyfield low rise blocks and Maydew returners Report P36, P49
  • Four Squares council tenants, Marden and Layard Squares leaseholders, and John Kennedy House leaseholders Report P38, P62
  • Bede Centre Report P50

Timeline

  • September 2010: Rehousing of Maydew secure tenants began and continued. Report P18
  • 25 September 2012: Cabinet approved an application for a compulsory purchase order. Report P26
  • 9 October 2012: Gateway 1 approval was given for the design and technical advisers. Report P31
  • 7 January 2013: Refurbishment works began at Four Squares and John Kennedy House. Report P38, P43
  • 24 January 2013: The first Resident Project Group meeting took place. Report P29
  • February 2013: Possession notices were planned, and planning approval was to be sought for Four Squares and the Hawkstone low rise works. Report P25, P39, P44
  • 3 February 2014: Four Squares internal refurbishment works were programmed to complete. Report P38
  • March 2014: The target for achieving vacant possession of Maydew House was March 2014. Report P25

Plain English for the jargon

  • CPO: A compulsory purchase order, used after negotiations over the two remaining leasehold interests did not reach agreement. [P26] [P27]
  • Ground 10: A possession process under Schedule 2 of the Housing Act 1985 that requires service of a Notice of Seeking Possession on secure tenants. [P25]
  • Notice of Seeking Possession: The notice required before Ground 10 possession proceedings against secure tenants. [P25]
  • Gateway 1: Approval for design and technical advisers to begin outline design and planning work. [P31]
  • Resident Project Group: A group of tenants and leaseholders that oversees the works programme and can join contractor and consultant procurement. [P29]
  • Section 20 consultation: Statutory leaseholder consultation. A separately tendered scheme needs two stages, each with a 30 day observation period. [P57]
  • Home loss payment: A payment available only to a tenant who does not return to their original flat. [P24]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That for Abbeyfield Estate: 1. The progress made on achieving vacant possession of Maydew House residents be noted. 2. That the outcome of the option-to-return expression of interest be noted. 3. That the procurement plan and milestones outlined in paragraph 19 of the report be noted. 4. That the proposed programme for the identification of voids for sale outlined in paragraph 20 of the report be noted. 5. That the preparations and progress towards the refurbishment of Maydew House, Damory House and Thaxted Court be noted. 6. That the issuing of Ground 10 notices as part of the notice of seeking possession process as outlined in paragraph 15 of the report be noted. 7. That it be noted that the council is taking active steps to secure the making of a compulsory purchase order. and in addition: 8. That the update on the progress of the Hawkstone and Four Squares estates be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 8 pages

Recommendations

That for Abbeyfield Estate the cabinet:

1. Notes the progress made on achieving vacant possession of Maydew House residents.

2. Notes the outcome of the option-to-return expression of interest.

3. Notes the procurement plan and milestones outlined in paragraph 19.

4. Notes the proposed programme for the identification of voids for sale outlined in paragraph 20.

5. Notes the preparations and progress towards the refurbishment of Maydew House, Damory House and Thaxted Court.

6. Notes the issuing of Ground 10 notices as part of the Notice of Seeking Possession process as outlined in paragraph15.

7. Notes the council is taking active steps to secure the making of a Compulsory Purchase Order.

1 And in addition, the cabinet:

8. Notes the update on the progress of the Hawkstone and Four Squares estates.

BACKGROUND INFORMATION

9. The cabinet considered an update report on the regeneration of the Abbeyfield Estate: Maydew House, Damory House and Thaxted Court on 17 July 2012 and the following decisions were agreed:

• That it be noted that Maydew House tenants who have been rehoused since 9 August 2010 and who qualify for the option to return can choose which flat they return to from the flats available for letting following refurbishment. • That a separate report seeking to make a compulsory purchase order for the acquisition of all interests not within the council’s ownership be brought to cabinet at a later date. • That the proposed development process including identification of void properties for sale, with a concentration in the top eight floors be noted. • That a later procurement for the consultants and contractor to deliver the enhanced refurbishment works as outlined in paragraph 44 of the report (dated 17 July 2012) be noted. • That arrangements for a concierge service on completion of the works programme be worked up separately from the other schemes in the borough in the light of the specific requirements pertaining at Abbeyfield Estate. • That the position for rent charges at Maydew House after refurbishment works are complete be agreed. • That the implications of the implementation of the Southwark Heat Network proposals on the estate be noted. • That the impact of the capital works service charges to leaseholders and the annual service charges to all residents be noted. • That the arrangements for ongoing consultation with residents and the Bede Centre be noted. • That an update report be received in six months on all high investment need estates within Southwark, including Abbeyfield.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Progress report on Abbeyfield Estate Regeneration scheme and update on delivery of Four Squares and Hawkstone EstateReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
CH
Councillor Claire HicksonCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DW
Duncan WhitfieldOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies