Community Infrastructure Levy (CIL) Draft Charging Schedule
AgreedExecutive6 papers
AI summarySouthwark Cabinet agreed to publish the draft CIL schedule and Regulation 123 list and invite representations. The Bakerloo Line extension, excluding land, will be added, and the schedule may proceed to public examination if consultation causes no substantive changes. Projected income is £7m-£8m per year.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedRegulation 123 list also approved for consultation
Money£7m-£8m per yearEstimated income at today’s prices
What happens nextConsultation, then public examinationSubmission follows if no substantive changes
Who it affectsQualifying new developmentCIL funds infrastructure supporting borough growth
What was decided
Cabinet agreed to publish and invite representations on the draft CIL charging schedule and draft Regulation 123 list. The Bakerloo Line extension, excluding land, is to be added to the list.
Cabinet noted the draft infrastructure delivery plan, equalities analysis, consultation plan and consultation report.
Cabinet approved submission of the draft charging schedule to the Planning Inspectorate for public examination, provided consultation produces no substantive changes. Authority to approve minor amendments was delegated to the Director of Planning, in consultation with the cabinet member for regeneration and corporate strategy.
Why
CIL would provide more certainty for infrastructure funding and developers, greater transparency for local people, and a more strategic way to fund infrastructure. From April 2014, more than five section 106 obligations could not be pooled for one infrastructure item. Report P7, P15, P20
The rates were based on borough site viability testing. Most tested residential developments were viable, and proposed charges were below maximum viable levels, supporting continued development and regeneration. Report P34, P40
The equalities analysis found limited impacts on protected groups. Nil office charges outside commercial areas adjoining the river were intended to avoid barriers to jobs and local services. Report P54, P55, P56
What happens next
Publish the documents and invite representations. The council will make them available online and in libraries, advertise in the press and notify mailing list consultees. Report P31
Make the draft Regulation 123 list available for public examination and submit the draft charging schedule to the Planning Inspectorate if consultation causes no substantive changes. Examination was anticipated in summer 2013. Report P24, P51
Authority to approve minor amendments arising from consultation was delegated to the Director of Planning, in consultation with the cabinet member for regeneration and corporate strategy. Subject to a favourable inspector report, adoption was expected by the end of 2013. Report P24
The money
£7m-£8m per year Estimated annual CIL income at today’s prices Report P50
up to 5% of CIL generated Available for monitoring and administering the charge Report P50, P64
£400 per square metre (p/sqm), £250 p/sqm and £50 p/sqm Proposed residential rates across three zones Report P35, P36
from £100 p/sqm to £70 p/sqm Office charge reduction in zone 1 Report P43
£250 p/sqm Supermarkets and shopping centres with parking Report P45
£125 p/sqm All other retail space Report P45
from £50 p/sqm to £30 p/sqm Charge reduction for all other uses Report P49
£35 per square metre Mayoral CIL collected by Southwark Report P12
Options considered
Chosen: Publish and consult on the draft charging schedule and Regulation 123 list. The regulations and Statement of Community Involvement set consultation requirements. Report P2, P25, P31
Chosen: Submit for public examination if consultation causes no substantive changes. The schedule requires consultation, examination and approval before adoption. Report P4, P24, P102
Rejected: Phase in the levy over time. The CIL Regulations do not allow authorities to phase in a levy. Report P40
Rejected: Amalgamate zones 1 and 2 into zone 3 at £250 p/sqm. Average maximum viable CIL differed between the proposed zones, and officers considered the charges justified. Report P39
Rejected: Move Canada Water into the £400 p/sqm zone. Canada Water had a lower average maximum viable CIL than zones 1 and 2. Report P39
Chosen: Retain the three proposed residential rates. Most tested developments were viable and the rates were comfortably below maximum viable charges. Report P40
Chosen: Reduce the zone 1 office charge from £100 p/sqm to £70 p/sqm. Retesting incorporated the Mayor’s Crossrail section 106 tariff and reassessed costs and capital yields. Report P43
Rejected: Differentiate retail charges only by floorspace size. The regulations did not allow distinction solely by size. The revised approach charges specified supermarkets and shopping centres £250 p/sqm and all other retail £125 p/sqm. Report P45
Implications
Financial: CIL was estimated to generate around £7m-£8m per year at today’s prices. It would help fund infrastructure but would not cover the full cost, so other funding would remain necessary. Report P50
Financial: A set share of Southwark CIL must be spent locally: 25% where an adopted neighbourhood plan exists and 15% elsewhere. Report P21
Legal: The charging schedule must be examined and then approved by full council. Once adopted, CIL would apply to most developments adding 100sqm or more floorspace or creating a new residential unit. Affordable housing and specified charitable building developments would be exempt. Report P10, P11, P102
Legal: CIL would replace most, but not all, section 106 income over time. Infrastructure on the Regulation 123 list could not then be funded through section 106 obligations, so the list must avoid double charging. Report P19, P51, P62
Risk: Most tested residential developments were viable and proposed charges were below maximum viable levels. Some sites may still have affordable housing impacts in the first year or two while the market absorbs the new charge. Report P40
Equalities: The analysis found limited impacts on protected groups, but identified possible impacts on small businesses and access to affordable housing. The council will need to monitor the impact of CIL. Report P54, P55, P56, P58, P92
Climate: The Core Strategy 2011 had already undergone sustainability appraisal. The report said a separate CIL appraisal was not required and CIL should not raise additional implications for sustainable development objectives. Report P61
Staffing: Officer time was expected within existing budgeted revenue resources. Significant additional costs would follow the council’s usual approval arrangements. Report P110
Who and where
Developments adding 100sqm or more floorspace or creating a new residential unit Report P10
19 February, 19 March 2012: Draft charging schedule consultation period Report P31
summer 2013: Public examination anticipated Report P24
end of 2013: Charging schedule adoption expected, subject to a favourable report Report P24
10 July and 17 October 2012: Preliminary draft charging schedule consultation period Report P22
5 September and 17 October 2012: Formal consultation within the preliminary draft stage Report P26
14 December 2012: Government CIL statutory guidance issued Report P50, P67
1 February 2013: Final officer report dated Report P116
April 2014: Limit on pooling more than five section 106 obligations takes effect Report P15, P80
Plain English for the jargon
Community Infrastructure Levy: A charge on qualifying new development that funds local infrastructure.
Charging schedule: The document that sets CIL rates and charging zones.
Regulation 123 List: Infrastructure to be funded through CIL rather than section 106 obligations once adopted.
Section 106 planning obligations: Site specific planning requirements or mitigation linked to a development.
Infrastructure Delivery Plan: A living document identifying infrastructure needed to support growth.
Public examination: Independent Planning Inspectorate review of the draft schedule.
Mayoral CIL: The Mayor’s levy for Crossrail, collected by Southwark.
Meaningful proportion: The required share of CIL income spent locally.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15
Resolved
That it be agreed to publish and invite representations on the community infrastructure levy (CIL) draft charging schedule (Appendix A of the report) and the draft “Regulation 123 List” (Appendix B). The Bakerloo Line extension (not including land) to be added to the CIL Regulation 123 list (Appendix B). 2. That the draft infrastructure delivery plan (Appendix C of the report), the equalities analysis (Appendix D), the consultation plan (Appendix E) and consultation report (Appendix F) be noted. 3. That the submission of the community infrastructure levy (CIL) draft charging schedule to the Planning Inspectorate for an examination-in-public be approved, provided no substantive changes are necessary following consultation. 4. That the approval of any minor amendments resulting from consultation on the community infrastructure levy (CIL) draft charging schedule and the draft “Regulation 123 List” be delegated to the director of planning, in consultation with the cabinet member for regeneration and corporate strategy.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 16 pages
Recommendations
That cabinet
1. Agree to publish and invite representations on the community infrastructure levy (CIL) draft charging schedule (Appendix A) and the draft “Regulation 123 List” (Appendix B).
2. Note the draft infrastructure delivery plan (Appendix C), the equalities analysis (Appendix D), the consultation plan (Appendix E) and consultation report (Appendix F).
3. Approve the submission of the community infrastructure levy (CIL) draft charging schedule to the Planning Inspectorate for an examination-in-public, provided no substantive changes are necessary following consultation.
4. Delegate the approval of any minor amendments resulting from consultation on the community infrastructure levy (CIL) draft charging schedule and the draft “Regulation 123 List” to the Director of Planning in consultation with the cabinet Member for Regeneration and Corporate Strategy.
1 BACKGROUND INFORMATION
5. The Community Infrastructure Levy (CIL) is a new levy that local authorities can choose to charge on new developments in their area. The money can be used to support development by funding infrastructure that the council, local community and neighbourhoods want. The benefits are increased certainty for the funding and delivery of infrastructure, increased certainty for developers and increased transparency for local people.
6. The Planning Act 2008 provides that London borough councils are charging authorities for the purposes of the Community Infrastructure Regulations 2010. If intending to apply the levy, charging authorities must produce a document called a charging schedule which sets out the rate for their levy. These rates must be supported by an evidence base including:
• An up-to-date development plan • The area’s infrastructure needs • An overall assessment of the economic viability of new development
7. Once adopted, the levy is a mandatory charge levied on most new developments that involve an increase of 100sqm or more of additional floorspace or that involve the creation of a new residential unit. The charging authority can set one standard rate or it can set specific rates for different areas and types of development. In setting rates, a charging authority is required to strike a reasonable balance between the need to finance infrastructure from CIL against the impact of CIL on the economic viability of development across its area. The charging rates and zones which Southwark is proposing are set out in Appendix A.
8. Some developments are exempt from paying the levy. These are developments of affordable housing and developments by charities of buildings used for charitable purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.