CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Housing and Community Services report back on Decima Street Tenants and Residents Association deputation

Noted Executive 1 paper

AI summaryLondon Borough of Southwark Cabinet noted the Decima Street deputation report. [D] [P1] It proposed capital budget support for additional costs of door entry systems at Decima, Meakin and Elim, with an overall requirement estimated closer to £299,000. [P2] [P9] [P11]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe report set out proposed delivery and funding arrangements [P11]
MoneyRequirement estimated closer to £299,000 [P9]JMB Manager estimate was £255,450 [P9]
What happens nextProposed door entry works programme [P11]The report proposed council and JMB involvement [P11]
Who it affectsDecima, Meakin and Elim residents [P2]Systems were requested for all three estates [P2]

What was decided

Cabinet noted the contents of the report on the Decima Street deputation. Report P1

Why

Leathermarket JMB asked for s106 funding to install door entry systems at Decima, Meakin and Elim. Consultation supported the priority, with proposals to upgrade 52 systems and install 20 new systems on estates meeting defined criteria. Report P2, P6, P7

The scheme had been on a project bank list for s106 funding in 2010. No major new development in the immediate vicinity had come forward, and tighter rules made future funding for door entry systems unlikely. Report P2, P3

Since April 2013, Leathermarket JMB had responsibility for its own ring fenced income and major works, including door entry installation and maintenance. The report therefore proposed capital budget support for additional costs. Report P10, P11

What happens next

The report proposed that the Maintenance and Compliance Team work with Leathermarket JMB to prioritise and programme the works, with capital budget provision for additional costs. Report P11

Leathermarket JMB could provide staffing resources for works in 2013/14, subject to necessary permissions including planning. Report P12

Any extension of the door entry and security budget beyond 2015 would be subject to further approval. Report P8

The money

  • £255,450 The JMB Manager's installation estimate, confirmed as within the expected range. Report P9
  • £299,000 The overall resource requirement was estimated closer to this amount, allowing for contingency and professional fees. Report P9

Options considered

  • Chosen: Note the deputation report. This was the decision recorded by Cabinet. Report P1
  • Rejected: Use s106 funding for the door entry systems. No major new development had come forward, and future s106 funding for door entry systems was considered unlikely. Report P2, P3
  • Rejected: Rely on Leathermarket JMB funding for 2013/14 works. The JMB could not contribute in that financial year because its budget was fully allocated. Report P10, P12

Implications

  • Financial: The report proposed that the capital budget provide the additional cost of the works. Report P11
  • Financial: The JMB could not contribute in 2013/14 because its budget was fully allocated, so it sought the full cost of works from the council. Report P12
  • Financial: The £255,450 installation estimate was within the expected range. Allowing for contingency and professional fees, the requirement was closer to £299,000. Report P9
  • Risk: S106 funding was not forthcoming because no major new development had come forward. Tighter rules also made future availability for door entry systems unlikely. Report P3
  • Risk: Extending the door entry and security budget beyond 2015 depended on further approval. Report P8
  • Legal: Any 2013/14 work by the JMB was subject to necessary permissions, including planning. Report P12
  • Staffing: Leathermarket JMB could provide staffing resources for works in 2013/14, subject to permissions. Report P12
  • Other: The report said the works would improve residents' quality of life and homes, and their sense of safety at home and on the estate. Report P14

Who and where

  • Residents at Decima, Meakin and Elim Report P2
  • Residents on identified estates meeting the defined criteria Report P6, P7
  • Leathermarket JMB Report P10, P11, P12
  • London Borough of Southwark Report P11

Timeline

  • 2010: The scheme was included on a project bank list for s106 funding. Report P2
  • January 2013 and 29 January 2013: The 2013/14 rent setting report went to Area Housing Forums for consideration and was subsequently approved by Cabinet. Report P4
  • 19 March 2013: Leathermarket JMB brought the deputation requesting s106 funding. Report P2
  • Since April 2013: The JMB had responsibility for its own ring fenced income and major works. Report P10
  • 8 April 2013: The report was issued in final version. Report P20
  • May 2013: Consultation results were being finalised for a Cabinet report, after key priorities were due to return for decision. Report P4, P6
  • 2013/14, 2013-2015 and 2014/15: The JMB sought the full cost of works in 2013/14 because its budget was fully allocated. The proposed programme covered upgrading 52 systems and installing 20 new systems in 2013-2015, with possible extension beyond 2015. Work in 2014/15 offered more flexibility. Report P7, P8, P12
  • 2026-05-28: Cabinet noted the contents of the report.

Plain English for the jargon

  • s106 funding: Funding available only when a major new development in the immediate vicinity is permitted, often paid only on completion. [P2] [P3]
  • Leathermarket JMB: The organisation responsible since April 2013 for its own ring fenced income and for major works to stock under a management agreement. [P10] [P11]
  • Area Housing Forums: Forums used to consider the 2013/14 rent setting report in January 2013. [P4]
  • Door entry and security systems: Proposed upgrades to 52 systems and 20 new installations on identified estates meeting defined criteria. [P6] [P7]
  • HRA redirection: Redirecting resources towards identified key housing priorities, including door entry and security systems. [P4] [P6]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

That the contents of the report be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 3 pages

Recommendation

1. That cabinet note the contents off this report.

Background

2. Leathermarket JMB brought a deputation to cabinet on 19 March 2013 requesting s106 funding to install a door entry system at Decima, Meakin and Elim. The scheme was included on a project bank list for s106 funding in 2010.

3. S106 funding is only forthcoming if a major new development is given permission in the immediate vicinity and even then the money often isn't paid until the development is complete. No such development has come forward. Furthermore, the regulations around what we can spend s106 on have tightened and it is unlikely that funding from s106 for door entry systems will be available in the future.

4. The 2013/14 rent setting report was presented to Area Housing Forums in January for consideration and comments and was subsequently approved by cabinet on 29 January 2013. Cabinet recommended that a number of areas identified for HRA redirection of resources into key priorities were of particular importance and should be considered in more detail by Area Forums and be brought back to Cabinet in May 2013 for decision.

KEY ISSUES FOR CONSIDERATION

5. Amongst these key priorities was the provision of door entry and security systems. Consultation has just been completed and the results are being finalised for the Cabinet report in May 2013. Within the proposals there was general support for the priorities identified and the provision of upgrading 52

1 systems and the installation of 20 new systems on identified estates that met the defined criteria against the proposed two year programme for 2013-2015.

6. In addition a number of additional proposals have been put forward through the consultation process that will lead subject to further approval to extending a door entry and security budget beyond 2015.

7. The maintenance and compliance team has examined the estimates of £255,450 provided by the JMB Manager and confirmed they are in a range of what we would expect for an installation of this type. However, projects of this type would normally include a contingency budget and an allowance for professional fees. If included, we estimate the overall resource requirement will be closer to £299,000.

8. Since April 2013, the JMB has been responsible for its own ring-fenced income in order that they better manage and maintain the stock designated to them under the terms of the management agreement and to allow the full implementation of a 30 year asset management strategy.

9. This means that the JMB is responsible for funding any major works, including the installation and maintenance of door entry systems. However the council recognises the prior commitment for the potential funding through s106 it is therefore proposed that the Maintenance and Compliance Team works with the JMB in prioritising and programming the works and that provision is made to provide the addition costs of these works from within the capital budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Housing and Community Services report on Decima Street TRA deputationReport 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
CH
Councillor Claire HicksonCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Housing and Community Services report back on Decima Street Tenants and Residents Association deputationThis decision
  2. Response to the Housing and Community Safety Sub-Committee's Review of Housing Repairs Key Performance IndicatorsNoted
  3. Response to the Housing and Community Safety Sub-Committee's Review of Unfinished Security Works on Four Squares EstateNoted
  4. Updated Response to the Housing and Community Safety Scrutiny Sub-Committee's Review of Housing Repairs Key Performance Indicators (KPIs)Noted
  5. Fire Safety Works at Canada Estate - Report of the Housing and Community Safety Scrutiny Sub-CommitteeNoted
  6. Response to the Housing and Community Safety Scrutiny Sub-Committee on the Fire Safety Works at Canada EstateNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open